1 | 1 | | 88R4533 ANG-F |
---|
2 | 2 | | By: Darby H.B. No. 1254 |
---|
3 | 3 | | |
---|
4 | 4 | | |
---|
5 | 5 | | A BILL TO BE ENTITLED |
---|
6 | 6 | | AN ACT |
---|
7 | 7 | | relating to certificates of public convenience and necessity for |
---|
8 | 8 | | certain transmission projects. |
---|
9 | 9 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
10 | 10 | | SECTION 1. Section 37.0541, Utilities Code, is amended to |
---|
11 | 11 | | read as follows: |
---|
12 | 12 | | Sec. 37.0541. CONSOLIDATION OF CERTAIN PROCEEDINGS. The |
---|
13 | 13 | | commission shall consolidate the proceeding on an application to |
---|
14 | 14 | | obtain or amend a certificate of convenience and necessity for the |
---|
15 | 15 | | construction of a transmission line with the proceeding on another |
---|
16 | 16 | | application to obtain or amend a certificate of convenience and |
---|
17 | 17 | | necessity for the construction of a transmission line if it is |
---|
18 | 18 | | apparent from the applications or a motion to intervene in either |
---|
19 | 19 | | proceeding that the transmission lines that are the subject of the |
---|
20 | 20 | | separate proceedings share a common point of interconnection. [This |
---|
21 | 21 | | section does not apply to a proceeding on an application for a |
---|
22 | 22 | | certificate of convenience and necessity for a transmission line to |
---|
23 | 23 | | serve a competitive renewable energy zone as part of a plan |
---|
24 | 24 | | developed by the commission under Section 39.904(g)(2).] |
---|
25 | 25 | | SECTION 2. Section 37.056, Utilities Code, is amended by |
---|
26 | 26 | | adding Subsections (a-1), (d-1), (d-2), and (d-3) and amending |
---|
27 | 27 | | Subsection (d) to read as follows: |
---|
28 | 28 | | (a-1) In this section: |
---|
29 | 29 | | (1) "Interzonal" means involving more than one ERCOT |
---|
30 | 30 | | load zone. |
---|
31 | 31 | | (2) "Intrazonal" means involving a single ERCOT load |
---|
32 | 32 | | zone. |
---|
33 | 33 | | (d) The commission by rule shall establish criteria, in |
---|
34 | 34 | | addition to the criteria described by Subsection (c), for granting |
---|
35 | 35 | | a certificate for a transmission project that serves the ERCOT |
---|
36 | 36 | | power region and[,] that is not necessary to meet state or federal |
---|
37 | 37 | | reliability standards[, and that is not included in a plan |
---|
38 | 38 | | developed under Section 39.904(g)]. |
---|
39 | 39 | | (d-1) Except as provided by Subsection (d-2), an |
---|
40 | 40 | | application for a certificate described by Subsection (d) [The |
---|
41 | 41 | | criteria] must include a comparison of the levelized estimated cost |
---|
42 | 42 | | of the transmission project [for consumers] and the levelized |
---|
43 | 43 | | estimated [congestion] cost savings and economic benefits [for |
---|
44 | 44 | | consumers] that may result from the [transmission] project[, |
---|
45 | 45 | | considering both current and future expected congestion levels and |
---|
46 | 46 | | the transmission project's ability to reduce those congestion |
---|
47 | 47 | | levels]. The commission shall include with the commission's |
---|
48 | 48 | | decision to grant or deny the certificate the commission's findings |
---|
49 | 49 | | on the comparison. The comparison must account for: |
---|
50 | 50 | | (1) the probable improvement of service and reduction |
---|
51 | 51 | | of costs for consumers that may be realized from the project; |
---|
52 | 52 | | (2) an estimated value of the reduction in curtailment |
---|
53 | 53 | | costs that may be realized from the project; |
---|
54 | 54 | | (3) an estimation of reduced transmission losses that |
---|
55 | 55 | | may be realized from the project; |
---|
56 | 56 | | (4) an assessment of whether the project will provide |
---|
57 | 57 | | improved access to the ERCOT power grid for new generation |
---|
58 | 58 | | facilities and the benefits that improved access could provide to |
---|
59 | 59 | | generation facilities, industrial load, and the ERCOT market; |
---|
60 | 60 | | (5) an estimation of reduced future transmission |
---|
61 | 61 | | investment costs that may be realized from the project; |
---|
62 | 62 | | (6) an estimation of costs of projects described by |
---|
63 | 63 | | Subsection (d-2) that may be avoided as a result of the project; and |
---|
64 | 64 | | (7) an estimation of direct economic benefits that may |
---|
65 | 65 | | be realized from the construction of the project [The commission |
---|
66 | 66 | | shall include with its decision on an application for a certificate |
---|
67 | 67 | | to which this subsection applies findings on the criteria]. |
---|
68 | 68 | | (d-2) If an application does not include a comparison |
---|
69 | 69 | | described by Subsection (d-1), the commission may not grant a |
---|
70 | 70 | | certificate for a project described by Subsection (d) unless the |
---|
71 | 71 | | commission finds that the project is needed to support a reliable |
---|
72 | 72 | | and adequate transmission network, to facilitate wholesale |
---|
73 | 73 | | competition, or to minimize curtailments due to interzonal |
---|
74 | 74 | | constraints and intrazonal congestion. |
---|
75 | 75 | | (d-3) Not less than once per year, the independent |
---|
76 | 76 | | organization certified under Section 39.151 for the ERCOT power |
---|
77 | 77 | | region shall identify pending applications for transmission |
---|
78 | 78 | | projects that will meet commission findings under Subsection (d-2). |
---|
79 | 79 | | SECTION 3. Section 39.904(k), Utilities Code, is amended to |
---|
80 | 80 | | read as follows: |
---|
81 | 81 | | (k) The commission and the independent organization |
---|
82 | 82 | | certified for ERCOT shall study the need for increased transmission |
---|
83 | 83 | | and generation capacity throughout this state and report to the |
---|
84 | 84 | | legislature the results of the study and any recommendations for |
---|
85 | 85 | | legislation. The report must be filed with the legislature not |
---|
86 | 86 | | later than December 31 of each even-numbered year [and may be filed |
---|
87 | 87 | | as a part of the report required by Subsection (j)]. |
---|
88 | 88 | | SECTION 4. Subchapter Z, Chapter 39, Utilities Code, is |
---|
89 | 89 | | amended by adding Section 39.919 to read as follows: |
---|
90 | 90 | | Sec. 39.919. CRITICAL DESIGNATION TRANSMISSION |
---|
91 | 91 | | INFRASTRUCTURE PROJECTS. (a) In this section: |
---|
92 | 92 | | (1) "Interzonal" means involving more than one ERCOT |
---|
93 | 93 | | load zone. |
---|
94 | 94 | | (2) "Intrazonal" means involving a single ERCOT load |
---|
95 | 95 | | zone. |
---|
96 | 96 | | (b) Not later than December 30, 2023, the independent |
---|
97 | 97 | | organization certified under Section 39.151 for the ERCOT power |
---|
98 | 98 | | region shall: |
---|
99 | 99 | | (1) identify, in consultation with the commission, |
---|
100 | 100 | | critical designation transmission infrastructure projects and the |
---|
101 | 101 | | transmission and distribution utilities that will construct and |
---|
102 | 102 | | operate the projects in a manner consistent with Section 37.056; |
---|
103 | 103 | | and |
---|
104 | 104 | | (2) submit a written description of each project to |
---|
105 | 105 | | the commission. |
---|
106 | 106 | | (c) Projects identified under Subsection (b) must |
---|
107 | 107 | | facilitate a timely and targeted expansion of the electric power |
---|
108 | 108 | | grid in ERCOT for the purposes of: |
---|
109 | 109 | | (1) resolving existing interzonal and intrazonal |
---|
110 | 110 | | transmission constraints, congestion, or curtailments, including |
---|
111 | 111 | | generic transmission constraints; and |
---|
112 | 112 | | (2) ensuring the future reliability of the ERCOT |
---|
113 | 113 | | electric power grid. |
---|
114 | 114 | | (d) To the extent practicable, projects identified under |
---|
115 | 115 | | Subsection (b) should: |
---|
116 | 116 | | (1) be cost-effective and designed to transmit high |
---|
117 | 117 | | volumes of electricity in and across ERCOT load zones efficiently; |
---|
118 | 118 | | (2) minimize the need for the acquisition of new |
---|
119 | 119 | | rights-of-way by replacing aging infrastructure or following |
---|
120 | 120 | | routes that align with existing rights-of-way or existing |
---|
121 | 121 | | transmission infrastructure; |
---|
122 | 122 | | (3) minimize interzonal constraints and intrazonal |
---|
123 | 123 | | congestion during construction activities; |
---|
124 | 124 | | (4) be designed to accommodate new solutions, |
---|
125 | 125 | | including higher voltages, if the independent organization |
---|
126 | 126 | | determines that new solutions are required; and |
---|
127 | 127 | | (5) be designed to significantly reduce present or |
---|
128 | 128 | | expected future interzonal constraints and intrazonal congestion. |
---|
129 | 129 | | (e) The independent organization certified under Section |
---|
130 | 130 | | 39.151 for the ERCOT power region shall identify as a critical |
---|
131 | 131 | | designation transmission infrastructure project under Subsection |
---|
132 | 132 | | (b) a project addressing an interzonal constraint or intrazonal |
---|
133 | 133 | | congestion in an area if: |
---|
134 | 134 | | (1) the constraint or congestion has been present for |
---|
135 | 135 | | three years or longer; and |
---|
136 | 136 | | (2) the area has experienced constraint or congestion |
---|
137 | 137 | | costs greater than or equal to $100 million per year in each of the |
---|
138 | 138 | | previous three years. |
---|
139 | 139 | | (f) The independent organization certified under Section |
---|
140 | 140 | | 39.151 for the ERCOT power region may consult with the independent |
---|
141 | 141 | | organization's market participant segments and other stakeholders |
---|
142 | 142 | | to identify projects under Subsection (b) that could facilitate: |
---|
143 | 143 | | (1) the growth of the economy of this state; or |
---|
144 | 144 | | (2) oil and gas, commercial, and industrial |
---|
145 | 145 | | development that could provide substantial new tax revenue, |
---|
146 | 146 | | landowner income, or new jobs in this state. |
---|
147 | 147 | | (g) Not later than the 450th day after the date that the |
---|
148 | 148 | | independent organization certified under Section 39.151 for the |
---|
149 | 149 | | ERCOT power region submits a written description of a project to the |
---|
150 | 150 | | commission under Subsection (b), the utility that will construct |
---|
151 | 151 | | and operate the project shall submit to the commission an |
---|
152 | 152 | | application for a certificate of public convenience and necessity |
---|
153 | 153 | | for the project. |
---|
154 | 154 | | (h) In considering an application for a certificate of |
---|
155 | 155 | | public convenience and necessity for a project identified under |
---|
156 | 156 | | Subsection (b), the commission is not required to consider the |
---|
157 | 157 | | factors provided by Sections 37.056(c)(1) and (2). The commission |
---|
158 | 158 | | shall consider all factors provided by Section 37.056, including |
---|
159 | 159 | | Sections 37.056(c)(1) and (2), for a project not identified under |
---|
160 | 160 | | Subsection (b). |
---|
161 | 161 | | (i) If the commission issues a certificate of public |
---|
162 | 162 | | convenience and necessity for a project identified under Subsection |
---|
163 | 163 | | (b), the commission shall find that the project is used and useful |
---|
164 | 164 | | to the utility in providing service for purposes of this section, |
---|
165 | 165 | | prudent, and includable in the rate base, regardless of the extent |
---|
166 | 166 | | of the utility's actual use of the project. |
---|
167 | 167 | | (j) Transmission service that is facilitated through a |
---|
168 | 168 | | project identified under Subsection (b) must be provided in a |
---|
169 | 169 | | manner consistent with Subchapter A, Chapter 35. |
---|
170 | 170 | | (k) This section expires September 1, 2032. |
---|
171 | 171 | | SECTION 5. Sections 39.904(g), (h), (i), and (j), Utilities |
---|
172 | 172 | | Code, are repealed. |
---|
173 | 173 | | SECTION 6. The changes in law made by this Act apply only to |
---|
174 | 174 | | a proceeding affecting a certificate of public convenience and |
---|
175 | 175 | | necessity that commences on or after the effective date of this Act. |
---|
176 | 176 | | A proceeding affecting a certificate of public convenience and |
---|
177 | 177 | | necessity that commenced before the effective date of this Act is |
---|
178 | 178 | | governed by the law in effect on the date the proceeding is |
---|
179 | 179 | | commenced, and that law is continued in effect for that purpose. |
---|
180 | 180 | | SECTION 7. The recovery of a transmission facility |
---|
181 | 181 | | investment made by an electric utility to serve a competitive |
---|
182 | 182 | | renewable energy zone is governed by the law in effect on the date |
---|
183 | 183 | | the facility is placed in service, regardless of whether the |
---|
184 | 184 | | facility is completed before, on, or after the effective date of |
---|
185 | 185 | | this Act, and that law is continued in effect for that purpose. |
---|
186 | 186 | | SECTION 8. This Act takes effect September 1, 2023. |
---|