1 | 1 | | 85R12219 JXC-F |
---|
2 | 2 | | By: Hall S.B. No. 2098 |
---|
3 | 3 | | |
---|
4 | 4 | | |
---|
5 | 5 | | A BILL TO BE ENTITLED |
---|
6 | 6 | | AN ACT |
---|
7 | 7 | | relating to requirements for underground facility damage |
---|
8 | 8 | | prevention and safety. |
---|
9 | 9 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
10 | 10 | | SECTION 1. Section 251.002(6), Utilities Code, is amended |
---|
11 | 11 | | to read as follows: |
---|
12 | 12 | | (6) "Excavator" means an individual who or legal |
---|
13 | 13 | | entity [a person] that actually excavates or intends to excavate in |
---|
14 | 14 | | this state. |
---|
15 | 15 | | SECTION 2. Subchapter A, Chapter 251, Utilities Code, is |
---|
16 | 16 | | amended by adding Section 251.0045 to read as follows: |
---|
17 | 17 | | Sec. 251.0045. EXCAVATION BY SUBCONTRACTOR. A |
---|
18 | 18 | | subcontractor who performs an excavation operation may not begin |
---|
19 | 19 | | the excavation unless the subcontractor has complied with the |
---|
20 | 20 | | requirements this chapter imposes on an excavator, regardless of |
---|
21 | 21 | | whether the general contractor that hired the subcontractor has |
---|
22 | 22 | | complied with the requirements. |
---|
23 | 23 | | SECTION 3. Section 251.151, Utilities Code, is amended by |
---|
24 | 24 | | amending Subsection (a) and adding Subsection (a-1) to read as |
---|
25 | 25 | | follows: |
---|
26 | 26 | | (a) Except as provided by Sections 251.155 and 251.156, an |
---|
27 | 27 | | excavator [a person] who intends to excavate shall notify a |
---|
28 | 28 | | notification center not earlier than the 14th day before the date |
---|
29 | 29 | | the excavation is to begin [or later than the 48th hour before the |
---|
30 | 30 | | time the excavation is to begin], excluding Saturdays, Sundays, and |
---|
31 | 31 | | legal holidays. An excavator may not excavate: |
---|
32 | 32 | | (1) before 8 a.m. on the third day after the date on |
---|
33 | 33 | | which the excavator gives the notice, excluding Saturdays, Sundays, |
---|
34 | 34 | | and legal holidays; or |
---|
35 | 35 | | (2) after the 21st day after the date on which the |
---|
36 | 36 | | excavator gives the notice, including Saturdays, Sundays, and legal |
---|
37 | 37 | | holidays. |
---|
38 | 38 | | (a-1) If markings made by an operator after notice is given |
---|
39 | 39 | | under Subsection (a) for an excavation operation showing the |
---|
40 | 40 | | location of underground facilities in the excavation area are no |
---|
41 | 41 | | longer visible, are unclear, or are damaged, the excavator shall |
---|
42 | 42 | | give another notice under Subsection (a) for the unfinished |
---|
43 | 43 | | portions of the excavation operation. |
---|
44 | 44 | | SECTION 4. Sections 251.157(a) and (d), Utilities Code, are |
---|
45 | 45 | | amended to read as follows: |
---|
46 | 46 | | (a) Each Class A underground facility operator contacted by |
---|
47 | 47 | | the notification system shall mark the approximate location of its |
---|
48 | 48 | | underground facilities at or near the site of the proposed |
---|
49 | 49 | | excavation if the operator believes that marking the location is |
---|
50 | 50 | | necessary. The operator shall mark the location not later than: |
---|
51 | 51 | | (1) 8 a.m. on the third day following the date on which |
---|
52 | 52 | | the excavator gives to the notification system notice of intent to |
---|
53 | 53 | | excavate under Section 251.151(a) [the 48th hour after the time the |
---|
54 | 54 | | excavator gives to the notification system notice of intent to |
---|
55 | 55 | | excavate], excluding Saturdays, Sundays, and legal holidays; |
---|
56 | 56 | | [(2) 11:59 a.m. on the Tuesday following a Saturday |
---|
57 | 57 | | notification unless the intervening Monday is a holiday; |
---|
58 | 58 | | [(3) 11:59 a.m. on the Wednesday following a Saturday |
---|
59 | 59 | | notification if the intervening Monday is a holiday;] or |
---|
60 | 60 | | (2) [(4)] a time agreed to by the operator and the |
---|
61 | 61 | | excavator. |
---|
62 | 62 | | (d) Not later than 8 a.m. on the third day following the date |
---|
63 | 63 | | on which the excavator gives to the notification system notice of |
---|
64 | 64 | | intent to excavate under Section 251.151(a), excluding Saturdays, |
---|
65 | 65 | | Sundays, and legal holidays [the 48th hour after the time the |
---|
66 | 66 | | excavator gives to the notification center notice of intent to |
---|
67 | 67 | | excavate], an operator contacted by the notification center shall |
---|
68 | 68 | | notify the excavator of the operator's plans to not mark the |
---|
69 | 69 | | proximate location of an underground facility at or near the site of |
---|
70 | 70 | | the proposed excavation. The operator must provide the |
---|
71 | 71 | | notification by e-mail or facsimile or by another verifiable |
---|
72 | 72 | | electronic method approved by the board. |
---|
73 | 73 | | SECTION 5. Section 251.151(b), Utilities Code, is repealed. |
---|
74 | 74 | | SECTION 6. This Act takes effect September 1, 2017. |
---|