2 | 4 | | |
---|
3 | 5 | | |
---|
4 | 6 | | A BILL TO BE ENTITLED |
---|
5 | 7 | | AN ACT |
---|
6 | 8 | | relating to the reliability of the ERCOT power grid. |
---|
7 | 9 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
8 | 10 | | SECTION 1. Section 39.1591, Utilities Code, is amended to |
---|
9 | 11 | | read as follows: |
---|
10 | 12 | | Sec. 39.1591. REPORT ON DISPATCHABLE AND NON-DISPATCHABLE |
---|
11 | 13 | | GENERATION FACILITIES. Not later than December 1 of each year, the |
---|
12 | 14 | | commission shall file a report with the legislature that: |
---|
13 | 15 | | (1) includes: |
---|
14 | 16 | | (A) the estimated annual costs incurred by |
---|
15 | 17 | | load-serving entities and generation facilities under this |
---|
16 | 18 | | subchapter associated with backing up dispatchable and |
---|
17 | 19 | | non-dispatchable electric generation facilities to guarantee that |
---|
18 | 20 | | a firm amount of electric energy will be available to the ERCOT |
---|
19 | 21 | | power grid; and |
---|
20 | 22 | | (B) as calculated by the independent system |
---|
21 | 23 | | operator, the cumulative annual costs that have been incurred in |
---|
22 | 24 | | the ERCOT market to facilitate the transmission of dispatchable and |
---|
23 | 25 | | non-dispatchable electricity to load and to interconnect |
---|
24 | 26 | | transmission level loads, including a statement of the total |
---|
25 | 27 | | cumulative annual costs and of the cumulative annual costs incurred |
---|
26 | 28 | | for each type of activity described by this paragraph; [and] |
---|
27 | 29 | | (2) documents the status of the implementation of this |
---|
28 | 30 | | subchapter, including whether the rules and protocols adopted to |
---|
29 | 31 | | implement this subchapter have materially improved the |
---|
30 | 32 | | reliability, resilience, and transparency of the electricity |
---|
31 | 33 | | market; and |
---|
32 | 34 | | (3) recommends any additional legislative measures |
---|
33 | 35 | | necessary to ensure that market signals are adequate to preserve |
---|
34 | 36 | | existing dispatchable generation and incentivize the construction |
---|
35 | 37 | | of new dispatchable generation capacity sufficient to meet the |
---|
36 | 38 | | reliability requirements adopted under Section 39.159 for at least |
---|
37 | 39 | | five years from the date of the report. |
---|
38 | 40 | | SECTION 2. Section 39.1592, Utilities Code, is amended to |
---|
39 | 41 | | read as follows: |
---|
40 | 42 | | Sec. 39.1592. GENERATION RELIABILITY REQUIREMENTS. (a) |
---|
41 | 43 | | This section applies only to an electric generation facility in the |
---|
42 | 44 | | ERCOT power region that is subject to [for which] a standard |
---|
43 | 45 | | generator interconnection agreement, [ is signed on or after |
---|
44 | 46 | | January 1, 2027, that]has been in operation for at least one year, |
---|
45 | 47 | | and [that] is not a self-generator. |
---|
46 | 48 | | (a-1) For the purposes of this section, a generation |
---|
47 | 49 | | facility is considered to be non-dispatchable if the facility's |
---|
48 | 50 | | output is controlled primarily by forces outside of human control. |
---|
49 | 51 | | (b) Not later than December 1 of each year, an owner or |
---|
50 | 52 | | operator of a non-dispatchable [an electric] generation facility [, |
---|
51 | 53 | | other than a battery energy storage resource,] shall demonstrate to |
---|
52 | 54 | | the commission the ability of the facility to ensure that during at |
---|
53 | 55 | | least 95 hours of the highest 100 net load hours to occur in the next |
---|
54 | 56 | | calendar year the facility's hourly availability factor, as |
---|
55 | 57 | | determined under Subsection (b-1), will equal or exceed the |
---|
56 | 58 | | facility's expected availability factor, as determined under |
---|
57 | 59 | | Subsection (b-2). |
---|
58 | 60 | | (b-1) The commission shall determine a non-dispatchable |
---|
59 | 61 | | generation facility's hourly availability factor by dividing the |
---|
60 | 62 | | facility's hourly average generation by the facility's installed |
---|
61 | 63 | | capacity. |
---|
62 | 64 | | (b-2) The commission shall determine a non-dispatchable |
---|
63 | 65 | | generation facility's expected availability factor by calculating |
---|
64 | 66 | | the average generation of the facility, divided by the facility's |
---|
65 | 67 | | installed capacity, during the highest 100 net load hours each |
---|
66 | 68 | | calendar year in an average of two or more immediately preceding |
---|
67 | 69 | | calendar years, [owner or operator's portfolio to operate or be |
---|
68 | 70 | | available to operate when called on for dispatch at or above the |
---|
69 | 71 | | seasonal average generation capability during the times of highest |
---|
70 | 72 | | reliability risk, as determined by the commission, due to low |
---|
71 | 73 | | operation reserves,] as determined by the commission. |
---|
72 | 74 | | (b-3) The owner or operator may [must be allowed to] meet |
---|
73 | 75 | | the performance requirements described by this section |
---|
74 | 76 | | [subsection] only by operating, constructing, or acquiring |
---|
75 | 77 | | resources that are eligible to act as ancillary service reserves |
---|
76 | 78 | | according to the protocols of the independent organization |
---|
77 | 79 | | certified for the ERCOT power region under Section 39.151 |
---|
78 | 80 | | [supplementing or contracting with on-site or off-site resources, |
---|
79 | 81 | | including battery energy storage resources. The commission shall |
---|
80 | 82 | | determine the average generation capability based on expected |
---|
81 | 83 | | resource availability and seasonal-rated capacity on a standalone |
---|
82 | 84 | | basis]. |
---|
83 | 85 | | (c) The commission shall require the independent |
---|
84 | 86 | | organization certified under Section 39.151 for the ERCOT power |
---|
85 | 87 | | region to: |
---|
86 | 88 | | (1) enforce the requirements of this section |
---|
87 | 89 | | [Subsection (b)] by imposing financial penalties, as determined by |
---|
88 | 90 | | the commission, for failing to comply with the performance |
---|
89 | 91 | | requirements described by this section [that subsection]; and |
---|
90 | 92 | | (2) provide financial incentives, as determined by the |
---|
91 | 93 | | commission, for exceeding the performance requirements described |
---|
92 | 94 | | by this section [that subsection]. |
---|
93 | 95 | | (d) The independent organization certified under Section |
---|
94 | 96 | | 39.151 for the ERCOT power region may not impose penalties under |
---|
95 | 97 | | Subsection (c): |
---|
96 | 98 | | (1) for resource unavailability due to planned |
---|
97 | 99 | | maintenance outages or transmission outages; or |
---|
98 | 100 | | (2) on resources that are already subject to |
---|
99 | 101 | | performance obligations [during the highest reliability risk |
---|
100 | 102 | | hours] under the day-ahead market rules or other ancillary or |
---|
101 | 103 | | reliability services established by the commission or the |
---|
102 | 104 | | independent organization[; or |
---|
103 | 105 | | [(3) during hours outside a baseline established by |
---|
104 | 106 | | the commission that includes morning and evening ramping periods]. |
---|
105 | 107 | | (e) The commission by rule may establish an ancillary |
---|
106 | 108 | | service market or a separate reliability service to implement this |
---|
107 | 109 | | section. |
---|
108 | 110 | | SECTION 3. The owner or operator of a generation facility to |
---|
109 | 111 | | which Section 39.1592(b), Utilities Code, as amended by this Act, |
---|
110 | 112 | | applies shall make the first demonstration required by that section |
---|
111 | 113 | | not later than December 1, 2026. |
---|
112 | 114 | | SECTION 4. This Act takes effect September 1, 2025. |
---|