1 | 1 | | 85R21958 JXC-D |
---|
2 | 2 | | By: Oliveira H.B. No. 1665 |
---|
3 | 3 | | Substitute the following for H.B. No. 1665: |
---|
4 | 4 | | By: Geren C.S.H.B. No. 1665 |
---|
5 | 5 | | |
---|
6 | 6 | | |
---|
7 | 7 | | A BILL TO BE ENTITLED |
---|
8 | 8 | | AN ACT |
---|
9 | 9 | | relating to the regulation of cross-border electric generating |
---|
10 | 10 | | facilities. |
---|
11 | 11 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
12 | 12 | | SECTION 1. Subchapter D, Chapter 39, Utilities Code, is |
---|
13 | 13 | | amended by adding Section 39.159 to read as follows: |
---|
14 | 14 | | Sec. 39.159. SWITCHABLE ELECTRIC GENERATING FACILITIES FOR |
---|
15 | 15 | | CROSS-BORDER DISPATCH. (a) In this section: |
---|
16 | 16 | | (1) "Critical load condition" means a temporary |
---|
17 | 17 | | condition on a power grid that requires or may require the |
---|
18 | 18 | | interruption of firm load. |
---|
19 | 19 | | (2) "Mexican power grid" means an electric power grid |
---|
20 | 20 | | in the United Mexican States that is adjacent to the ERCOT power |
---|
21 | 21 | | grid. |
---|
22 | 22 | | (3) "Switchable electric generating facility" means |
---|
23 | 23 | | an electric generating facility that consists of one or more units |
---|
24 | 24 | | that: |
---|
25 | 25 | | (A) are capable of synchronizing with and |
---|
26 | 26 | | dispatching into the ERCOT power grid or the Mexican power grid at |
---|
27 | 27 | | different times; and |
---|
28 | 28 | | (B) can each dispatch into only the ERCOT power |
---|
29 | 29 | | grid or the Mexican power grid at any given time. |
---|
30 | 30 | | (b) Subject to Subsection (c), the commission shall approve |
---|
31 | 31 | | a binding coordination agreement made between the operators of the |
---|
32 | 32 | | ERCOT power grid and the Mexican power grid that governs the |
---|
33 | 33 | | dispatching of energy into the ERCOT power grid and the Mexican |
---|
34 | 34 | | power grid from a new switchable electric generating facility that |
---|
35 | 35 | | is capable of making all generating units available to serve the |
---|
36 | 36 | | ERCOT power grid during an emergency and that is commissioned after |
---|
37 | 37 | | September 1, 2017, if the agreement complies with the requirements |
---|
38 | 38 | | of this section. |
---|
39 | 39 | | (c) The commission may impose reasonable conditions on a |
---|
40 | 40 | | binding coordination agreement to protect the public interest. |
---|
41 | 41 | | (d) The commission shall approve a binding coordination |
---|
42 | 42 | | agreement filed with the commission that complies with the |
---|
43 | 43 | | requirements of this section not later than the 185th day after the |
---|
44 | 44 | | date the agreement is filed. |
---|
45 | 45 | | (e) A binding coordination agreement must: |
---|
46 | 46 | | (1) require that at least 35 percent of the switchable |
---|
47 | 47 | | electric generating facility be committed to serve the ERCOT power |
---|
48 | 48 | | grid to the exclusion of the Mexican power grid during an ERCOT |
---|
49 | 49 | | critical load condition, regardless of conditions on the Mexican |
---|
50 | 50 | | power grid; |
---|
51 | 51 | | (2) provide reasonable assurance that the remaining |
---|
52 | 52 | | nameplate capacity of the switchable electric generating facility |
---|
53 | 53 | | cannot be denied to the operator of the Mexican power grid when the |
---|
54 | 54 | | facility is called on by the operator of the Mexican power grid, |
---|
55 | 55 | | regardless of whether an ERCOT critical load condition exists on |
---|
56 | 56 | | the ERCOT power grid, unless the remaining capacity: |
---|
57 | 57 | | (A) has been offered to the ERCOT power grid and |
---|
58 | 58 | | is selected by the operator of the ERCOT power grid to provide |
---|
59 | 59 | | ancillary services in accordance with Section 35.004(e); or |
---|
60 | 60 | | (B) is otherwise expressly contractually |
---|
61 | 61 | | committed to the operator of the ERCOT power grid; and |
---|
62 | 62 | | (3) provide that the owner of the switchable electric |
---|
63 | 63 | | generating facility is responsible for any penalties imposed on the |
---|
64 | 64 | | operator of the ERCOT power grid by the commission, the Texas |
---|
65 | 65 | | Reliability Entity, the Federal Energy Regulatory Commission, or |
---|
66 | 66 | | the North American Electric Reliability Corporation for any action |
---|
67 | 67 | | taken by the operator of the ERCOT power grid in accordance with |
---|
68 | 68 | | Subdivision (2) if the entity imposing the penalty determines that |
---|
69 | 69 | | a wrongful action of the switchable electric generating facility |
---|
70 | 70 | | caused the violation for which the penalty is imposed. |
---|
71 | 71 | | (f) A binding coordination agreement may limit the |
---|
72 | 72 | | provision of service from a unit to the ERCOT power grid during an |
---|
73 | 73 | | emergency. |
---|
74 | 74 | | SECTION 2. This Act takes effect September 1, 2017. |
---|