7 | 7 | | relating to the requirement for commercially reasonable, long-term |
---|
8 | 8 | | contracts for renewable energy. |
---|
9 | 9 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
10 | 10 | | SECTION 1. Section 39.904, Utilities Code, is amended by |
---|
11 | 11 | | adding Subsection (a-1) to read as follows: |
---|
12 | 12 | | (a-1) To ensure that the goals of Subsection (a) are met, |
---|
13 | 13 | | the commission by rule shall require a retail electric provider, |
---|
14 | 14 | | municipally owned utility, or electric cooperative that purchases |
---|
15 | 15 | | renewable energy to enter into commercially reasonable long-term |
---|
16 | 16 | | contracts for that renewable energy. The commission by rule shall |
---|
17 | 17 | | determine the criteria for the commercial reasonableness of a |
---|
18 | 18 | | contract under this subsection. At a minimum, commission rules |
---|
19 | 19 | | shall require a contract to be for a term of 10 to 15 years. |
---|
20 | 20 | | SECTION 2. The changes in law made by this Act apply only to |
---|
21 | 21 | | a contract for renewable energy that is entered into on or after the |
---|
22 | 22 | | effective date of this Act. A contract that is entered into before |
---|
23 | 23 | | the effective date of this Act is subject to the law in effect on |
---|
24 | 24 | | that date, and that law is continued in effect for that purpose. |
---|
25 | 25 | | SECTION 3. The Public Utility Commission of Texas shall |
---|
26 | 26 | | adopt rules consistent with Section 39.904(a-1), Utilities Code, as |
---|
27 | 27 | | added by this Act, not later than December 1, 2009. |
---|
28 | 28 | | SECTION 4. This Act takes effect September 1, 2009. |
---|