Texas 2023 - 88th Regular

Texas House Bill HB5297 Compare Versions

OldNewDifferences
11 88R14140 JXC-D
22 By: Bryant H.B. No. 5297
33
44
55 A BILL TO BE ENTITLED
66 AN ACT
77 relating to the interconnection of the ERCOT power grid to grids
88 outside the ERCOT power region.
99 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
1010 SECTION 1. Subtitle B, Title 2, Utilities Code, is amended
1111 by adding Chapter 39A to read as follows:
1212 CHAPTER 39A. INTERCONNECTION OF FACILITIES IN ERCOT TO GRIDS
1313 OUTSIDE ERCOT POWER REGION
1414 Sec. 39A.0101. UTILITY AND COOPERATIVE AUTHORITY.
1515 Notwithstanding any other law, a transmission and distribution
1616 utility, municipally owned utility, or electric cooperative that
1717 transmits or distributes power purchased at wholesale in the ERCOT
1818 power region may construct, own, and operate facilities as
1919 necessary to:
2020 (1) access transmission service from outside of the
2121 ERCOT power region; and
2222 (2) purchase power at wholesale from outside of the
2323 ERCOT power region.
2424 Sec. 39A.0102. COMMISSION AUTHORITY. (a) The commission
2525 may request any federal approval necessary for the interconnection
2626 of a facility described by Section 39A.0101.
2727 (b) Unless otherwise provided by federal law, the
2828 commission shall require the independent organization certified
2929 for the ERCOT power region under Section 39.151 to approve the
3030 interconnection of a facility described by Section 39A.0101 unless
3131 the commission or the independent organization determines that the
3232 interconnection poses a significant and imminent risk to public
3333 health and safety.
3434 (c) The commission may provide technical and administrative
3535 assistance to a transmission and distribution utility, municipally
3636 owned utility, or electric cooperative seeking to construct, own,
3737 or operate a facility described by Section 39A.0101.
3838 (d) The commission may approve wholesale electricity
3939 transactions between entities in the ERCOT power region and
4040 entities outside the ERCOT power region.
4141 Sec. 39A.0103. SYNCHRONOUS AND NON-SYNCHRONOUS
4242 INTERCONNECTIONS. (a) This chapter applies to synchronous and
4343 non-synchronous interconnections.
4444 (b) Unless otherwise provided by federal law, the
4545 commission shall approve an application for a certificate of
4646 convenience and necessity submitted under Section 39A.0104 by a
4747 transmission and distribution utility, municipally owned utility,
4848 or electric cooperative for a facility that would synchronously
4949 interconnect to a facility outside the ERCOT power region if the
5050 application complies with all applicable provisions of Chapter 37
5151 and this chapter.
5252 SECTION 2. Sections 37.051(c-1), (c-2), and (c-3),
5353 Utilities Code, are redesignated as Section 39A.0104, Utilities
5454 Code, and amended to read as follows:
5555 Sec. 39A.0104. CERTIFICATES OF CONVENIENCE AND NECESSITY.
5656 (a) A transmission and distribution utility, [(c-1)
5757 Notwithstanding any other provision of this title except Section
5858 11.009, and except as provided by Subsection (c-2), a person,
5959 including an electric utility or] municipally owned utility, or
6060 electric cooperative may not interconnect a facility described by
6161 Section 39A.0101 [to the ERCOT transmission grid that enables
6262 additional power to be imported into or exported out of the ERCOT
6363 power grid] unless the utility or cooperative [person] obtains a
6464 certificate from the commission in the manner provided by Chapter
6565 37 and this chapter stating that the interconnection does not pose a
6666 significant and imminent risk to public health and safety [public
6767 convenience and necessity requires or will require the
6868 interconnection].
6969 (b) In the case of a conflict between Chapter 37 and this
7070 chapter, this chapter prevails.
7171 (c) Sections 37.056(c)(1) and (2) and (d) do not apply to an
7272 application for a certificate described by Subsection (a).
7373 (d) Unless otherwise provided by federal law, the
7474 commission shall approve an application for a certificate described
7575 by Subsection (a) unless the commission determines that granting
7676 the application poses a significant and imminent risk to public
7777 health and safety.
7878 (e) The transmission and distribution utility, municipally
7979 owned utility, or electric cooperative [person] must apply to the
8080 commission for a [the] certificate described by Subsection (a) not
8181 later than the 180th day before the date the utility or cooperative
8282 [person] seeks any order from the Federal Energy Regulatory
8383 Commission related to the interconnection.
8484 (f) [The commission shall apply Section 37.056 in
8585 considering an application under this subsection. In addition, the
8686 commission must determine that the application is consistent with
8787 the public interest before granting the certificate. The commission
8888 may adopt rules necessary to implement this subsection. This
8989 subsection does not apply to a facility that is in service on
9090 December 31, 2014.
9191 [(c-2)] The commission, not later than the 185th day after
9292 the date the application is filed, shall approve an application
9393 [filed under Subsection (c-1)] for a facility that is to be
9494 constructed under an interconnection agreement appended to an offer
9595 of settlement approved in a final order of the Federal Energy
9696 Regulatory Commission that was issued in Docket No. TX11-01-001 on
9797 or before December 31, 2014, directing physical connection between
9898 the ERCOT and SERC regions under Sections 210, 211, and 212 of the
9999 Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In
100100 approving the application, the commission may prescribe reasonable
101101 conditions to protect the public interest that are consistent with
102102 the final order of the Federal Energy Regulatory Commission.
103103 (g) [(c-3)] Nothing in this section [Subsection (c-1) or
104104 (c-2)] is intended to restrict the authority of the commission or
105105 the independent organization certified under Section 39.151 for the
106106 ERCOT power region to adopt rules or protocols of general
107107 applicability.
108108 SECTION 3. (a) It is the intent of the legislature that the
109109 ERCOT power region become synchronously interconnected to other
110110 power regions not later than December 31, 2030.
111111 (b) Not later than October 1, 2024, the Public Utility
112112 Commission of Texas shall examine the laws and rules governing the
113113 entities and facilities described by Section 39A.0101, Utilities
114114 Code, as added by this Act, and submit a report to the legislature
115115 with recommendations for legislative and administrative action
116116 needed to facilitate the interconnection of facilities in the ERCOT
117117 power region with other power regions.
118118 (c) Not later than October 1, 2024, the comptroller of
119119 public accounts shall conduct a study on the costs to the public and
120120 this state of the power outages that occurred as a result of Winter
121121 Storm Uri. The study must include an estimate of the average cost
122122 per household in the ERCOT power region and a comparison of those
123123 costs to costs incurred by households in other states that
124124 experienced power outages from Winter Storm Uri.
125125 SECTION 4. This Act takes effect September 1, 2023.