Rhode Island 2025 Regular Session

Rhode Island House Bill H5450 Latest Draft

Bill / Introduced Version Filed 02/12/2025

                             
 
 
 
2025 -- H 5450 
======== 
LC001198 
======== 
S T A T E O F R H O D E I S L A N D 
IN GENERAL ASSEMBLY 
JANUARY SESSION, A.D. 2025 
____________ 
 
A N   A C T 
RELATING TO PUBLIC PROPERTY AND WORKS -- ALL-ELECTRIC BUILDING ACT 
Introduced By: Representatives Handy, Cortvriend, Kislak, Stewart, McGaw, Speakman, 
Boylan, Fogarty, Carson, and Ajello 
Date Introduced: February 12, 2025 
Referred To: House Municipal Government & Housing 
 
 
It is enacted by the General Assembly as follows: 
SECTION 1. Title 37 of the General Laws entitled "PUBLIC PROPERTY AND WORKS" 1 
is hereby amended by adding thereto the following chapter: 2 
CHAPTER 27 3 
ALL-ELECTRIC BUILDING ACT 4 
37-27-1. Short title.     5 
This chapter shall be known and may be cited as the "All-Electric Building Act".  6 
37-27-2. Definitions.     7 
As used in this chapter: 8 
(1) "All-electric building or project" means a building or project that uses a permanent 9 
supply of electricity, as the sole source of energy to meet its building energy needs. An all-electric 10 
building or project shall have no natural gas, propane, or oil heaters, boilers, piping systems, 11 
fixtures or infrastructure installed to meet building energy needs. 12 
(2) "All-electric ready" means a building, project, or portion thereof, that contains electrical 13 
systems and designs that provide sufficient capacity for a future retrofit of a mixed-fuel building to 14 
an all-electric building, including sufficient space, drainage, electrical conductors or raceways, bus 15 
bar capacity, and overcurrent protective devices for such retrofit. The public utilities commission, 16 
in conjunction with the office of housing and community development and the state building code 17 
commission, shall promulgate guidelines for an electric-ready building on or before January 1, 18 
2026. 19   
 
 
LC001198 - Page 2 of 4 
(3) "Building energy needs" means all space conditioning including heating and cooling, 1 
water heating including pools and spas, cooking appliances and clothes drying appliances. 2 
(4) "Mixed-fuel building" means a building that uses a combination of electricity and 3 
natural gas, propane, or oil to meet its building energy needs. For the purposes of this section, 4 
"mixed-fuel building" shall not include buildings that use geothermal or solar energy to meet their 5 
heating and/or cooling building energy needs; provided, however, that are otherwise, all-electric 6 
buildings. 7 
(5) "Mixed-use building" means a building used for both residential and commercial 8 
purposes. 9 
37-27-3. Permits for all-electric buildings.     10 
(a) No city or town shall issue a permit for the construction of any new commercial, 11 
residential, or mixed-use building, that is not an all-electric building, if the initial application for 12 
such permit was submitted after December 31, 2026, unless the circumstances set forth in 13 
subsection (b) or (e) of this section apply. For purposes of this subsection, the initial application 14 
shall be the first site or building permit application, associated with the building or project. 15 
(b) Notwithstanding the provisions of subsection (a) of this section, a city or town may 16 
issue a permit for construction of a new mixed-fuel building upon a finding by the permitting body 17 
of such city or town, that constructing an all-electric building or project is physically or technically 18 
infeasible and that a modification is warranted. Financial considerations shall not be a sufficient 19 
basis to determine physical or technical infeasibility. Modifications shall only be issued under this 20 
exception where the permitting body finds that: 21 
(1) Sufficient evidence was submitted to substantiate the infeasibility of an all-electric 22 
building or project design. Such evidence shall show that the building either: 23 
(i) Cannot satisfy necessary building code requirements, without the usage of gas or oil 24 
piping systems, fixtures and/or infrastructure; or 25 
(ii) If the building is specifically designated for occupancy by a commercial food service 26 
establishment, that such establishment cannot feasibly operate using commercially available all-27 
electric appliances; 28 
(2) The installation of natural gas or oil piping systems, fixtures and/or infrastructure is 29 
strictly limited to the system and area of the building for which an all-electric building or project 30 
design is infeasible; 31 
(3) The area or service within the project where gas or oil piping systems, fixtures and/or 32 
infrastructure are installed, is all-electric ready; and 33 
(4) The project's modified design provides equivalent health, safety and fire protection to 34   
 
 
LC001198 - Page 3 of 4 
an all-electric building or project design. 1 
(c) No local permitting body shall issue building or construction permits that would convert 2 
an all-electric building or project into a mixed-fuel building where the initial application was 3 
submitted after December 31, 2026. 4 
(d) On or before February 1, 2027, the public utilities commission, the office of housing 5 
community development and the state building code commission, shall report jointly to the 6 
governor, the senate president, and the speaker of the house, regarding what changes to electric rate 7 
designs, new or existing subsidy programs, policies, or laws, are necessary to ensure this section 8 
does not diminish the production of affordable housing or the affordability of electricity for 9 
customers in all-electric buildings. For the purpose of this subsection, "affordability of electricity" 10 
means that electricity does not cost more than six percent (6%) of a residential customer's income. 11 
(e) Exemptions. Notwithstanding the provisions of subsection (a) of this section, a city or 12 
town shall issue a permit for new construction, substantial remodel, or rehabilitation of a building 13 
or group of buildings, in which the use of mixed-fuel is used, to meet building energy needs and 14 
said building or group of buildings, are for the sole use as a hospital, medical facility, laboratory 15 
for biological research or restaurant. 16 
SECTION 2. This act shall take effect upon passage. 17 
======== 
LC001198 
========  
 
 
LC001198 - Page 4 of 4 
EXPLANATION 
BY THE LEGISLATIVE COUNCIL 
OF 
A N   A C T 
RELATING TO PUBLIC PROPERTY AND WORKS -- ALL-ELECTRIC BUILDING ACT 
***
This act would provide that no city or town may issue a permit for the construction of new 1 
buildings, that are not an all-electric building, if the initial application for a permit was submitted 2 
after December 31, 2026, unless certain circumstances apply. Exceptions would be granted to 3 
restaurants, hospitals, medical facilities or biolabs. 4 
This act would take effect upon passage. 5 
======== 
LC001198 
========