5-VIRGINIA ACTS OF ASSEMBLY -- CHAPTER
5+25107870D
66
7-An Act to amend the Code of Virginia by adding in Article 1 of Chapter 22 of Title 15.2 a section numbered 15.2-2209.4, relating to siting of data centers; site assessment; high energy use facility.
7+HOUSE BILL NO. 1601
88
9-[H 1601]
9+AMENDMENT IN THE NATURE OF A SUBSTITUTE
1010
11-Approved
11+(Proposed by the Joint Conference Committee
12+
13+on February 21, 2025)
14+
15+(Patron Prior to SubstituteDelegate Thomas)
16+
17+A BILL to amend the Code of Virginia by adding in Article 1 of Chapter 22 of Title 15.2 a section numbered 15.2-2209.4, relating to siting of data centers; site assessment; high energy use facility.
18+
19+
1220
1321 Be it enacted by the General Assembly of Virginia:
1422
1523 1. That the Code of Virginia is amended by adding in Article 1 of Chapter 22 of Title 15.2 a section numbered 15.2-2209.4 as follows:
1624
1725 15.2-2209.4. Siting of data centers; site assessment.
1826
1927 A. As used in this section, "high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.
2028
2129 B. Prior to any approval of a rezoning application, special exception, or special use permit for the siting of a new HEUF, a locality shall require that an applicant perform and submit a site assessment to examine, to the extent practicable and within the timeline provided by subdivision A 7 of 15.2-2286, the sound profile of the HEUF on residential units and schools located within 500 feet of the HEUF property boundary. A locality may also require that a site assessment examine, to the extent practicable and within the timeline provided by subdivision A 7 of 15.2-2286, the effect of the proposed facility on (i) ground and surface water resources, (ii) agricultural resources, (iii) parks, (iv) registered historic sites, and (v) forestland on the HEUF site or immediately contiguous land.
2230
2331 C. Prior to any approval of a rezoning application, special exception, or special use permit for the siting of a new HEUF, a locality shall require that the electric utility providing retail service to the new HEUF, to the extent known and practicable and within the timeline provided by subdivision A 7 of 15.2-2286, submit to the locality a form describing (i) any new or existing substations that will be used to serve the HEUF and (ii) the anticipated transmission voltage required to serve the HEUF.
2432
2533 D. Site assessments submitted to a locality under subsections B and C shall be used by the locality to assess consistency with the policies of the locality's comprehensive plan, if any, and compliance with the locality's adopted noise ordinances, zoning ordinance provisions, and other applicable laws and regulations, if any.
2634
2735 E. A locality's site assessment regarding an HEUF shall not be construed to change, replace, or impact any authority or jurisdiction of the State Corporation Commission, or otherwise delegate any of the State Corporation Commission's authority or jurisdiction to any locality.
2836
2937 F. This section shall not apply to a site with an existing legislative or administrative approval where an applicant is seeking an expansion or modification of an already existing or approved facility and such expansion does not exceed an additional 100 megawatts or more of electrical power.
3038
3139 G. Nothing in this section shall be construed to prohibit, limit, or otherwise supersede existing local zoning authority.