Texas 2021 - 87th Regular

Texas House Bill HB4478 Latest Draft

Bill / Introduced Version Filed 03/12/2021

                            87R9632 JXC-F
 By: Huberty H.B. No. 4478


 A BILL TO BE ENTITLED
 AN ACT
 relating to planning and financial responsibility requirements for
 certain aggregate production operations; providing for the
 imposition of an administrative penalty.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  The heading to Chapter 28A, Water Code, is
 amended to read as follows:
 CHAPTER 28A. [REGISTRATION AND INSPECTION OF CERTAIN] AGGREGATE
 PRODUCTION OPERATIONS
 SECTION 2.  Chapter 28A, Water Code, is amended by adding
 Subchapter D to read as follows:
 SUBCHAPTER D. PLANNING AND FINANCIAL RESPONSIBILITY
 Sec. 28A.151.  DEFINITION. In this subchapter, "water body"
 means a navigable watercourse, river, stream, or lake.
 Sec. 28A.152.  APPLICABILITY. This subchapter applies only
 to an aggregate production operation the site of which is located
 not more than 1,500 feet from the San Jacinto River.
 Sec. 28A.153.  RESTORATION PLAN. (a)  In this section,
 "restore" means to change the physical, chemical, or biological
 qualities of a receiving water body in order to return the water
 body to its background condition, including on- and off-site
 stabilization to reduce or eliminate an unauthorized discharge or a
 substantial threat of an unauthorized discharge.
 (b)  The initial application filed by the responsible party
 for the registration of an aggregate production operation must
 include a proposed plan for how the responsible party will restore a
 receiving water body affected by an unauthorized discharge from the
 operation. The responsible party shall update the plan as needed
 with each renewal of the registration of the operation.
 (c)  The restoration plan must:
 (1)  identify receiving water bodies at risk of an
 unauthorized discharge from the aggregate production operation;
 (2)  describe the process to be used in documenting the
 existing physical, chemical, and biological background conditions
 of each of the adjacent receiving water bodies;
 (3)  provide a schedule for completing the
 determination of background conditions of each of the receiving
 water bodies and for updating background conditions in the future,
 as appropriate;
 (4)  identify the goals and objectives of potential
 restoration actions;
 (5)  provide a reasonable range of restoration
 alternatives and the preferred restoration alternative that may be
 implemented to return affected receiving water bodies to background
 conditions in the event of an unauthorized discharge;
 (6)  describe the process for monitoring the
 effectiveness of the preferred restoration action, including
 performance criteria, that will be used to determine the success of
 the restoration or need for interim site stabilization;
 (7)  identify a process for public involvement in the
 selection of the restoration alternative to be implemented to
 restore the receiving water bodies to background conditions; and
 (8)  provide a detailed estimate of the maximum
 probable cost, based on the cost to a third party conducting the
 action without a financial interest or ownership in the operation,
 of completing a restoration action, given the size, location, and
 description of the operation and the nature of the receiving water
 bodies.
 (d)  The responsible party must submit to the commission
 certification of the restoration plan, within the appropriate area
 or discipline, issued by a licensed engineer or licensed
 geoscientist. Components of the restoration plan may be
 independently certified, as appropriate.
 Sec. 28A.154.  RECLAMATION PLAN. (a)  In this section,
 "reclaim" means to use land treatment processes designed to
 minimize degradation of water quality, damage to fish or wildlife
 habitat, erosion, and other adverse effects from aggregate
 production operations and includes backfilling, soil stabilization
 and compacting, grading, erosion control measures, appropriate
 revegetation, or other measures, as appropriate.
 (b)  The initial application filed by the responsible party
 for the registration of an aggregate production operation must
 include a proposed plan for how the responsible party will reclaim
 the area disturbed by the operation. The responsible party shall
 update the plan as needed with each renewal of the registration of
 the operation.
 (c)  The reclamation plan must:
 (1)  provide a description of the proposed use of the
 disturbed area following reclamation;
 (2)  develop site-specific standards for reclamation
 appropriate to the proposed use that address the following:
 (A)  removal or final stabilization of all raw
 material, intermediate material, final product, waste product,
 byproduct, and ancillary material;
 (B)  removal of waste or closure of all waste
 disposal areas;
 (C)  removal of structures, where appropriate;
 (D)  removal and reclamation of all temporary
 roads and railroads;
 (E)  backfilling, regrading, and recontouring;
 (F)  slope stability for remaining highwalls and
 detention ponds;
 (G)  revegetation of the reclaimed area, giving
 consideration to species diversity and the use of native species;
 (H)  establishment of wildlife habitat;
 (I)  establishment of drainage patterns;
 (J)  establishment of permanent control
 structures, such as retention ponds, where necessary to address
 erosion, siltation, and runoff from post-aggregate production and
 reclaimed areas; and
 (K)  removal of all equipment; and
 (3)  provide a description of how reclamation will be
 conducted, such as in phases, and a timetable for the completion of
 reclamation activities.
 (d)  The reclamation plan must include a detailed estimate of
 the maximum probable cost required to complete and implement the
 plan, including inflation costs. The maximum probable cost must be
 based on the cost to a third party conducting the reclamation
 without a financial interest or ownership in the aggregate
 production operation.
 (e)  The responsible party must submit to the commission
 certification of the reclamation plan, within the appropriate area
 or discipline, issued by a licensed engineer or licensed
 geoscientist. Components of the reclamation plan may be
 independently certified, as appropriate.
 Sec. 28A.155.  FINANCIAL RESPONSIBILITY. (a) The
 commission by rule shall require the responsible party for an
 aggregate production operation to establish and maintain, until the
 commission determines that the responsible party has successfully
 complied with all restoration and reclamation requirements of this
 subchapter and the restoration and reclamation plans, evidence of
 financial responsibility for:
 (1)  restoration of a water body affected by an
 unauthorized discharge from the operation; and
 (2)  reclamation of the area disturbed by the
 operation.
 (b)  The amount of financial assurance must be at least the
 amount determined by the executive director of the commission as
 sufficient to meet the requirements of the:
 (1)  restoration plan filed for the aggregate
 production operation under Section 28A.153; and
 (2)  reclamation plan filed for the aggregate
 production operation under Section 28A.154.
 Sec. 28A.156.  PENALTY. The commission may assess a penalty
 of not less than $5,000 and not more than $20,000 for each year in
 which an aggregate production operation operates without
 maintaining the evidence of financial responsibility required by
 Section 28A.155. The total penalty under this section may not
 exceed $40,000 for an aggregate production operation that is
 operated in three or more years without maintaining the evidence of
 financial responsibility.
 Sec. 28A.157.  RECOVERY OF COSTS FOR UNAUTHORIZED
 DISCHARGES. If the commission incurs any costs in undertaking a
 corrective or enforcement action with respect to an unauthorized
 discharge from an aggregate production operation to which this
 subchapter applies, including a reclamation or restoration action,
 the responsible party is liable to the state for all reasonable
 costs of the corrective or enforcement action, including court
 costs and reasonable attorney's fees, and for any punitive damages
 that may be assessed by the court.
 Sec. 28A.158.  AGGREGATE PRODUCTION OPERATION RECLAMATION
 AND RESTORATION FUND ACCOUNT. (a) Penalties and other money
 received by the commission as a result of an enforcement action
 taken under this subchapter, and any gift or grant the commission
 receives for the purposes of this subchapter, shall be deposited in
 the aggregate production operation reclamation and restoration
 fund account in the general revenue fund. Money in the account may
 be appropriated only to the commission for the reclamation and
 restoration of the beds, bottoms, and banks of water bodies
 affected by the unlawful discharges subject to this subchapter.
 (b)  At least 60 days before spending money from the
 reclamation and restoration fund account, the commission shall
 publish notice of its proposed plan and conduct a hearing for the
 purpose of soliciting public comment, oral or written. The
 commission shall fully consider all written and oral submissions on
 the proposed plan.
 (c)  At least 30 days before the date of the public hearing,
 the notice must be published in the Texas Register and in a
 newspaper of general circulation in the county where the violation
 resulting in the payment of the penalties or other money occurred.
 (d)  Interest and other income earned on money in the account
 shall be credited to the account. The account is exempt from the
 application of Section 403.095, Government Code.
 SECTION 3.  (a)  This section applies only to an aggregate
 production operation, as defined by Section 28A.001, Water Code,
 that is registered under Chapter 28A, Water Code, before the
 effective date of this Act.
 (b)  The responsible party for an aggregate production
 operation to which Subchapter D, Chapter 28A, Water Code, as added
 by this Act, applies shall:
 (1)  file the restoration and reclamation plans
 required by that subchapter with the Texas Commission on
 Environmental Quality with the first renewal of the registration of
 the operation that occurs after the effective date of this Act; and
 (2)  establish the evidence of financial
 responsibility required by that subchapter not later than the date
 of the first renewal of the registration of the operation that
 occurs after the effective date of this Act.
 SECTION 4.  This Act takes effect September 1, 2021.