Wisconsin 2023-2024 Regular Session

Wisconsin Senate Bill SB650 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 LRB-0577/1
22 KP:cjs
33 2023 - 2024 LEGISLATURE
44 2023 SENATE BILL 650
55 November 9, 2023 - Introduced by Senators COWLES, STROEBEL, BALLWEG and NASS,
66 cosponsored by Representatives G USTAFSON, NEYLON, TITTL, BALDEH,
77 DITTRICH, KRUG, MURPHY, O'CONNOR, RETTINGER, ROZAR, SPIROS and TRANEL.
88 Referred to Committee on Utilities and Technology.
99 AN ACT to amend 196.371 (3) (b); and to create 196.371 (3) (bs), 196.49 (5r) (d)
1010 and 196.491 (3) (L) of the statutes; relating to: amending certain orders and
1111 certificates issued by the Public Service Commission.
1212 Analysis by the Legislative Reference Bureau
1313 This bill authorizes the Public Service Commission to rescind, alter, or amend
1414 an advance order specifying the rate-making principles applicable to a public
1515 utility's recovery of capital costs for purchasing or constructing an electric
1616 generating facility. Under the bill, PSC may amend such an order if it determines
1717 that market conditions related to the facility have changed and that the actual costs
1818 of the facility have substantially decreased since the order was issued. The public
1919 utility has at least 60 days to accept or waive acceptance of an order altered or
2020 amended under the bill. If the public utility waives acceptance of that order, PSC
2121 must withdraw that order and any other prior advance order specifying rate-making
2222 principles for recovery of the facility's capital costs, and must consider the facility's
2323 capital costs in all future rate-making proceedings as if no advance order had been
2424 issued.
2525 Under current law, a public utility may apply to PSC for an advance order
2626 specifying the rate-making principles for recovery of capital costs of a facility. If the
2727 public utility accepts the advance order, PSC is bound by that order in its treatment
2828 of the recovery of the facility's capital costs in all future rate-making proceedings
2929 involving the public utility. If the public utility waives acceptance of the advance
3030 order, PSC must withdraw the order and consider the facility's capital costs in all
3131 future rate-making proceedings as if no advance order had been issued.
3232 1
3333 2
3434 3 - 2 -2023 - 2024 Legislature LRB-0577/1
3535 KP:cjs
3636 SENATE BILL 650
3737 The bill also requires PSC to reopen proceedings that resulted in the issuance
3838 of a certificate of public convenience and necessity (CPCN) or a certificate of
3939 authority (CA) for a facility or project if it determines that the actual cost of
4040 constructing the facility or project is 5 percent or more above the construction cost
4141 approved by PSC in issuing the CPCN or CA. PSC must hold a public hearing and
4242 public comment period of at least 15 days on the reasons for the increase in
4343 construction costs. If in the public interest, PSC may rescind, alter, or amend the
4444 CPCN or CA for the facility or project. Under current law, a person seeking to
4545 construct a large electric generating facility or high-voltage transmission line must
4646 obtain a CPCN from PSC. In addition, a public utility must obtain a CA from PSC
4747 to construct certain other facilities and projects.
4848 For further information see the state fiscal estimate, which will be printed as
4949 an appendix to this bill.
5050 The people of the state of Wisconsin, represented in senate and assembly, do
5151 enact as follows:
5252 SECTION 1. 196.371 (3) (b) of the statutes is amended to read:
5353 196.371 (3) (b) If Except as provided in par. (bs), if the public utility accepts the
5454 order, then, in all future rate-making proceedings regarding the public utility, the
5555 order shall be binding on the commission in its treatment of the recovery of the
5656 capital costs of the facility that is subject to the order and the commission may not
5757 consider the order or the effects of the order in its treatment of the recovery of any
5858 other cost of the public utility.
5959 SECTION 2. 196.371 (3) (bs) of the statutes is created to read:
6060 196.371 (3) (bs) 1. The commission may at any time, upon notice to the public
6161 utility and after a hearing, rescind, alter, or amend an order under this section if the
6262 commission determines that market conditions related to the facility have
6363 substantially changed and the actual costs of the facility have substantially
6464 decreased since the time that the order was issued.
6565 2. The commission shall specify in an altered or amended order under this
6666 paragraph a deadline at least 60 days after the date of issuance of the order for the
6767 1
6868 2
6969 3
7070 4
7171 5
7272 6
7373 7
7474 8
7575 9
7676 10
7777 11
7878 12
7979 13
8080 14
8181 15 - 3 -2023 - 2024 Legislature
8282 LRB-0577/1
8383 KP:cjs
8484 SECTION 2
8585 SENATE BILL 650
8686 public utility to notify the commission in writing whether the public utility accepts
8787 or waives acceptance of the order. If the public utility does not make the notification
8888 by the deadline specified in the order, the public utility is considered to have waived
8989 acceptance of the order.
9090 3. Except as provided in subd. 1., if the public utility accepts the order under
9191 subd. 1., then, in all future rate-making proceedings regarding the public utility, the
9292 order shall be binding on the commission in its treatment of the recovery of the
9393 capital costs of the facility that is subject to the order, and the commission may not
9494 consider the order or the effects of the order in its treatment of the recovery of any
9595 other cost of the public utility.
9696 4. If the public utility waives or is considered to have waived acceptance of the
9797 order under subd. 1., the commission shall withdraw that order and any other prior
9898 order under this section regarding the facility and consider the capital costs of the
9999 facility in all future rate-making proceedings in the same manner as the commission
100100 considers capital costs for which no order has been issued under this section.
101101 SECTION 3. 196.49 (5r) (d) of the statutes is created to read:
102102 196.49 (5r) (d) 1. The commission shall reopen the proceeding that resulted in
103103 the issuance of a certificate sub. (3) or (5) if the commission determines that the
104104 actual cost of constructing the project, plant, equipment, property, or facility for
105105 which the certificate was issued is 5 percent or more above the construction cost
106106 approved by the commission in issuing the certificate.
107107 2. The commission shall hold a public hearing on the reasons for the increase
108108 in construction costs of the project, plant, equipment, property, or facility for a
109109 proceeding reopened under subd. 1. and shall hold a public comment period of at least
110110 15 days on the reasons for the increase in construction costs.
111111 1
112112 2
113113 3
114114 4
115115 5
116116 6
117117 7
118118 8
119119 9
120120 10
121121 11
122122 12
123123 13
124124 14
125125 15
126126 16
127127 17
128128 18
129129 19
130130 20
131131 21
132132 22
133133 23
134134 24
135135 25 - 4 -2023 - 2024 Legislature LRB-0577/1
136136 KP:cjs
137137 SECTION 3 SENATE BILL 650
138138 3. After the hearing and comment period required under subd. 2., if in the
139139 public interest, the commission may rescind, alter, or amend the order issuing the
140140 certificate under sub. (3) or (5) for the project, plant, equipment, property, or facility.
141141 SECTION 4. 196.491 (3) (L) of the statutes is created to read:
142142 196.491 (3) (L) 1. The commission shall reopen the proceeding that resulted in
143143 the issuance of a certificate of public convenience and necessity under this subsection
144144 for a facility if the commission determines that the actual cost of constructing the
145145 facility is 5 percent or more above the cost of the constructing the facility approved
146146 by the commission in issuing the certificate.
147147 2. The commission shall hold a public hearing on the reasons for the increase
148148 in construction costs of the facility for a proceeding reopened under subd. 1 and shall
149149 hold a public comment period of at least 15 days on the reasons for the increase in
150150 construction costs of the facility.
151151 3. After the hearing and comment period required under subd. 2., if in the
152152 public interest, the commission may rescind, alter, or amend the order issuing the
153153 certificate of public convenience and necessity under this subsection for the facility.
154154 (END)
155155 1
156156 2
157157 3
158158 4
159159 5
160160 6
161161 7
162162 8
163163 9
164164 10
165165 11
166166 12
167167 13
168168 14
169169 15
170170 16
171171 17