[ utilities - public utility - exception – 
electricity - refusal - rights - natural gas - 
effective date –  
  	emergency ] 
 
 
 
 
BE IT ENACTED BY THE PEOPLE OF THE STATE OF OKLAHOMA: 
SECTION 1.     AMENDATORY     17 O.S. 2021, Section 151, as 
amended by Section 1, Chapter 67, O.S.L. 2024 (17 O.S. Supp. 2024, 
Section 151), is amended to read as follows: 
Section 151.  A.  1.  The term "p ublic utility" as used in 
Sections 151 through 155 of this title, shall be taken to mean and 
include every corporation, association, company, individuals, their 
trustees, lessees, or receivers, successors or assigns, except as 
hereinafter provided, and exc ept cities, towns, or other bodies 
politic, that now or hereafter may own, operate, or manage any plant 
or equipment, or any part thereof, directly or indirectly, for   
 
ENGR. H. B. NO. 1374 	Page 2  1 
2 
3 
4 
5 
6 
7 
8 
9 
10 
11 
12 
13 
14 
15 
16 
17 
18 
19 
20 
21 
22 
23 
24 
  
public use, or may supply any commodity to be furnished to the 
public. 
(a) For the conveyance of gas by pipeline. 
(b) For the production, transmission, delivery or 
furnishing of heat or light with gas. 
(c) For the production, transmission, delivery or 
furnishing electric current for light, heat or power. 
(d) For the transportation, delivery or furnishing of 
water for domestic purposes or for power.  Provided 
further that a corporation organized and existing not 
for profit pursuant to Title 18 of the Oklahoma 
Statutes, Sections 851 -863, but for the purpose of 
developing and providing rural water supply and sewage 
disposal facilities to serve rural residents shall not 
be declared a public utility under this act, and shall 
be exempt in any and all respects from the 
jurisdiction and control of the Corporation Commission 
of this state. 
2.  The term "Commission" shall be taken to mean Corporation 
Commission of Oklahoma. 
B.  Provided that: 
1.  In Washington County, where any corporation, association, 
company, individuals, their trustees, lessees, or receivers, 
successors or assigns, is engaged in the pr ivate business of   
 
ENGR. H. B. NO. 1374 	Page 3  1 
2 
3 
4 
5 
6 
7 
8 
9 
10 
11 
12 
13 
14 
15 
16 
17 
18 
19 
20 
21 
22 
23 
24 
  
manufacturing any products other than those hereinbefore defined, 
and in the manufacture of such products operate and maintain private 
electric or water plants for its own power and electrical energy or 
water used in its manufacturing pla nt, without the right of eminent 
domain and without the use of streets, highways or public property, 
it may contract upon terms and prices approved by Corporation 
Commission the sale of a bona fide surplus of electrical energy or 
water developed in such pr ivate plants to any public utility engaged 
in manufacturing and distributing electrical energy in Washington 
County, Oklahoma, without becoming a public utility.  Provided 
further any city or town within a county having a population of over 
five hundred thousand (500,000) or any county having a population of 
over five hundred thousand (500,000), according to the 1970 Federal 
Census, which is a beneficiary of a public trust that has multiple 
beneficiaries and that includes within any or all of its boundaries 
a water supply and/or distribution system, or any portion thereof, 
shall have the authority to condemn all or any portion of any water 
supply and/or distribution system owned and/or operated and/or 
leased by a public trust within the limits of the condemn ing city or 
town or within the unincorporated areas of the condemning county; 
provided the power granted hereunder shall not be exercised until 
the condemning city, town or county shall have made provision to pay 
off all outstanding bonded indebtedness inc urred by the public 
trust, including interest on the bonds to maturity of the bonds, or   
 
ENGR. H. B. NO. 1374 	Page 4  1 
2 
3 
4 
5 
6 
7 
8 
9 
10 
11 
12 
13 
14 
15 
16 
17 
18 
19 
20 
21 
22 
23 
24 
  
first call date, and premium, if any, to which the property to be 
condemned or the revenues therefrom has been pledged for security. 
2.  The the term public utility sha ll not include or be taken to 
mean a corporation, association, company, individuals, their 
trustees, lessees, receivers, successors, or assigns assignees 
engaged in the production of green hydrogen electricity, provided 
that such entity furnishes an electr ic service or commodity only on 
the premises directly to itself, an affiliate, or tenants solely 
engaged in the production of green hydrogen on the premises or 
indirectly by contracting with a public utility, rural electric 
cooperative, or municipality for the purpose of furnishing electric 
service to a specific customer or is an exempt wholesale generator , 
so long as that service or commodity is not resold as retail 
electric service or supplied indirectly or directly for public use .  
Nothing herein shall r elieve such an entity of its obligation to 
comply with state and federal grid interconnection and registration 
requirements and associated costs from the applicable regional 
transmission organization or public utility in the state , nor shall 
it limit any party from asserting a right they may otherwise be 
entitled to under Oklahoma law .  There shall not be a requirement 
nor obligation for a public utility to serve any customer receiving 
electric service from an entity described herein.  Further, it shall 
not limit any party from asserting a right the party may otherwise 
be entitled to under Oklahoma law including filings with the   
 
ENGR. H. B. NO. 1374 	Page 5  1 
2 
3 
4 
5 
6 
7 
8 
9 
10 
11 
12 
13 
14 
15 
16 
17 
18 
19 
20 
21 
22 
23 
24 
  
Commission.  Additionally, any project pursuant to this act shall be 
required to utilize a natural gas component in its power generation 
capacity. 
SECTION 2.  This act shall become effective July 1, 2025. 
SECTION 3.  It being immediately necessary for the preservation 
of the public peace, health or safety, an emergency is hereby 
declared to exist, by re ason whereof this act shall take effect and 
be in full force from and after its passage and approval. 
Passed the House of Representatives the 26th day of March, 2025. 
 
 
 
  
 	Presiding Officer of the House 
 	of Representatives 
 
 
 
Passed the Senate the ___ day of ___________, 2025. 
 
 
 
  
 	Presiding Officer of the Senate