5 | 3 | | |
---|
6 | 4 | | |
---|
7 | 5 | | A BILL TO BE ENTITLED |
---|
8 | 6 | | AN ACT |
---|
9 | 7 | | relating to the construction manager-at-risk method of contracting |
---|
10 | 8 | | for governmental construction projects. |
---|
11 | 9 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
12 | 10 | | SECTION 1. Section 2269.255(a), Government Code, is amended |
---|
13 | 11 | | to read as follows: |
---|
14 | 12 | | (a) A construction manager-at-risk shall publicly advertise |
---|
15 | 13 | | for bids or proposals and receive bids or proposals from trade |
---|
16 | 14 | | contractors or subcontractors for the performance of all major |
---|
17 | 15 | | elements of the work other than the minor work that may be included |
---|
18 | 16 | | in the general conditions. Except as otherwise provided by this |
---|
19 | 17 | | subchapter, a construction manager-at-risk shall use the |
---|
20 | 18 | | competitive bidding method or competitive sealed proposal method to |
---|
21 | 19 | | consider a contract with a trade contractor or subcontractor in the |
---|
22 | 20 | | manner required by this chapter for a governmental entity to |
---|
23 | 21 | | consider a contract with a contractor. If a construction |
---|
24 | 22 | | manager-at-risk uses the competitive sealed proposal method to |
---|
25 | 23 | | consider a contract with a trade contractor or subcontractor: |
---|
26 | 24 | | (1) price must be one of the selection criteria; and |
---|
27 | 25 | | (2) the weighted value of price as a selection |
---|
30 | 28 | | SECTION 2. Section 2269.256(a), Government Code, is amended |
---|
31 | 29 | | to read as follows: |
---|
32 | 30 | | (a) The construction manager-at-risk shall review all trade |
---|
33 | 31 | | contractor or subcontractor bids or proposals in a manner that does |
---|
34 | 32 | | not disclose the contents of the bid or proposal during the |
---|
35 | 33 | | selection process to a person not employed by the construction |
---|
36 | 34 | | manager-at-risk, architect, engineer, or governmental entity. All |
---|
37 | 35 | | bids or proposals shall be made available to the governmental |
---|
38 | 36 | | entity [on request] and to the public not later than the seventh day |
---|
39 | 37 | | after the later of the award of the contract or [the seventh day |
---|
40 | 38 | | after] the date of final selection of bids or proposals. |
---|
41 | 39 | | SECTION 3. Sections 2269.255(a) and 2269.256(a), |
---|
42 | 40 | | Government Code, as amended by this Act, apply only in relation to a |
---|
43 | 41 | | contract for which a construction manager-at-risk first advertises |
---|
44 | 42 | | bids or proposals on or after the effective date of this Act. |
---|
45 | 43 | | SECTION 4. This Act takes effect September 1, 2019. |
---|