1 | | - | By: Nichols, Creighton S.B. No. 1413 |
---|
2 | | - | (In the Senate - Filed February 19, 2025; March 6, 2025, |
---|
3 | | - | read first time and referred to Committee on Water, Agriculture and |
---|
4 | | - | Rural Affairs; April 15, 2025, reported adversely, with favorable |
---|
5 | | - | Committee Substitute by the following vote: Yeas 7, Nays 0; |
---|
6 | | - | April 15, 2025, sent to printer.) |
---|
7 | | - | Click here to see the committee vote |
---|
8 | | - | COMMITTEE SUBSTITUTE FOR S.B. No. 1413 By: Hancock |
---|
| 1 | + | 89R10822 ANG-D |
---|
| 2 | + | By: Nichols S.B. No. 1413 |
---|
26 | | - | section and is entitled to that release. |
---|
27 | | - | (b-1) This section applies only if the landowner's property |
---|
28 | | - | is located in: |
---|
29 | | - | (1) a county with a population of at least 1.2 million; |
---|
30 | | - | (2) [,] a county adjacent to a county with a population |
---|
31 | | - | of at least 1.2 million; |
---|
32 | | - | (3) [, or] a county with a population of more than |
---|
33 | | - | 200,000 and less than 233,500 that does not contain a public or |
---|
34 | | - | private university that had a total enrollment in the most recent |
---|
35 | | - | fall semester of 40,000 or more; or |
---|
36 | | - | (4) a county adjacent to a county described by |
---|
37 | | - | Subdivision (2)[, and not in a county that has a population of more |
---|
38 | | - | than 50,500 and less than 52,000]. |
---|
39 | | - | (b-2) This subsection applies only to a petition for a tract |
---|
40 | | - | of land located in a county described by Subsection (b-1)(4). The |
---|
41 | | - | petitioner shall provide written notice, by certified mail and |
---|
42 | | - | regular mail, to the certificate holder of the petitioner's intent |
---|
43 | | - | to petition the utility commission for expedited release of an area |
---|
44 | | - | from a certificate of public convenience and necessity under this |
---|
45 | | - | section not later than the 60th day before the date on which the |
---|
46 | | - | petitioner submits the petition to the utility commission. The |
---|
47 | | - | notice must include contact information for the property owner |
---|
48 | | - | whose tract or tracts are the subject of the petition. The |
---|
49 | | - | certificate holder may waive the notice required by this |
---|
50 | | - | subsection. |
---|
51 | | - | (b-3) [(b-1)] On the day a petitioner submits a petition to |
---|
52 | | - | the utility commission under this section, the petitioner shall |
---|
53 | | - | send, via certified mail, a copy of the petition to the certificate |
---|
54 | | - | holder, who may submit information to the utility commission to |
---|
55 | | - | controvert information submitted by the petitioner. |
---|
56 | | - | (e) The certificate holder may not initiate an application |
---|
57 | | - | to borrow money under a federal loan program after the date the |
---|
58 | | - | notice is provided or waived under Subsection (b-2) [petition is |
---|
59 | | - | filed] until the utility commission issues a decision on the |
---|
60 | | - | petition. |
---|
| 20 | + | section and is entitled to that release if the landowner's property |
---|
| 21 | + | is located in a county with a population of at least 1.2 million, a |
---|
| 22 | + | county adjacent to a county with a population of at least 1.2 |
---|
| 23 | + | million, [or] a county with a population of more than 200,000 and |
---|
| 24 | + | less than 233,500 that does not contain a public or private |
---|
| 25 | + | university that had a total enrollment in the most recent fall |
---|
| 26 | + | semester of 40,000 or more, or a county adjacent to a county |
---|
| 27 | + | adjacent to a county with a population of at least 1.2 million [and |
---|
| 28 | + | not in a county that has a population of more than 50,500 and less |
---|
| 29 | + | than 52,000]. |
---|
70 | | - | (f) If the utility commission determines that compensation |
---|
71 | | - | to the certificate holder is owed under this section and Section |
---|
72 | | - | 13.254(g), the [The] utility commission shall [may] require an |
---|
73 | | - | award of compensation to be paid by the petitioner to the |
---|
74 | | - | certificate holder [in the manner provided by this section]. If the |
---|
75 | | - | utility commission requires an award of compensation, the utility |
---|
76 | | - | commission shall require the petitioner to submit a report to the |
---|
77 | | - | utility commission verifying for the purposes of Subsection (j) |
---|
78 | | - | that the compensation has been paid to the certificate holder. |
---|