1 | 1 | | 89R3396 CS-D |
---|
2 | 2 | | By: Guillen H.B. No. 5633 |
---|
3 | 3 | | |
---|
4 | 4 | | |
---|
5 | 5 | | |
---|
6 | 6 | | |
---|
7 | 7 | | A BILL TO BE ENTITLED |
---|
8 | 8 | | AN ACT |
---|
9 | 9 | | relating to the operation of Texas backup power packages. |
---|
10 | 10 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
11 | 11 | | SECTION 1. Section 34.0204, Utilities Code, is amended to |
---|
12 | 12 | | read as follows: |
---|
13 | 13 | | Sec. 34.0204. TEXAS BACKUP POWER PACKAGES. (a) The |
---|
14 | 14 | | commission may use money in the Texas energy fund without further |
---|
15 | 15 | | appropriation to provide a grant or loan for the operation of a |
---|
16 | 16 | | Texas backup power package that: |
---|
17 | 17 | | (1) is engineered to minimize operation costs; |
---|
18 | 18 | | (2) uses interconnection technology and controls that |
---|
19 | 19 | | enable immediate islanding from the power grid and stand-alone |
---|
20 | 20 | | operation for the host facility; |
---|
21 | 21 | | (3) is capable of operating for at least 96 [48] |
---|
22 | 22 | | continuous hours without refueling or connecting to a separate |
---|
23 | 23 | | power source; and |
---|
24 | 24 | | (4) is designed so that one or more Texas backup power |
---|
25 | 25 | | packages can be aggregated on-site to serve not more than eight |
---|
26 | 26 | | [2.5] megawatts of load at the host facility[; |
---|
27 | 27 | | [(5) provides power sourced from: |
---|
28 | 28 | | [(A) a combination of natural gas or propane with |
---|
29 | 29 | | photovoltaic panels and battery storage; or |
---|
30 | 30 | | [(B) battery storage on an electric school bus; |
---|
31 | 31 | | and |
---|
32 | 32 | | [(6) is not used by the owner or host facility for the |
---|
33 | 33 | | sale of energy or ancillary services]. |
---|
34 | 34 | | (b) An owner or host facility of a Texas backup power |
---|
35 | 35 | | package for which a grant or loan is provided under this chapter |
---|
36 | 36 | | that sells energy or ancillary services from the package is not |
---|
37 | 37 | | required to register with the commission as a power generation |
---|
38 | 38 | | company under Section 39.351 if the package has a generation |
---|
39 | 39 | | capacity of not more than 2,000 kilowatts. |
---|
40 | 40 | | SECTION 2. The change in law made by this Act to Section |
---|
41 | 41 | | 34.0204(a)(3), Utilities Code, applies only to a Texas backup power |
---|
42 | 42 | | package for which a grant or loan is issued on or after the |
---|
43 | 43 | | effective date of this Act. |
---|
44 | 44 | | SECTION 3. This Act takes effect September 1, 2025. |
---|