11 By: Nichols S.B. No. 808
2- (Clardy)
32
43
54 A BILL TO BE ENTITLED
65 AN ACT
76 relating to the construction manager-at-risk method of contracting
87 for governmental construction projects.
98 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
109 SECTION 1. Section 2269.255(a), Government Code, is amended
1110 to read as follows:
1211 (a) A construction manager-at-risk shall publicly advertise
1312 for bids or proposals and receive bids or proposals from trade
1413 contractors or subcontractors for the performance of all major
1514 elements of the work other than the minor work that may be included
1615 in the general conditions. Except as otherwise provided by this
1716 subchapter, a construction manager-at-risk shall use the
1817 competitive bidding method or competitive sealed proposal method to
1918 consider a contract with a trade contractor or subcontractor in the
2019 manner required by this chapter for a governmental entity to
2120 consider a contract with a contractor. If a construction
2221 manager-at-risk uses the competitive sealed proposal method to
2322 consider a contract with a trade contractor or subcontractor:
2423 (1) price must be one of the selection criteria; and
2524 (2) the weighted value of price as a selection
2625 criterion must be 40 percent or more of the total weighted value of
2726 all of the selection criteria.
2827 SECTION 2. Section 2269.256(a), Government Code, is amended
2928 to read as follows:
3029 (a) The construction manager-at-risk shall review all trade
3130 contractor or subcontractor bids or proposals in a manner that does
3231 not disclose the contents of the bid or proposal during the
3332 selection process to a person not employed by the construction
3433 manager-at-risk, architect, engineer, or governmental entity. All
3534 bids or proposals shall be made available to the governmental
3635 entity [on request] and to the public not later than the seventh day
3736 after the later of the award of the contract or [the seventh day
3837 after] the date of final selection of bids or proposals.
3938 SECTION 3. Sections 2269.255(a) and 2269.256(a),
4039 Government Code, as amended by this Act, apply only in relation to a
4140 contract for which a construction manager-at-risk first advertises
4241 bids or proposals on or after the effective date of this Act.
4342 SECTION 4. This Act takes effect September 1, 2019.