1 | 1 | | 2025S0155-1 02/28/25 |
---|
2 | 2 | | By: Parker S.B. No. 1942 |
---|
3 | 3 | | |
---|
4 | 4 | | |
---|
5 | 5 | | |
---|
6 | 6 | | |
---|
7 | 7 | | A BILL TO BE ENTITLED |
---|
8 | 8 | | AN ACT |
---|
9 | 9 | | relating to electricity planning for large loads. |
---|
10 | 10 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
11 | 11 | | SECTION 1. Subchapter D, Chapter 39, Utilities Code, is |
---|
12 | 12 | | amended by adding Section 39.169 to read as follows: |
---|
13 | 13 | | Sec. 39.169. LARGE LOAD INTERCONNECTION; RELIABILITY |
---|
14 | 14 | | PROGRAM. (a) In this section, "behind-the-meter generation" means |
---|
15 | 15 | | a new generation facility on the retail customer's side of the |
---|
16 | 16 | | meter. |
---|
17 | 17 | | (b) The commission by rule shall require the independent |
---|
18 | 18 | | organization certified under Section 39.151 for the ERCOT power |
---|
19 | 19 | | region to develop and implement an interconnection program to |
---|
20 | 20 | | provide an expedited interconnection process for operators of large |
---|
21 | 21 | | loads who agree to cease consuming energy from the power grid |
---|
22 | 22 | | through deployment of their behind-the-meter generation when |
---|
23 | 23 | | directed to by the independent organization. The program must be |
---|
24 | 24 | | available only to large loads that are a facility at a single site |
---|
25 | 25 | | with an aggregate peak power demand that exceeds a demand threshold |
---|
26 | 26 | | established by the independent organization. The threshold must be |
---|
27 | 27 | | at least 75 megawatts unless the independent organization |
---|
28 | 28 | | determines that a lower threshold will better ensure reliability in |
---|
29 | 29 | | the ERCOT power region. |
---|
30 | 30 | | (c) The program must require the independent organization |
---|
31 | 31 | | certified under Section 39.151 for the ERCOT power region and the |
---|
32 | 32 | | relevant electric cooperative, municipally owned utility, or |
---|
33 | 33 | | transmission and distribution utility to give priority to a large |
---|
34 | 34 | | load in the interconnection queue participating in the program. |
---|
35 | 35 | | (d) The program must provide that: |
---|
36 | 36 | | (1) an interconnection application for a |
---|
37 | 37 | | participating large load with behind-the-meter generation that |
---|
38 | 38 | | agrees to offer the energy generated by the behind-the-meter |
---|
39 | 39 | | generation to the power grid at times directed by the independent |
---|
40 | 40 | | organization or reduce its energy consumption from the power grid |
---|
41 | 41 | | to a minimum level established by the independent organization will |
---|
42 | 42 | | be given priority over other interconnection applications that are |
---|
43 | 43 | | pending before the independent organization and the relevant |
---|
44 | 44 | | electric cooperative, municipally owned utility, or transmission |
---|
45 | 45 | | and distribution utility, including any applications from other |
---|
46 | 46 | | participating large loads without behind-the-meter generation; |
---|
47 | 47 | | (2) if applicable, the generator interconnection |
---|
48 | 48 | | application for a participating large load's behind-the-meter |
---|
49 | 49 | | generation will be processed in parallel with the load |
---|
50 | 50 | | interconnection application; and |
---|
51 | 51 | | (3) an applicant for participation in the program may |
---|
52 | 52 | | choose: |
---|
53 | 53 | | (A) if authorized by the independent |
---|
54 | 54 | | organization and the relevant electric cooperative, municipally |
---|
55 | 55 | | owned utility, or transmission and distribution utility, to |
---|
56 | 56 | | contract with a vendor approved by the relevant electric |
---|
57 | 57 | | cooperative, municipally owned utility, or transmission and |
---|
58 | 58 | | distribution utility or by the independent organization to perform |
---|
59 | 59 | | all studies required by the relevant electric cooperative, |
---|
60 | 60 | | municipally owned utility, or transmission and distribution |
---|
61 | 61 | | utility before the approval of the interconnection application; |
---|
62 | 62 | | (B) to procure equipment required for the |
---|
63 | 63 | | interconnection in accordance with technical specifications |
---|
64 | 64 | | provided by the relevant electric cooperative, municipally owned |
---|
65 | 65 | | utility, or transmission and distribution utility; and |
---|
66 | 66 | | (C) to construct interconnection facilities in |
---|
67 | 67 | | accordance with technical and other requirements of the relevant |
---|
68 | 68 | | electric cooperative, municipally owned utility, or transmission |
---|
69 | 69 | | and distribution utility. |
---|
70 | 70 | | (e) The program shall provide that studies required by an |
---|
71 | 71 | | electric cooperative, municipally owned utility, or transmission |
---|
72 | 72 | | and distribution utility before the approval of an interconnection |
---|
73 | 73 | | application for a participating large load may evaluate the load as |
---|
74 | 74 | | non-firm. |
---|
75 | 75 | | SECTION 2. This Act takes effect September 1, 2025. |
---|