 By: Bell of Kaufman H.B. No. 3290




 A BILL TO BE ENTITLED
 AN ACT
 relating to the time period for which certain funds payable under a
 construction contract must be reserved for the benefit of
 mechanic's lien claimants.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 53.101, Property Code, is amended by
 amending Subsection (a) and adding Subsection (a-1) to read as
 follows:
 (a)  During the progress of work under an original contract
 for which a mechanic's lien may be claimed and for the period
 described by Subsection (a-1) [30 days after the work under the
 contract is completed], the owner shall reserve:
 (1)  10 percent of the contract price of the work to the
 owner; or
 (2)  10 percent of the value of the work, measured by
 the proportion that the work done bears to the work to be done,
 using the contract price or, if there is no contract price, using
 the reasonable value of the completed work.
 (a-1)  After the completion of work under an original
 contract for which a mechanic's lien may be claimed, the owner shall
 reserve the funds described by Subsection (a) for a period ending
 the earlier of:
 (1)  the 31st day after the date the work under the
 contract is completed; or
 (2)  the 61st day after the date:
 (A)  a certificate of occupancy is issued for the
 improvement; or
 (B)  the improvement is first used for its
 intended purpose.
 SECTION 2.  The changes in law made by this Act apply only to
 a contract entered into on or after the effective date of this Act.
 A contract entered into before the effective date of this Act is
 governed by the law as it existed immediately before the effective
 date of this Act, and that law is continued in effect for that
 purpose.
 SECTION 3.  This Act takes effect September 1, 2025.