Wisconsin 2023-2024 Regular Session

Wisconsin Assembly Bill AB681 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 LRB-4712/1
22 KP:cjs
33 2023 - 2024 LEGISLATURE
44 2023 ASSEMBLY BILL 681
55 November 27, 2023 - Introduced by Representatives GUSTAFSON, NEYLON, BALDEH,
66 DITTRICH, KRUG, MURPHY, O'CONNOR, RETTINGER, ROZAR, SPIROS, TITTL and
77 TRANEL, cosponsored by Senators COWLES, STROEBEL, BALLWEG and NASS.
88 Referred to Committee on Energy and Utilities.
99 ***AUTHORS SUBJECT TO CHANGE***
1010 AN ACT to amend 196.371 (3) (b); and to create 196.371 (3) (bs), 196.49 (5r) (d)
1111 and 196.491 (3) (L) of the statutes; relating to: amending certain orders and
1212 certificates issued by the Public Service Commission.
1313 Analysis by the Legislative Reference Bureau
1414 This bill authorizes the Public Service Commission to rescind, alter, or amend
1515 an advance order specifying the rate-making principles applicable to a public
1616 utility's recovery of capital costs for purchasing or constructing an electric
1717 generating facility. Under the bill, PSC may amend such an order if it determines
1818 that market conditions related to the facility have changed and that the actual costs
1919 of the facility have substantially decreased since the order was issued. The public
2020 utility has at least 60 days to accept or waive acceptance of an order altered or
2121 amended under the bill. If the public utility waives acceptance of that order, PSC
2222 must withdraw that order and any other prior advance order specifying rate-making
2323 principles for recovery of the facility's capital costs, and must consider the facility's
2424 capital costs in all future rate-making proceedings as if no advance order had been
2525 issued.
2626 Under current law, a public utility may apply to PSC for an advance order
2727 specifying the rate-making principles for recovery of capital costs of a facility. If the
2828 public utility accepts the advance order, PSC is bound by that order in its treatment
2929 of the recovery of the facility's capital costs in all future rate-making proceedings
3030 involving the public utility. If the public utility waives acceptance of the advance
3131 order, PSC must withdraw the order and consider the facility's capital costs in all
3232 future rate-making proceedings as if no advance order had been issued.
3333 1
3434 2
3535 3 - 2 -2023 - 2024 Legislature LRB-4712/1
3636 KP:cjs
3737 ASSEMBLY BILL 681
3838 The bill also requires PSC to reopen proceedings that resulted in the issuance
3939 of a certificate of public convenience and necessity (CPCN) or a certificate of
4040 authority (CA) for a facility or project if it determines that the actual cost of
4141 constructing the facility or project is 5 percent or more above the construction cost
4242 approved by PSC in issuing the CPCN or CA. PSC must hold a public hearing and
4343 public comment period of at least 15 days on the reasons for the increase in
4444 construction costs. If in the public interest, PSC may rescind, alter, or amend the
4545 CPCN or CA for the facility or project. Under current law, a person seeking to
4646 construct a large electric generating facility or high-voltage transmission line must
4747 obtain a CPCN from PSC. In addition, a public utility must obtain a CA from PSC
4848 to construct certain other facilities and projects.
4949 For further information see the state fiscal estimate, which will be printed as
5050 an appendix to this bill.
5151 The people of the state of Wisconsin, represented in senate and assembly, do
5252 enact as follows:
5353 SECTION 1. 196.371 (3) (b) of the statutes is amended to read:
5454 196.371 (3) (b) If Except as provided in par. (bs), if the public utility accepts the
5555 order, then, in all future rate-making proceedings regarding the public utility, the
5656 order shall be binding on the commission in its treatment of the recovery of the
5757 capital costs of the facility that is subject to the order and the commission may not
5858 consider the order or the effects of the order in its treatment of the recovery of any
5959 other cost of the public utility.
6060 SECTION 2. 196.371 (3) (bs) of the statutes is created to read:
6161 196.371 (3) (bs) 1. The commission may at any time, upon notice to the public
6262 utility and after a hearing, rescind, alter, or amend an order under this section if the
6363 commission determines that market conditions related to the facility have
6464 substantially changed and the actual costs of the facility have substantially
6565 decreased since the time that the order was issued.
6666 2. The commission shall specify in an altered or amended order under this
6767 paragraph a deadline at least 60 days after the date of issuance of the order for the
6868 1
6969 2
7070 3
7171 4
7272 5
7373 6
7474 7
7575 8
7676 9
7777 10
7878 11
7979 12
8080 13
8181 14
8282 15 - 3 -2023 - 2024 Legislature
8383 LRB-4712/1
8484 KP:cjs
8585 SECTION 2
8686 ASSEMBLY BILL 681
8787 public utility to notify the commission in writing whether the public utility accepts
8888 or waives acceptance of the order. If the public utility does not make the notification
8989 by the deadline specified in the order, the public utility is considered to have waived
9090 acceptance of the order.
9191 3. Except as provided in subd. 1., if the public utility accepts the order under
9292 subd. 1., then, in all future rate-making proceedings regarding the public utility, the
9393 order shall be binding on the commission in its treatment of the recovery of the
9494 capital costs of the facility that is subject to the order, and the commission may not
9595 consider the order or the effects of the order in its treatment of the recovery of any
9696 other cost of the public utility.
9797 4. If the public utility waives or is considered to have waived acceptance of the
9898 order under subd. 1., the commission shall withdraw that order and any other prior
9999 order under this section regarding the facility and consider the capital costs of the
100100 facility in all future rate-making proceedings in the same manner as the commission
101101 considers capital costs for which no order has been issued under this section.
102102 SECTION 3. 196.49 (5r) (d) of the statutes is created to read:
103103 196.49 (5r) (d) 1. The commission shall reopen the proceeding that resulted in
104104 the issuance of a certificate sub. (3) or (5) if the commission determines that the
105105 actual cost of constructing the project, plant, equipment, property, or facility for
106106 which the certificate was issued is 5 percent or more above the construction cost
107107 approved by the commission in issuing the certificate.
108108 2. The commission shall hold a public hearing on the reasons for the increase
109109 in construction costs of the project, plant, equipment, property, or facility for a
110110 proceeding reopened under subd. 1. and shall hold a public comment period of at least
111111 15 days on the reasons for the increase in construction costs.
112112 1
113113 2
114114 3
115115 4
116116 5
117117 6
118118 7
119119 8
120120 9
121121 10
122122 11
123123 12
124124 13
125125 14
126126 15
127127 16
128128 17
129129 18
130130 19
131131 20
132132 21
133133 22
134134 23
135135 24
136136 25 - 4 -2023 - 2024 Legislature LRB-4712/1
137137 KP:cjs
138138 SECTION 3 ASSEMBLY BILL 681
139139 3. After the hearing and comment period required under subd. 2., if in the
140140 public interest, the commission may rescind, alter, or amend the order issuing the
141141 certificate under sub. (3) or (5) for the project, plant, equipment, property, or facility.
142142 SECTION 4. 196.491 (3) (L) of the statutes is created to read:
143143 196.491 (3) (L) 1. The commission shall reopen the proceeding that resulted in
144144 the issuance of a certificate of public convenience and necessity under this subsection
145145 for a facility if the commission determines that the actual cost of constructing the
146146 facility is 5 percent or more above the cost of the constructing the facility approved
147147 by the commission in issuing the certificate.
148148 2. The commission shall hold a public hearing on the reasons for the increase
149149 in construction costs of the facility for a proceeding reopened under subd. 1 and shall
150150 hold a public comment period of at least 15 days on the reasons for the increase in
151151 construction costs of the facility.
152152 3. After the hearing and comment period required under subd. 2., if in the
153153 public interest, the commission may rescind, alter, or amend the order issuing the
154154 certificate of public convenience and necessity under this subsection for the facility.
155155 (END)
156156 1
157157 2
158158 3
159159 4
160160 5
161161 6
162162 7
163163 8
164164 9
165165 10
166166 11
167167 12
168168 13
169169 14
170170 15
171171 16
172172 17