Wisconsin 2023-2024 Regular Session

Wisconsin Assembly Bill AB470 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 LRB-4032/1
22 EHS:amn
33 2023 - 2024 LEGISLATURE
44 2023 ASSEMBLY BILL 470
55 October 5, 2023 - Introduced by Representatives PETERSEN, MURSAU, O'CONNOR,
66 PLUMER, STEFFEN, SWEARINGEN and WICHGERS, cosponsored by Senators
77 BRADLEY, MARKLEIN and WANGGAARD. Referred to Committee on Energy and
88 Utilities.
99 ***AUTHORS SUBJECT TO CHANGE***
1010 AN ACT to create 196.485 (1) (cr), 196.485 (1) (ef) and 196.485 (3g) of the statutes;
1111 relating to: an incumbent transmission facility owner's right to construct,
1212 own, and maintain certain transmission facilities and Public Service
1313 Commission procedures if the transmission facility is a regionally cost-shared
1414 transmission line.
1515 Analysis by the Legislative Reference Bureau
1616 This bill grants to an incumbent transmission facility owner the right to
1717 construct, own, and maintain a transmission facility that has been approved for
1818 construction in the Midcontinent Independent System Operator 's (MISO)
1919 transmission plan and that connects to transmission facilities owned by that
2020 incumbent transmission facility owner.  Under the bill, an “incumbent transmission
2121 facility owner” is a transmission company or a cooperative or public utility that owns
2222 a transmission facility and provides transmission service in this state.  Under
2323 current law, MISO is an organization that is subject to the jurisdiction of the Federal
2424 Energy Regulatory Commission and that coordinates and controls electric
2525 transmission in a region of the country that includes this state.  The bill provides that
2626 the right to construct, own, and maintain a transmission facility that connects to
2727 transmission facilities owned by two or more incumbent transmission facility owners
2828 belongs individually and proportionally to each incumbent transmission facility
2929 owner, unless otherwise agreed upon in writing.
3030 The bill also defines “regionally cost-shared transmission line” to mean a
3131 high-voltage transmission line that is eligible for regional cost sharing and is not
3232 1
3333 2
3434 3
3535 4
3636 5 - 2 -2023 - 2024  Legislature LRB-4032/1
3737 EHS:amn
3838 ASSEMBLY BILL 470
3939 subject to a right of first refusal in accordance with the MISO tariff.  Under the bill,
4040 if under MISO's transmission plan a regionally cost-shared transmission line has
4141 been approved for construction and connection to facilities owned by an incumbent
4242 transmission facility owner, the incumbent transmission facility owner must give
4343 the Public Service Commission written notice regarding the owner's intent to
4444 construct, own, and maintain the line no later than 90 days after approval of the
4545 transmission plan.  If the owner indicates that it does not intent to construct the line,
4646 the bill requires it to fully explain that decision in the notice to PSC.  In that case,
4747 the bill allows PSC to determine whether the incumbent transmission facility owner
4848 or another entity must construct the line, taking into consideration issues such as
4949 cost, efficiency, and reliability.
5050 The bill requires an incumbent transmission facility owner with the right to
5151 construct a MISO-approved regionally cost-shared transmission line to include in
5252 any application for a certificate of public convenience and necessity an estimate of
5353 the cost of construction, along with documentation that the estimate is the result of
5454 competitively bid engineering, procurement, and construction contracts.  The bill
5555 also requires such an incumbent transmission facility owner to provide to PSC until
5656 construction is complete quarterly reports that include updated estimates of the
5757 construction cost and an explanation of any changes from prior cost estimates.
5858 The people of the state of Wisconsin, represented in senate and assembly, do
5959 enact as follows:
6060 SECTION 1. 196.485 (1) (cr) of the statutes is created to read:
6161 196.485 (1) (cr)  “Incumbent transmission facility owner" means a transmission
6262 company or transmission utility.
6363 SECTION 2. 196.485 (1) (ef) of the statutes is created to read:
6464 196.485 (1) (ef)  “Regionally cost-shared transmission line” means a
6565 high-voltage transmission line that is eligible, in whole or in part, for regional cost
6666 sharing and is not subject to a right of first refusal in accordance with the tariff of
6767 the Midwest independent system operator.
6868 SECTION 3. 196.485 (3g) of the statutes is created to read:
6969 196.485 (3g)  INCUMBENT TRANSMISSION FACILITY OWNER RIGHTS.  (a)  Rights.
7070 Subject to the approval of the commission under s. 196.491 (3), an incumbent
7171 transmission facility owner has the right to construct, own, and maintain a
7272 1
7373 2
7474 3
7575 4
7676 5
7777 6
7878 7
7979 8
8080 9
8181 10
8282 11
8383 12 - 3 -2023 - 2024  Legislature
8484 LRB-4032/1
8585 EHS:amn
8686 SECTION 3
8787 ASSEMBLY BILL 470
8888 transmission facility that has been approved for construction in the Midwest
8989 independent system operator's transmission plan and that connects to transmission
9090 facilities owned by that incumbent transmission facility owner.  The right to
9191 construct, own, and maintain a transmission facility that connects to transmission
9292 facilities owned by 2 or more incumbent transmission facility owners belongs
9393 individually and proportionally to each incumbent transmission facility owner,
9494 unless otherwise agreed upon in writing.
9595 (b)  Commission procedure.  1.  If, in the Midwest independent system operator's
9696 transmission plan, a regionally cost-shared transmission line has been approved for
9797 construction and connection to facilities owned by an incumbent transmission
9898 facility owner, the incumbent transmission facility owner shall give written notice
9999 to the commission regarding the owner's intent to construct, own, and maintain the
100100 regionally cost-shared transmission line no later than 90 days after approval of the
101101 transmission plan.
102102 2.  If an incumbent transmission facility owner indicates in its notice to the
103103 commission under subd. 1. that it does not intend to construct the regionally
104104 cost-shared transmission line, it shall in the notice fully explain the basis for that
105105 decision.  In that case, the commission may determine whether the incumbent
106106 transmission facility owner or another entity is required to construct the regionally
107107 cost-shared transmission line, taking into consideration issues such as cost,
108108 efficiency, reliability, and other factors identified in this chapter.
109109 (c)  Cost control and requirement of competition.  With respect to a regionally
110110 cost-shared transmission line approved by the Midwest independent system
111111 operator, an incumbent transmission facility owner with the right to construct the
112112 transmission line shall do all of the following:
113113 1
114114 2
115115 3
116116 4
117117 5
118118 6
119119 7
120120 8
121121 9
122122 10
123123 11
124124 12
125125 13
126126 14
127127 15
128128 16
129129 17
130130 18
131131 19
132132 20
133133 21
134134 22
135135 23
136136 24
137137 25 - 4 -2023 - 2024  Legislature LRB-4032/1
138138 EHS:amn
139139 SECTION 3 ASSEMBLY BILL 470
140140 1.  In any application filed pursuant to s. 196.491 (3), provide to the commission
141141 an estimate of the cost to construct the regionally cost-shared transmission line and
142142 documentation showing that this cost is the result of competitively bid engineering,
143143 procurement, and construction contracts.
144144 2.  Until construction of the regionally cost-shared transmission line is
145145 complete, provide to the commission a quarterly report that includes an updated
146146 estimate of the cost to construct the regionally cost-shared transmission line and an
147147 explanation of changes from prior cost estimates provided under this subdivision or
148148 subd. 1.
149149 (END)