15 | | - | Sec. 39.159. ELIMINATING EFFECTS OF CERTAIN FEDERAL TAX |
---|
16 | | - | CREDITS. (a) The commission and the ERCOT independent system |
---|
17 | | - | operator shall study potential rules, operating procedures, and |
---|
18 | | - | protocols to eliminate or compensate for any distortion in |
---|
19 | | - | electricity pricing in the ERCOT power region caused by a federal |
---|
20 | | - | tax credit provided under 26 U.S.C. Section 45. The commission |
---|
21 | | - | shall request comments from interested parties as part of the |
---|
22 | | - | study. |
---|
23 | | - | (b) The scope of the study under this section must include |
---|
24 | | - | peak price formation, negative pricing, ancillary services, |
---|
25 | | - | congestion, reserve margins, and transmission and distribution |
---|
26 | | - | costs. |
---|
27 | | - | (c) The commission shall include the results of the study in |
---|
28 | | - | the report required by Section 31.003 to be submitted to the |
---|
29 | | - | legislature before January 15, 2021. |
---|
30 | | - | (d) This section expires September 1, 2021. |
---|
| 13 | + | Sec. 39.159. MARKET DISTORTION RESPONSE. (a) The |
---|
| 14 | + | commission and the ERCOT independent system operator shall adopt |
---|
| 15 | + | rules, operating procedures, and protocols to eliminate or |
---|
| 16 | + | compensate for any distortion in electricity pricing in the ERCOT |
---|
| 17 | + | power region caused by a federal tax credit provided under 26 U.S.C. |
---|
| 18 | + | Section 45. |
---|
| 19 | + | (b) Rules, operating procedures, and protocols adopted |
---|
| 20 | + | under this section must ensure that costs imposed on the system by |
---|
| 21 | + | the sale of electricity that is eligible for a federal tax credit |
---|
| 22 | + | provided under 26 U.S.C. Section 45, including costs of maintaining |
---|
| 23 | + | sufficient capacity to serve load at the summer peak demand caused |
---|
| 24 | + | by the loss of new investment from below-market prices, are paid by |
---|
| 25 | + | the parties that impose the costs. |
---|
| 26 | + | (c) In conjunction with adopting rules, operating |
---|
| 27 | + | procedures, and protocols under this section, the commission and |
---|
| 28 | + | the ERCOT independent system operator shall eliminate any rules, |
---|
| 29 | + | operating procedures, or protocols that attempt to adjust |
---|
| 30 | + | electricity prices to reflect the value of reserves at different |
---|
| 31 | + | reserve levels based on the probability of reserves falling below |
---|
| 32 | + | the minimum contingency level and the value of lost load. |
---|