1 | 1 | | LRB-4712/1 |
---|
2 | 2 | | KP:cjs |
---|
3 | 3 | | 2023 - 2024 LEGISLATURE |
---|
4 | 4 | | 2023 ASSEMBLY BILL 681 |
---|
5 | 5 | | November 27, 2023 - Introduced by Representatives GUSTAFSON, NEYLON, BALDEH, |
---|
6 | 6 | | DITTRICH, KRUG, MURPHY, O'CONNOR, RETTINGER, ROZAR, SPIROS, TITTL and |
---|
7 | 7 | | TRANEL, cosponsored by Senators COWLES, STROEBEL, BALLWEG and NASS. |
---|
8 | 8 | | Referred to Committee on Energy and Utilities. |
---|
9 | 9 | | ***AUTHORS SUBJECT TO CHANGE*** |
---|
10 | 10 | | AN ACT to amend 196.371 (3) (b); and to create 196.371 (3) (bs), 196.49 (5r) (d) |
---|
11 | 11 | | and 196.491 (3) (L) of the statutes; relating to: amending certain orders and |
---|
12 | 12 | | certificates issued by the Public Service Commission. |
---|
13 | 13 | | Analysis by the Legislative Reference Bureau |
---|
14 | 14 | | This bill authorizes the Public Service Commission to rescind, alter, or amend |
---|
15 | 15 | | an advance order specifying the rate-making principles applicable to a public |
---|
16 | 16 | | utility's recovery of capital costs for purchasing or constructing an electric |
---|
17 | 17 | | generating facility. Under the bill, PSC may amend such an order if it determines |
---|
18 | 18 | | that market conditions related to the facility have changed and that the actual costs |
---|
19 | 19 | | of the facility have substantially decreased since the order was issued. The public |
---|
20 | 20 | | utility has at least 60 days to accept or waive acceptance of an order altered or |
---|
21 | 21 | | amended under the bill. If the public utility waives acceptance of that order, PSC |
---|
22 | 22 | | must withdraw that order and any other prior advance order specifying rate-making |
---|
23 | 23 | | principles for recovery of the facility's capital costs, and must consider the facility's |
---|
24 | 24 | | capital costs in all future rate-making proceedings as if no advance order had been |
---|
25 | 25 | | issued. |
---|
26 | 26 | | Under current law, a public utility may apply to PSC for an advance order |
---|
27 | 27 | | specifying the rate-making principles for recovery of capital costs of a facility. If the |
---|
28 | 28 | | public utility accepts the advance order, PSC is bound by that order in its treatment |
---|
29 | 29 | | of the recovery of the facility's capital costs in all future rate-making proceedings |
---|
30 | 30 | | involving the public utility. If the public utility waives acceptance of the advance |
---|
31 | 31 | | order, PSC must withdraw the order and consider the facility's capital costs in all |
---|
32 | 32 | | future rate-making proceedings as if no advance order had been issued. |
---|
33 | 33 | | 1 |
---|
34 | 34 | | 2 |
---|
35 | 35 | | 3 - 2 -2023 - 2024 Legislature LRB-4712/1 |
---|
36 | 36 | | KP:cjs |
---|
37 | 37 | | ASSEMBLY BILL 681 |
---|
38 | 38 | | The bill also requires PSC to reopen proceedings that resulted in the issuance |
---|
39 | 39 | | of a certificate of public convenience and necessity (CPCN) or a certificate of |
---|
40 | 40 | | authority (CA) for a facility or project if it determines that the actual cost of |
---|
41 | 41 | | constructing the facility or project is 5 percent or more above the construction cost |
---|
42 | 42 | | approved by PSC in issuing the CPCN or CA. PSC must hold a public hearing and |
---|
43 | 43 | | public comment period of at least 15 days on the reasons for the increase in |
---|
44 | 44 | | construction costs. If in the public interest, PSC may rescind, alter, or amend the |
---|
45 | 45 | | CPCN or CA for the facility or project. Under current law, a person seeking to |
---|
46 | 46 | | construct a large electric generating facility or high-voltage transmission line must |
---|
47 | 47 | | obtain a CPCN from PSC. In addition, a public utility must obtain a CA from PSC |
---|
48 | 48 | | to construct certain other facilities and projects. |
---|
49 | 49 | | For further information see the state fiscal estimate, which will be printed as |
---|
50 | 50 | | an appendix to this bill. |
---|
51 | 51 | | The people of the state of Wisconsin, represented in senate and assembly, do |
---|
52 | 52 | | enact as follows: |
---|
53 | 53 | | SECTION 1. 196.371 (3) (b) of the statutes is amended to read: |
---|
54 | 54 | | 196.371 (3) (b) If Except as provided in par. (bs), if the public utility accepts the |
---|
55 | 55 | | order, then, in all future rate-making proceedings regarding the public utility, the |
---|
56 | 56 | | order shall be binding on the commission in its treatment of the recovery of the |
---|
57 | 57 | | capital costs of the facility that is subject to the order and the commission may not |
---|
58 | 58 | | consider the order or the effects of the order in its treatment of the recovery of any |
---|
59 | 59 | | other cost of the public utility. |
---|
60 | 60 | | SECTION 2. 196.371 (3) (bs) of the statutes is created to read: |
---|
61 | 61 | | 196.371 (3) (bs) 1. The commission may at any time, upon notice to the public |
---|
62 | 62 | | utility and after a hearing, rescind, alter, or amend an order under this section if the |
---|
63 | 63 | | commission determines that market conditions related to the facility have |
---|
64 | 64 | | substantially changed and the actual costs of the facility have substantially |
---|
65 | 65 | | decreased since the time that the order was issued. |
---|
66 | 66 | | 2. The commission shall specify in an altered or amended order under this |
---|
67 | 67 | | paragraph a deadline at least 60 days after the date of issuance of the order for the |
---|
68 | 68 | | 1 |
---|
69 | 69 | | 2 |
---|
70 | 70 | | 3 |
---|
71 | 71 | | 4 |
---|
72 | 72 | | 5 |
---|
73 | 73 | | 6 |
---|
74 | 74 | | 7 |
---|
75 | 75 | | 8 |
---|
76 | 76 | | 9 |
---|
77 | 77 | | 10 |
---|
78 | 78 | | 11 |
---|
79 | 79 | | 12 |
---|
80 | 80 | | 13 |
---|
81 | 81 | | 14 |
---|
82 | 82 | | 15 - 3 -2023 - 2024 Legislature |
---|
83 | 83 | | LRB-4712/1 |
---|
84 | 84 | | KP:cjs |
---|
85 | 85 | | SECTION 2 |
---|
86 | 86 | | ASSEMBLY BILL 681 |
---|
87 | 87 | | public utility to notify the commission in writing whether the public utility accepts |
---|
88 | 88 | | or waives acceptance of the order. If the public utility does not make the notification |
---|
89 | 89 | | by the deadline specified in the order, the public utility is considered to have waived |
---|
90 | 90 | | acceptance of the order. |
---|
91 | 91 | | 3. Except as provided in subd. 1., if the public utility accepts the order under |
---|
92 | 92 | | subd. 1., then, in all future rate-making proceedings regarding the public utility, the |
---|
93 | 93 | | order shall be binding on the commission in its treatment of the recovery of the |
---|
94 | 94 | | capital costs of the facility that is subject to the order, and the commission may not |
---|
95 | 95 | | consider the order or the effects of the order in its treatment of the recovery of any |
---|
96 | 96 | | other cost of the public utility. |
---|
97 | 97 | | 4. If the public utility waives or is considered to have waived acceptance of the |
---|
98 | 98 | | order under subd. 1., the commission shall withdraw that order and any other prior |
---|
99 | 99 | | order under this section regarding the facility and consider the capital costs of the |
---|
100 | 100 | | facility in all future rate-making proceedings in the same manner as the commission |
---|
101 | 101 | | considers capital costs for which no order has been issued under this section. |
---|
102 | 102 | | SECTION 3. 196.49 (5r) (d) of the statutes is created to read: |
---|
103 | 103 | | 196.49 (5r) (d) 1. The commission shall reopen the proceeding that resulted in |
---|
104 | 104 | | the issuance of a certificate sub. (3) or (5) if the commission determines that the |
---|
105 | 105 | | actual cost of constructing the project, plant, equipment, property, or facility for |
---|
106 | 106 | | which the certificate was issued is 5 percent or more above the construction cost |
---|
107 | 107 | | approved by the commission in issuing the certificate. |
---|
108 | 108 | | 2. The commission shall hold a public hearing on the reasons for the increase |
---|
109 | 109 | | in construction costs of the project, plant, equipment, property, or facility for a |
---|
110 | 110 | | proceeding reopened under subd. 1. and shall hold a public comment period of at least |
---|
111 | 111 | | 15 days on the reasons for the increase in construction costs. |
---|
112 | 112 | | 1 |
---|
113 | 113 | | 2 |
---|
114 | 114 | | 3 |
---|
115 | 115 | | 4 |
---|
116 | 116 | | 5 |
---|
117 | 117 | | 6 |
---|
118 | 118 | | 7 |
---|
119 | 119 | | 8 |
---|
120 | 120 | | 9 |
---|
121 | 121 | | 10 |
---|
122 | 122 | | 11 |
---|
123 | 123 | | 12 |
---|
124 | 124 | | 13 |
---|
125 | 125 | | 14 |
---|
126 | 126 | | 15 |
---|
127 | 127 | | 16 |
---|
128 | 128 | | 17 |
---|
129 | 129 | | 18 |
---|
130 | 130 | | 19 |
---|
131 | 131 | | 20 |
---|
132 | 132 | | 21 |
---|
133 | 133 | | 22 |
---|
134 | 134 | | 23 |
---|
135 | 135 | | 24 |
---|
136 | 136 | | 25 - 4 -2023 - 2024 Legislature LRB-4712/1 |
---|
137 | 137 | | KP:cjs |
---|
138 | 138 | | SECTION 3 ASSEMBLY BILL 681 |
---|
139 | 139 | | 3. After the hearing and comment period required under subd. 2., if in the |
---|
140 | 140 | | public interest, the commission may rescind, alter, or amend the order issuing the |
---|
141 | 141 | | certificate under sub. (3) or (5) for the project, plant, equipment, property, or facility. |
---|
142 | 142 | | SECTION 4. 196.491 (3) (L) of the statutes is created to read: |
---|
143 | 143 | | 196.491 (3) (L) 1. The commission shall reopen the proceeding that resulted in |
---|
144 | 144 | | the issuance of a certificate of public convenience and necessity under this subsection |
---|
145 | 145 | | for a facility if the commission determines that the actual cost of constructing the |
---|
146 | 146 | | facility is 5 percent or more above the cost of the constructing the facility approved |
---|
147 | 147 | | by the commission in issuing the certificate. |
---|
148 | 148 | | 2. The commission shall hold a public hearing on the reasons for the increase |
---|
149 | 149 | | in construction costs of the facility for a proceeding reopened under subd. 1 and shall |
---|
150 | 150 | | hold a public comment period of at least 15 days on the reasons for the increase in |
---|
151 | 151 | | construction costs of the facility. |
---|
152 | 152 | | 3. After the hearing and comment period required under subd. 2., if in the |
---|
153 | 153 | | public interest, the commission may rescind, alter, or amend the order issuing the |
---|
154 | 154 | | certificate of public convenience and necessity under this subsection for the facility. |
---|
155 | 155 | | (END) |
---|
156 | 156 | | 1 |
---|
157 | 157 | | 2 |
---|
158 | 158 | | 3 |
---|
159 | 159 | | 4 |
---|
160 | 160 | | 5 |
---|
161 | 161 | | 6 |
---|
162 | 162 | | 7 |
---|
163 | 163 | | 8 |
---|
164 | 164 | | 9 |
---|
165 | 165 | | 10 |
---|
166 | 166 | | 11 |
---|
167 | 167 | | 12 |
---|
168 | 168 | | 13 |
---|
169 | 169 | | 14 |
---|
170 | 170 | | 15 |
---|
171 | 171 | | 16 |
---|
172 | 172 | | 17 |
---|