Wisconsin 2023-2024 Regular Session

Wisconsin Assembly Bill AB1164 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 LRB-3739/1
22 JPC:skw
33 2023 - 2024 LEGISLATURE
44 2023 ASSEMBLY BILL 1164
55 March 22, 2024 - Introduced by Representative BROOKS. Referred to Committee on
66 State Affairs.
77 AN ACT relating to: expenditure of $213,302.77 from the general fund in
88 payment of a claim against the state made by JRT Top Notch Roofs, LLC.
99 Analysis by the Legislative Reference Bureau
1010 This bill directs the expenditure of $213,302.77 from the general fund in
1111 payment of a claim against the Department of Administration by JRT Top Notch
1212 Roofs, LLC.  The claimant entered into a contract with DOA to replace the roof of
1313 Esker Hall at the University of Wisconsin-Whitewater.  The claimant asserts that
1414 the bid documents stated that the project would begin “on or before” a date provided
1515 in the notice to proceed and that the notice to proceed stated that the project would
1616 begin “on or before” May 17, 2021.  The claimant claims that the claimant submitted
1717 a tentative schedule with a start date of April 5, 2021, which was rejected by DOA.
1818 The claimant asserts that the later start date affected its ability to acquire project
1919 materials in a timely manner and that DOA refused to negotiate the start date in
2020 good faith.  The claimant claims that, despite its best efforts to meet DOA demands,
2121 DOA stopped communicating with the claimant and terminated the contract.  The
2222 claimant asserts that the schedules it proposed were contractually compliant and
2323 that DOA had no right to terminate the contract.  The claimant demands that DOA
2424 rescind the contract termination and reinstate the claimant on the project.
2525 Alternatively, if the claimant is not allowed to complete the project, the claimant
2626 requests $213,302.77 in lost revenue.  DOA concedes that the notice to proceed
2727 inadvertently stated that work would begin “on or before” May 17, 2021.  However,
2828 DOA maintains that the contract signed by the claimant stated that work was to
2929 begin “on or after” the date specified in the notice to proceed, that the bid documents
3030 1
3131 2 - 2 -2023 - 2024  Legislature LRB-3739/1
3232 JPC:skw
3333 ASSEMBLY BILL 1164
3434 clearly stated that mobilization was not scheduled to take place until June 2021, and
3535 that any alleged confusion was resolved when DOA informed the claimant that it
3636 would not be permitted to mobilize until May 17, 2021.  To the extent there was any
3737 confusion in the bid documents, DOA asserts that bidders were to notify DOA prior
3838 to the bid opening, which the claimant did not do.  In response to the claimant's
3939 concerns about procuring materials, DOA asserts that it proposed extending the
4040 completion deadline by 16 days.  DOA further notes that the contract allowed the
4141 claimant to obtain and request reimbursement for offsite materials storage.  DOA
4242 maintains that any difficulties obtaining project materials were caused by the
4343 claimant's failure to purchase those materials in a timely manner.  On July 21, 2022,
4444 the claims board denied the claim because it concluded that the claim raises
4545 questions of fact that are better evaluated by a court of law (see 2021 Senate Journal,
4646 p. 975).
4747 For further information see the state fiscal estimate, which will be printed as
4848 an appendix to this bill.
4949 The people of the state of Wisconsin, represented in senate and assembly, do
5050 enact as follows:
5151 SECTION 1.0Claim against the state.  There is directed to be expended from
5252 the appropriation under s. 20.505 (4) (d) $213,302.77 in payment of a claim against
5353 the state brought by JRT Top Notch Roofs, LLC, Milwaukee, WI 53213, to
5454 compensate the claimant for a contract terminated by the department of
5555 administration related to the Esker Hall roof replacement project at the University
5656 of Wisconsin-Whitewater.  Acceptance of this payment releases this state and its
5757 officers, employees, and agents from any further liability resulting from the
5858 termination of the contract between the claimant and the department of
5959 administration.
6060 (END)
6161 1
6262 2
6363 3
6464 4
6565 5
6666 6
6767 7
6868 8
6969 9
7070 10