1 | 1 | | 84R4667 AJA-D |
---|
2 | 2 | | By: Workman H.B. No. 1784 |
---|
3 | 3 | | |
---|
4 | 4 | | |
---|
5 | 5 | | A BILL TO BE ENTITLED |
---|
6 | 6 | | AN ACT |
---|
7 | 7 | | relating to damages in an action arising out of a deficiency in the |
---|
8 | 8 | | construction or repair of an improvement to real property. |
---|
9 | 9 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
10 | 10 | | SECTION 1. Chapter 41, Civil Practice and Remedies Code, is |
---|
11 | 11 | | amended by adding Section 41.015 to read as follows: |
---|
12 | 12 | | Sec. 41.015. DAMAGES FOR CONSTRUCTION DEFECT. (a) In this |
---|
13 | 13 | | section, "construction defect" means a deficiency in the |
---|
14 | 14 | | construction or repair of an improvement to real property. |
---|
15 | 15 | | (b) This section applies only to a claim asserted by a |
---|
16 | 16 | | person to recover the actual costs incurred in curing a |
---|
17 | 17 | | construction defect from the person who originally designed, |
---|
18 | 18 | | administered, constructed, or repaired an improvement to real |
---|
19 | 19 | | property. |
---|
20 | 20 | | (c) This section applies to a claim regardless of whether |
---|
21 | 21 | | the claim is asserted by a person who contracted for the |
---|
22 | 22 | | construction or repair. |
---|
23 | 23 | | (d) The amount of actual damages for the cost to cure a |
---|
24 | 24 | | construction defect that might otherwise be awarded in a claim |
---|
25 | 25 | | subject to this section is reduced by 10 percent for each |
---|
26 | 26 | | anniversary of the date of substantial completion of the |
---|
27 | 27 | | construction or repair that occurs before the date the action |
---|
28 | 28 | | asserting the claim is filed. An award of exemplary damages, |
---|
29 | 29 | | multiplied damages, or other damages that is computed on the basis |
---|
30 | 30 | | of the amount awarded as damages for the cost to cure the |
---|
31 | 31 | | construction defect must reflect any reduction of that amount under |
---|
32 | 32 | | this section. |
---|
33 | 33 | | SECTION 2. The change in law made by this Act applies only |
---|
34 | 34 | | to construction or repair of an improvement to real property |
---|
35 | 35 | | commenced on or after the effective date of this Act under a |
---|
36 | 36 | | contract entered into on or after the effective date of this Act. |
---|
37 | 37 | | Construction or repair of an improvement to real property under a |
---|
38 | 38 | | contract entered into before the effective date of this Act is |
---|
39 | 39 | | governed by the law in effect immediately before the effective date |
---|
40 | 40 | | of this Act, and that law is continued in effect for that purpose. |
---|
41 | 41 | | SECTION 3. This Act takes effect September 1, 2015. |
---|