Texas 2021 - 87th Regular

Texas Senate Bill SB1283 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 87R8812 BRG-F
22 By: Hancock S.B. No. 1283
33
44
55 A BILL TO BE ENTITLED
66 AN ACT
77 relating to attachments for broadband service on utility poles
88 owned by an electric cooperative.
99 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
1010 SECTION 1. The heading to Chapter 252, Utilities Code, is
1111 amended to read as follows:
1212 CHAPTER 252. CABLE ATTACHMENTS TO ELECTRIC COOPERATIVE'S
1313 DISTRIBUTION POLES
1414 SECTION 2. Title 5, Utilities Code, is amended by adding
1515 Chapter 253 to read as follows:
1616 CHAPTER 253. BROADBAND ATTACHMENTS TO ELECTRIC COOPERATIVE'S
1717 DISTRIBUTION POLES
1818 SUBCHAPTER A. GENERAL PROVISIONS
1919 Sec. 253.0001. DEFINITIONS. In this chapter:
2020 (1) "Broadband provider" means an entity that provides
2121 broadband service either directly or through an affiliate that uses
2222 the entity's communications facilities, regardless of whether the
2323 entity:
2424 (A) provides additional services in addition to
2525 broadband service; or
2626 (B) uses its facilities in whole or in part to
2727 provide broadband service.
2828 (2) "Broadband service" means Internet service with
2929 the capability of providing:
3030 (A) a download speed of 25 megabits per second or
3131 faster; and
3232 (B) an upload speed of three megabits per second
3333 or faster.
3434 (3) "Communications space" means the lower usable
3535 space on a pole that is typically reserved for low-voltage
3636 communications equipment.
3737 (4) "Large order application" means an application
3838 submitted by a broadband provider under this subchapter requesting
3939 access to attach pole attachments to a number of poles:
4040 (A) that exceeds the lesser of 300 poles or a
4141 number equal to 0.5 percent of the electric cooperative's poles;
4242 and
4343 (B) that is not more than the lesser of 3,000
4444 poles or a number equal to five percent of the electric
4545 cooperative's poles.
4646 (5) "Pole" has the meaning assigned by Section
4747 252.001.
4848 (6) "Pole attachment" means an affixture of cables,
4949 strands, wires, and associated equipment used in the provision of a
5050 broadband provider's services attached to a pole directly or
5151 indirectly or placed in a right-of-way owned or controlled by an
5252 electric cooperative.
5353 (7) "Simple make-ready activities" means work to
5454 accommodate a new pole attachment on a pole and includes work where
5555 existing attachments in the communications space are moved without
5656 any reasonable expectation of:
5757 (A) service outage or facility damage;
5858 (B) a need to splice an existing communications
5959 attachment; or
6060 (C) a need to relocate an existing wireless
6161 attachment.
6262 Sec. 253.0002. APPLICABILITY AND CONSTRUCTION OF CHAPTER.
6363 (a) This chapter applies to a pole attachment affixed by a
6464 broadband provider to a pole owned and controlled by an electric
6565 cooperative. This chapter does not apply to a pole attachment
6666 regulated by the Federal Communications Commission under 47 U.S.C.
6767 Section 224.
6868 (b) This chapter does not abrogate or affect a right or
6969 obligation of a party to a pole attachment contract entered into by
7070 a broadband provider and an electric cooperative before September
7171 1, 2021.
7272 (c) A broadband provider that attaches a pole attachment to
7373 a pole owned by an electric cooperative under the terms of this
7474 chapter is subject to Sections 252.006, 252.007, and 252.008 in the
7575 same manner as if the broadband provider were a cable operator.
7676 (d) This chapter does not limit a right of a party to a pole
7777 attachment contract to request modification, amendment, or renewal
7878 of such contract to conform it to the provisions of this chapter.
7979 Sec. 253.0003. NO STATE CERTIFICATION; NO REGULATORY
8080 AUTHORITY. (a) This chapter does not constitute state
8181 certification under 47 U.S.C. Section 224. If a court determines
8282 that this chapter constitutes certification under that section,
8383 this chapter is not enforceable and has no effect.
8484 (b) This chapter may not be construed to subject an electric
8585 cooperative to regulation by the Federal Communications Commission
8686 under 47 U.S.C. Section 224.
8787 (c) This chapter does not authorize a department, agency, or
8888 political subdivision of this state to exercise enforcement or
8989 regulatory authority over attachments to electric cooperative
9090 poles.
9191 Sec. 253.0004. CONSTRUCTION OF TERMS AND PHRASES.
9292 Technical terms and phrases in this chapter, other than those
9393 defined by Section 253.0001, shall be construed using the term's or
9494 phrase's usual and customary meanings in the electric and broadband
9595 industries.
9696 Sec. 253.0005. COST-BASED NON-RECURRING CHARGES.
9797 Non-recurring charges authorized by this chapter must be
9898 cost-based.
9999 SUBCHAPTER B. APPLICATION FOR ACCESS TO POLES
100100 Sec. 253.0101. APPLICATION FOR POLE ACCESS. (a) A
101101 broadband provider may not access a pole owned by an electric
102102 cooperative for the purpose of placing a pole attachment unless the
103103 provider applies for that access in accordance with this
104104 subchapter.
105105 (b) An electric cooperative shall:
106106 (1) establish a timeline for a broadband provider to
107107 apply for and obtain access to poles for placing a pole attachment
108108 under this chapter; and
109109 (2) make available an explanation of the information
110110 reasonably required for an application for access to poles for
111111 placing a pole attachment under this chapter to be considered
112112 complete.
113113 Sec. 253.0102. REVIEW OF APPLICATION FOR COMPLETENESS. (a)
114114 An electric cooperative shall review an application for
115115 completeness before the cooperative reviews the application on the
116116 merits.
117117 (b) An electric cooperative shall notify an applicant
118118 whether an application is complete not later than:
119119 (1) the 10th business day after the date the
120120 cooperative receives the application;
121121 (2) the 25th business day after the date the
122122 cooperative receives a large order application;
123123 (3) the fifth business day after the date the
124124 cooperative receives a resubmitted application; or
125125 (4) the 20th business day after the date the
126126 cooperative receives a resubmitted large order application.
127127 Sec. 253.0103. TREATMENT OF MULTIPLE APPLICATIONS BY SAME
128128 APPLICANT. For purposes of this chapter, an electric cooperative
129129 may treat as a single application for pole access an application the
130130 cooperative receives from the same applicant before the 31st day
131131 after the cooperative receives that applicant's most recent
132132 previous application.
133133 Sec. 253.0104. GRANT OR DENIAL OF APPLICATION. (a) Except
134134 as provided by Sections 253.0204 and 253.0302, an electric
135135 cooperative shall grant or deny an application for pole access
136136 under this chapter and provide to the applicant a survey of the
137137 poles affected by the application not later than:
138138 (1) the 45th day after the date the cooperative
139139 receives a complete application; or
140140 (2) the 60th day after the date the cooperative
141141 receives a complete large order application.
142142 (b) An electric cooperative may deny an application for
143143 access to a pole under this chapter if:
144144 (1) generally applicable safety, reliability, or
145145 engineering requirements established for the protection of public
146146 health, safety, or welfare prevent granting access; or
147147 (2) the pole lacks sufficient capacity.
148148 (c) Notwithstanding Subsection (b)(1), an electric
149149 cooperative may not deny access to a pole if the capacity, safety,
150150 reliability, or engineering consideration may be remedied by
151151 rearranging, expanding, replacing, or otherwise safely
152152 reengineering the pole or pole attachments through make-ready
153153 activities.
154154 (d) An electric cooperative's denial of an application to
155155 access a pole under this chapter must:
156156 (1) be specific;
157157 (2) include all relevant evidence and information that
158158 supports the denial; and
159159 (3) explain how the evidence and information relate to
160160 the denial.
161161 Sec. 253.0105. DEADLINES NOT APPLICABLE TO CERTAIN
162162 APPLICATIONS. (a) An electric cooperative is not required to meet
163163 the deadlines under this subchapter for an application for pole
164164 access to place pole attachments on more than 3,000 poles or more
165165 than 5 percent of the electric cooperative's poles.
166166 (b) An electric cooperative may not act under Subsection (a)
167167 to delay an application unreasonably and shall negotiate in good
168168 faith with the applicant regarding the time required to fulfill the
169169 cooperative's duties.
170170 SUBCHAPTER C. MAKE-READY ACTIVITIES
171171 Sec. 253.0201. DEADLINES FOR MAKE-READY ACTIVITIES. (a)
172172 Not later than the 15th day after the date an electric cooperative
173173 grants an application, the electric cooperative shall provide to
174174 the broadband provider a detailed and itemized estimate of the
175175 expected costs of all necessary make-ready activities.
176176 (b) An electric cooperative shall complete all make-ready
177177 activities in the communications space and send a detailed,
178178 itemized final invoice to the broadband provider not later than:
179179 (1) the 30th day after the date the electric
180180 cooperative receives payment of the estimated make-ready cost from
181181 the broadband provider; or
182182 (2) for a large order application, the 75th day after
183183 the date the electric cooperative receives payment of the estimated
184184 make-ready cost from the broadband provider.
185185 (c) An electric cooperative shall complete all make-ready
186186 activities above the communications space, including pole
187187 replacements, and send a detailed, itemized final invoice to the
188188 broadband provider not later than:
189189 (1) the 90th day after the date the electric
190190 cooperative receives payment of the estimated make-ready cost from
191191 the broadband provider; or
192192 (2) for a large order application, the 135th day after
193193 the date the electric cooperative receives payment of the estimated
194194 make-ready cost from the broadband provider.
195195 Sec. 253.0202. EXTENSION OF MAKE-READY ACTIVITIES
196196 DEADLINE. (a) An electric cooperative may extend a deadline under
197197 Section 253.0201(b) or (c) for a cause that renders the deadline
198198 infeasible. A cooperative that chooses to extend a deadline shall:
199199 (1) immediately and in writing notify the broadband
200200 provider and each person with an affected existing pole attachment
201201 about the delay; and
202202 (2) identify the affected poles and provide a detailed
203203 explanation of the reason for the delay and an estimated new
204204 completion date to the broadband provider and each person with an
205205 affected existing pole attachment.
206206 (b) An electric cooperative may not extend a deadline under
207207 this section for a period longer than is necessary to complete
208208 make-ready activities on affected poles.
209209 (c) An electric cooperative may not extend a deadline under
210210 this section because of a preexisting violation on an affected pole
211211 caused by a person other than the broadband provider. The
212212 cooperative shall correct a preexisting violation as part of the
213213 make-ready process and before the applicable deadline at the cost
214214 of the responsible person.
215215 (d) An electric cooperative shall resume make-ready
216216 activities without discrimination when the cooperative returns to
217217 routine operations.
218218 Sec. 253.0203. DEADLINES NOT APPLICABLE TO CERTAIN
219219 APPLICATIONS. (a) An electric cooperative is not required to meet
220220 the deadlines under this subchapter for an application to place
221221 pole attachments on more than 3,000 poles or more than five percent
222222 of the electric cooperative's poles.
223223 (b) An electric cooperative may not act under Subsection (a)
224224 to delay an application unreasonably and shall negotiate in good
225225 faith with the applicant regarding the time required to fulfill the
226226 cooperative's duties.
227227 Sec. 253.0204. CONTRACTORS FOR MAKE-READY ACTIVITIES. (a)
228228 A broadband provider may hire a contractor approved by the electric
229229 cooperative to complete a survey under Section 253.0104 or perform
230230 a make-ready activity under this subchapter that is not timely
231231 completed by the electric cooperative or a person with an existing
232232 pole attachment.
233233 (b) The broadband provider shall provide reasonably timely
234234 notice to the electric cooperative and each person with an existing
235235 pole attachment on an affected pole that the provider intends to
236236 hire a contractor as authorized by Subsection (a).
237237 (c) The broadband provider shall provide reasonably timely
238238 notice to the electric cooperative and each person with an existing
239239 pole attachment on an affected pole of the contractor's completion
240240 of the make-ready activities.
241241 (d) An electric cooperative may not act under Subsection (a)
242242 unreasonably to withhold approval of a contractor for purposes of
243243 this section.
244244 (e) Not later than the 90th day after the date a broadband
245245 provider provides notice as provided by Subsection (c), the
246246 cooperative or person may inspect the make-ready work.
247247 (f) Not later than the 14th day after the date that an
248248 electric cooperative or person completes an inspection under
249249 Subsection (e), the cooperative or person may notify the broadband
250250 provider of any damage or code violations caused by such work. The
251251 notice must include specific documentation.
252252 (g) The electric cooperative or person that completes an
253253 inspection may:
254254 (1) remedy any defective make-ready work at the cost
255255 of the broadband provider; or
256256 (2) require the provider to remedy the defect not
257257 later than the 14th day after the provider receives the notice under
258258 Subsection (f).
259259 Sec. 253.0205. LIST OF APPROVED CONTRACTORS. (a) An
260260 electric cooperative shall maintain and make available a list of
261261 approved contractors for work above the communications space and
262262 pole replacements. An electric cooperative may require any work
263263 above the communications space and pole replacements to be
264264 performed by contractors on this list, including work performed by
265265 a contractor hired under Section 253.0204.
266266 (b) An electric cooperative may not act unreasonably to
267267 withhold consent for a requested addition of a qualified contractor
268268 to the list described by Subsection (a).
269269 SUBCHAPTER D. OPTION FOR SIMPLE MAKE-READY ACTIVITIES
270270 Sec. 253.0301. OPTION: SIMPLE MAKE-READY. A broadband
271271 provider may choose to perform simple make-ready activities using
272272 one-touch make-ready procedures in place of the process outlined
273273 under Subchapter C.
274274 Sec. 253.0302. GRANT OR DENIAL OF APPLICATION: SIMPLE
275275 MAKE-READY. (a) A broadband provider that chooses to perform
276276 simple make-ready activities as described by Section 253.0301 must
277277 indicate that choice and describe the work to be performed as part
278278 of the provider's initial application under Subchapter B.
279279 (b) An electric cooperative shall grant or deny an
280280 application for simple make-ready activities under this section not
281281 later than:
282282 (1) the 15th day after the date the cooperative
283283 receives a complete application; or
284284 (2) the 30th day after the date the cooperative
285285 receives a complete large order application.
286286 Sec. 253.0303. SIMPLE MAKE-READY ACTIVITIES PERFORMED BY
287287 CONTRACTOR. (a) If an application for activities under Section
288288 253.0302 is granted, a contractor hired by the broadband provider
289289 shall perform all necessary surveys.
290290 (b) The broadband provider and contractor shall provide a
291291 reasonable opportunity for the electric cooperative and a person
292292 with an existing pole attachment on an affected pole to be present
293293 for any field inspections.
294294 (c) A contractor hired by the broadband provider may perform
295295 all simple make-ready activities. Not later than the 15th day
296296 before the date the contractor begins performing simple make-ready
297297 activities, the contractor shall provide to the electric
298298 cooperative and a person with an existing pole attachment on an
299299 affected pole written notice that:
300300 (1) identifies the contractor performing the
301301 activities; and
302302 (2) sets out reasonable opportunities for the
303303 cooperative and person to be present for the activities.
304304 Sec. 253.0304. INSPECTION OF WORK AND REMEDIATION OF
305305 DAMAGES. (a) A broadband provider immediately shall notify the
306306 electric cooperative and a person with an existing pole attachment
307307 on an affected pole of any damage to the cooperative's or person's
308308 facilities reasonably likely to interrupt the entity's service.
309309 (b) An electric cooperative or person that receives notice
310310 under Subsection (a) may:
311311 (1) complete any remedial work at a reasonable cost to
312312 the broadband provider; or
313313 (2) require the broadband provider immediately to
314314 remedy the damage at the provider's own expense.
315315 (c) Not later than the 15th day after the date a broadband
316316 provider or contractor hired by the provider completes simple
317317 make-ready activities on a pole, the provider shall notify the
318318 electric cooperative and a person with an existing pole attachment
319319 on the pole of the completed work.
320320 (d) Not later than the 90th day after the date an electric
321321 cooperative or person receives notice under Subsection (c), the
322322 cooperative or person may inspect the work. Not later than the 14th
323323 day after the date of the inspection, the cooperative or person may
324324 provide notice to the broadband provider, with specific
325325 documentation, of any damage or code violations caused by the work.
326326 (e) An electric cooperative or person that provides notice
327327 under Subsection (d) may:
328328 (1) remedy any defective make-ready work at the cost
329329 of the broadband provider; or
330330 (2) require the provider to remedy the defect not
331331 later than the 14th day after the date the provider received the
332332 notice under Subsection (d).
333333 SUBCHAPTER E. POLES AND POLE ATTACHMENTS
334334 Sec. 253.0401. DUTIES OF ELECTRIC COOPERATIVE. An electric
335335 cooperative shall rearrange, expand, replace, or otherwise safely
336336 reengineer any pole at the request of a broadband provider whose
337337 application for access to a pole is granted if the change is:
338338 (1) consistent with the National Electrical Safety
339339 Code; and
340340 (2) reasonably necessary to safely accommodate a pole
341341 attachment.
342342 Sec. 253.0402. RECOVERY OF COSTS FOR REPLACING POLES. (a)
343343 If an electric cooperative is required under Section 253.0401 to
344344 replace a pole that has been in service for longer than 75 percent
345345 and less than 100 percent of the average service life of a pole
346346 owned by the cooperative, the cooperative may not require
347347 reimbursement of costs associated with replacing the pole from the
348348 broadband provider that exceed the cooperative's reasonable costs
349349 of advancing the retirement of the existing pole.
350350 (b) The costs under Subsection (a) shall be determined by
351351 adding:
352352 (1) the remaining undepreciated value of the existing
353353 pole;
354354 (2) any interest expense of advancing the replacement
355355 of the pole relative to replacing the pole at the end of the average
356356 service life of a pole owned by the electric cooperative; and
357357 (3) any reasonable incremental cost of increasing the
358358 capacity of the replacement pole relative to the installation cost
359359 of the average new pole installed by the electric cooperative.
360360 (c) If an electric cooperative is required under Section
361361 253.0401 to replace a pole that has been in service for the average
362362 service life of a pole owned by the electric cooperative or longer,
363363 the cooperative may not require reimbursement of costs associated
364364 with replacing the pole from the broadband provider that exceed any
365365 reasonable incremental cost of increasing the capacity of the
366366 replacement pole relative to the installation cost of the average
367367 new pole installed by the electric cooperative.
368368 (d) An electric cooperative shall determine the average
369369 service life of a pole as the period of time during which an
370370 electric cooperative's books maintained for tax and accounting
371371 purposes consider an average pole to have positive value, after
372372 depreciation.
373373 Sec. 253.0403. SHARING COSTS OF MODIFICATION TO POLE. (a)
374374 The following entities must share proportionately in the costs of
375375 modifying a pole under Section 253.0401:
376376 (1) the broadband provider who obtains access to a
377377 pole through a modification to the pole; and
378378 (2) a person who directly benefits from a
379379 modification, including:
380380 (A) the electric cooperative;
381381 (B) a person with an existing attachment on the
382382 pole who adds to or modifies the person's attachment after
383383 receiving notice of the modification; and
384384 (C) a party that makes an attachment to a pole
385385 after the completion of a modification that made the attachment
386386 possible.
387387 (b) This section does not affect the responsibility of the
388388 electric cooperative under Sections 253.0401 and 253.0402.
389389 Sec. 253.0404. EXTENSION ARMS AND TEMPORARY POLE
390390 ATTACHMENTS. (a) A broadband provider may use extension arms and
391391 temporary attachments pending the completion of make-ready
392392 activities if use of extension arms and temporary attachments
393393 complies with the National Electrical Safety Code or other
394394 applicable safety codes.
395395 (b) An electric cooperative may require a broadband
396396 provider to convert a temporary attachment to a permanent
397397 attachment not later than the 60th day after the date of the
398398 completion of make-ready activities and may require the provider to
399399 comply with the National Electrical Safety Code or other
400400 applicable safety codes.
401401 Sec. 253.0405. POLE ATTACHMENT SPECIFICATIONS. (a) A
402402 broadband provider may not be required to meet pole attachment
403403 specifications that exceed the specifications in the National
404404 Electrical Safety Code, applicable fire safety codes, and any
405405 building code or similar code of general applicability for the
406406 protection of public health, safety, or welfare a political
407407 subdivision adopted before the provider submitted an application to
408408 the cooperative.
409409 (b) This section may not be construed to expand the power of
410410 any local government jurisdiction.
411411 Sec. 253.0406. OVERLASHING. (a) A broadband provider with
412412 an existing pole attachment may not be required to obtain advance
413413 approval from an electric cooperative to overlash or permit a third
414414 party to overlash the provider's existing wires.
415415 (b) An electric cooperative may require a broadband
416416 provider to provide notice before and after overlashing. The
417417 cooperative may not require notice before overlashing to be
418418 provided before the 15th day before the date of the overlashing
419419 activities.
420420 (c) An electric cooperative may require a broadband
421421 provider to modify an overlashing proposal to address specific and
422422 identified capacity, safety, reliability, or engineering issues.
423423 The cooperative may not prohibit the provider from overlashing
424424 because of a preexisting violation caused by another person.
425425 (d) An electric cooperative may require a broadband
426426 provider to remedy damage or code violations caused by overlashing
427427 if the electric cooperative:
428428 (1) inspects the overlash not later than the 90th day
429429 after the date the cooperative receives notice that an overlash is
430430 complete; and
431431 (2) informs the provider of the damage or violation
432432 not later than the 14th day after the date of the inspection.
433433 Sec. 253.0407. USE OF POLE ATTACHMENTS FOR MULTIPLE
434434 SERVICES. A broadband provider that attaches a pole attachment
435435 under this chapter may use the attachment for any service delivered
436436 over the provider's facilities, including cable service.
437437 SUBCHAPTER F. POLE ATTACHMENT CONTRACTS
438438 Sec. 253.0501. POLE ATTACHMENT CONTRACTS WITH BROADBAND
439439 PROVIDERS. (a) A broadband provider and an electric cooperative
440440 shall establish the rates, terms, and conditions for pole
441441 attachments by a written pole attachment contract executed by both
442442 parties. The rates, terms, and conditions for attachments by a
443443 broadband provider on an electric cooperative's poles must be just,
444444 reasonable, and nondiscriminatory.
445445 (b) In determining whether rates, terms, and conditions are
446446 just and reasonable, the following factors must be considered:
447447 (1) the interests of and benefits to the consumers and
448448 potential consumers of the electric cooperative's services;
449449 (2) the interests of and benefits to the subscribers
450450 and potential subscribers to broadband services offered through the
451451 pole attachments;
452452 (3) the interests of and benefits to third parties
453453 from the availability of broadband services offered through the
454454 pole attachments;
455455 (4) compliance with the specifications in the National
456456 Electrical Safety Code, applicable fire safety codes, and any
457457 building code or similar code of general applicability for the
458458 protection of public health, safety, or welfare applicable to the
459459 pole attachments; and
460460 (5) the maintenance and reliability of both electric
461461 distribution and broadband services.
462462 (c) A broadband provider and an electric cooperative shall
463463 negotiate a pole attachment contract and any amendment,
464464 modification, or renewal thereof in good faith.
465465 (d) A request to negotiate a new pole attachment contract or
466466 to amend, modify, or renew a contract pertaining to pole
467467 attachments by a broadband provider or an electric cooperative must
468468 be made in writing.
469469 Sec. 253.0502. CONTRACT NEGOTIATIONS AND MEDIATION. (a)
470470 If a broadband provider and an electric cooperative are unable to
471471 agree to a new pole attachment contract before the expiration date
472472 of an existing contract, the rates, terms, and conditions of the
473473 existing contract and the terms and conditions of the electric
474474 cooperative's application and permitting processes remain in
475475 force:
476476 (1) during the 90-day negotiation period described by
477477 Subsection (b) and during the period of any agreed extension;
478478 (2) during the 60-day mediation period described by
479479 Subsection (b) and during the period of any agreed extension; and
480480 (3) pending final disposition of any litigation
481481 commenced under Subsection (c).
482482 (b) If a broadband provider and an electric cooperative are
483483 unable to agree to a new pole attachment contract before the 91st
484484 day after the expiration date of an existing contract, and are
485485 unable to agree to an extension of the negotiation period for a
486486 certain number of days, the broadband provider and electric
487487 cooperative shall attempt to resolve any disagreement over the
488488 rates, terms, or conditions by submitting the contract negotiations
489489 to a mediation process. The mediation process may not extend later
490490 than the 60th day after the end of the initial 90-day negotiation
491491 period and any agreed extension of that period unless the broadband
492492 provider and electric cooperative agree to an extension of the
493493 mediation period for a certain number of days. The mediation
494494 process must be conducted in a county in which the electric
495495 cooperative has distribution poles. The broadband provider and
496496 electric cooperative must share equally the expenses for the
497497 mediator.
498498 (c) If the mediation process under Subsection (b) does not
499499 resolve the disagreement over the rates, terms, or conditions of a
500500 new pole attachment agreement, or if a dispute arises under the
501501 terms of an existing agreement or the requirements of this chapter,
502502 the broadband provider or electric cooperative may file suit in a
503503 district court to resolve the disagreement or dispute, including to
504504 enforce the terms of the agreement or of this chapter.
505505 SECTION 3. This Act takes effect September 1, 2021.