1312 AN ACT to amend Tennessee Code Annotated, Title 5;
1413 Title 6; Title 7; Title 13; Title 54; Title 65 and Title
1514 68, relative to high energy use facilities.
1615
1716 BE IT ENACTED BY THE GENERAL ASSEMBLY OF THE STATE OF TENNESSEE:
1817 SECTION 1. Tennessee Code Annotated, Title 13, Chapter 7, is amended by adding
1918 the following as a new part:
2019 13-7-701. Definitions.
2120 As used in this section, unless context requires otherwise:
2221 (1) "High energy use facility" or "HEUF" means a project requiring one hundred
2322 megawatts (100 MW) or more of electrical power from an electric utility providing retail
2423 service to the facility, and includes a data center project requiring one hundred
2524 megawatts (100 MW) or more of electrical power from an electric utility providing retail
2625 service to the facility;
2726 (2) "Locality" means a county, municipal, or other local governing body with
2827 jurisdiction over zoning, permitting, regulations, and ordinances;
2928 (2) "Special exception" means a use of real property that is not permitted in a
3029 particular zoning district, except by means of a special use permit, variance, rezoning
3130 application, or other legislative or administrative action; and
3231 (3) "Special use permit" means a permit issued by a locality or state-level
3332 agency that authorizes a special exception.
3433 13-7-702. Site assessments.
3534 (a)
3635
3736
3837 - 2 - 002295
3938
4039 (1) Prior to the approval of a rezoning request, special exception, or special use
4140 permit for the siting of a new HEUF, a locality must require the applicant to perform and
4241 submit a site assessment to examine the sound profile of the HEUF on residential areas
4342 and schools within five hundred feet (500') of the HEUF property.
4443 (2) A locality may require that a site assessment examine the effects of the
4544 proposed HEUF facility on water, agricultural resources, parks, registered historic sites,
4645 and forestland located on the HEUF site or immediately contiguous land.
4746 (3) A locality may request that permitting procedures, if any are required, and
4847 site assessments be conducted with guidance and oversight from the department of
4948 environment and conservation.
5049 (b) Prior to the approval of a rezoning request, special exception, or special use permit
5150 for the siting of a new HEUF, a locality must require the electric utility providing retail service to
5251 the new HEUF to submit a site assessment to the locality describing:
5352 (1) New electric generating units that will be required within the jurisdiction to
5453 serve the project;
5554 (2) New or existing substations that will be used to serve the HEUF; and
5655 (3) The anticipated transmission voltage required to serve the HEUF.
5756 (c) Site assessments submitted to a locality under subsections (a) and (b) must be used
5857 by the locality to assess consistency with the policies of the locality's comprehensive plan and
5958 compliance with the locality's noise ordinances, zoning ordinances, and other applicable laws
6059 and regulations.
6160 (d) This part does not apply to a site with existing local, legislative, or administrative
6261 approval where an applicant is seeking an expansion or modification of an already existing or
6362 approved facility, and such expansion does not exceed an additional one hundred megawatts
6463 (100 MW) or more of electrical power.
6564
6665
6766 - 3 - 002295
6867
6968 (e) This section does not repeal or modify the regulatory authority of any administrative
7069 agency, nor any federal, state, or local law.
7170 (f) This section does not repeal or modify an existing locality's authority to regulate
7271 zoning or permitting, or to issue ordinances within the locality's jurisdiction.
7372 SECTION 2. The headings in this act are for reference purposes only and do not
7473 constitute a part of the law enacted by this act. However, the code commission is requested to
7574 include the headings in any compilation or publication containing this act.
7675 SECTION 3. This act takes effect upon becoming a law, the public welfare requiring it.