Texas 2025 - 89th Regular

Texas House Bill HB4091 Latest Draft

Bill / Introduced Version Filed 03/07/2025

Download
.pdf .doc .html
                            89R8612 JXC-D
 By: Anchía H.B. No. 4091




 A BILL TO BE ENTITLED
 AN ACT
 relating to the interconnection of the ERCOT power grid to grids
 outside the ERCOT power region.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 31.002(5), Utilities Code, is amended to
 read as follows:
 (5)  "Electric Reliability Council of Texas" or "ERCOT"
 means:
 (A)  the area in Texas served by electric
 utilities, municipally owned utilities, and electric cooperatives
 that is not synchronously interconnected with electric utilities
 outside the state; or
 (B)  if the commission approves a synchronous
 interconnection under Chapter 39A, an area designated by the
 commission by rule as necessary to administer this subtitle.
 SECTION 2.  Subtitle B, Title 2, Utilities Code, is amended
 by adding Chapter 39A to read as follows:
 CHAPTER 39A. INTERCONNECTION OF FACILITIES IN ERCOT TO GRIDS
 OUTSIDE ERCOT POWER REGION
 Sec. 39A.0101.  UTILITY AND COOPERATIVE AUTHORITY.
 Notwithstanding any other law, a transmission and distribution
 utility, municipally owned utility, or electric cooperative that
 transmits or distributes power purchased at wholesale in the ERCOT
 power region may construct, own, and operate facilities as
 necessary to:
 (1)  interconnect transmission facilities inside the
 ERCOT power region to transmission facilities outside of the ERCOT
 power region; and
 (2)  purchase power at wholesale from outside of the
 ERCOT power region.
 Sec. 39A.0102.  SALE AUTHORITY.  Notwithstanding any other
 law, an electric utility, electric cooperative, municipally owned
 utility, or power generation company operating in this state may
 sell electric energy at wholesale for retail sale inside or outside
 the ERCOT power region for the purposes of this chapter.
 Sec. 39A.0103.  COMMISSION AUTHORITY. (a) The commission
 may request any federal approval necessary for the synchronous or
 nonsynchronous interconnection of a facility described by Section
 39A.0101.
 (b)  The commission may require the independent organization
 certified for the ERCOT power region under Section 39.151 to
 approve the synchronous or nonsynchronous interconnection of a
 facility described by Section 39A.0101 unless otherwise provided by
 federal law or the commission or the independent organization
 determines that the interconnection poses a significant and
 imminent risk to public health and safety.
 (c)  The commission may provide technical and administrative
 assistance to a transmission and distribution utility, municipally
 owned utility, or electric cooperative seeking to construct, own,
 or operate a facility described by Section 39A.0101.
 (d)  The commission shall implement, and shall provide to the
 Federal Energy Regulatory Commission, the Electric Reliability
 Organization as defined by 16 U.S.C. Section 824o, and the
 independent organization certified under Section 39.151 for the
 ERCOT power region any assistance necessary to implement, a
 reliability standard for the purposes of this chapter that requires
 minimum total transfer capabilities between the ERCOT power region
 and other regions as follows:
 (1)  4.3 gigawatts between the area under functional
 control of the independent organization and the area under
 functional control of the Southwest Power Pool;
 (2)  2.5 gigawatts between the area under functional
 control of the independent organization and the area under
 functional control of Midcontinent Independent System Operator;
 and
 (3)  2.6 gigawatts between the area under functional
 control of the independent organization and the Western
 Interconnection.
 (e)  The commission shall designate one or more entities
 described by Section 39A.0101 to site and construct new
 transmission facilities or modify existing transmission facilities
 to achieve the minimum total transfer capabilities described by
 Subsection (d) or delegate authority to the independent
 organization certified under Section 39.151 for the ERCOT power
 region to designate the entities.
 (f)  Notwithstanding any other law, the commission may
 require an entity designated under Subsection (e) to make requests,
 obtain approvals, enter into contracts, and construct or modify
 facilities as necessary to interconnect a transmission facility
 with a facility outside of ERCOT.
 SECTION 3.  Sections 37.051(c-1), (c-2), and (c-3),
 Utilities Code, are redesignated as Section 39A.0104, Utilities
 Code, and amended to read as follows:
 Sec. 39A.0104.  CERTIFICATES OF CONVENIENCE AND NECESSITY.
 (a) A transmission and distribution utility, [(c-1)
 Notwithstanding any other provision of this title except Section
 11.009, and except as provided by Subsection (c-2), a person,
 including an electric utility or] municipally owned utility, or
 electric cooperative may not interconnect a facility to the ERCOT
 transmission grid that enables additional power to be imported into
 or exported out of the ERCOT power grid unless the utility or
 cooperative [person] obtains a certificate from the commission in
 the manner provided by Chapter 37 and this chapter stating that the
 interconnection does not pose a significant and imminent risk to
 public health and safety [public convenience and necessity requires
 or will require the interconnection].
 (b)  In the case of a conflict between Chapter 37 and this
 chapter, this chapter prevails.
 (c)  Sections 37.056(c)(1) and (2) and (d) do not apply to an
 application for a certificate described by Subsection (a).
 (d)  The commission may approve an application for a
 certificate described by Subsection (a) unless otherwise provided
 by federal law or the commission determines that granting the
 application poses a significant and imminent risk to public health
 and safety.
 (e)  The transmission and distribution utility, municipally
 owned utility, or electric cooperative [person] must apply to the
 commission for a [the] certificate described by Subsection (a) not
 later than the 180th day before the date the utility or cooperative
 [person] seeks any order from the Federal Energy Regulatory
 Commission related to the interconnection.
 (f) [The commission shall apply Section 37.056 in
 considering an application under this subsection. In addition, the
 commission must determine that the application is consistent with
 the public interest before granting the certificate. The commission
 may adopt rules necessary to implement this subsection. This
 subsection does not apply to a facility that is in service on
 December 31, 2014.
 [(c-2)] The commission, not later than the 185th day after
 the date the application is filed, shall approve an application
 [filed under Subsection (c-1)] for a facility that is to be
 constructed under an interconnection agreement appended to an offer
 of settlement approved in a final order of the Federal Energy
 Regulatory Commission that was issued in Docket No. TX11-01-001 on
 or before December 31, 2014, directing physical connection between
 the ERCOT and SERC regions under Sections 210, 211, and 212 of the
 Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In
 approving the application, the commission may prescribe reasonable
 conditions to protect the public interest that are consistent with
 the final order of the Federal Energy Regulatory Commission.
 (g) [(c-3)] Nothing in this section [Subsection (c-1) or
 (c-2)] is intended to restrict the authority of the commission or
 the independent organization certified under Section 39.151 for the
 ERCOT power region to adopt rules or protocols of general
 applicability.
 SECTION 4.  This Act takes effect September 1, 2025.