California 2023-2024 Regular Session

California Assembly Bill AB643 Compare Versions

OldNewDifferences
1-Amended IN Assembly May 01, 2023 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 643Introduced by Assembly Member BermanFebruary 09, 2023 An act to add Sections 769.4 and 913.10 Section 769.4 to the Public Utilities Code, relating to electricity.LEGISLATIVE COUNSEL'S DIGESTAB 643, as amended, Berman. Electricity: interconnection timelines: report. Electric Rule 21: interconnection: distributed renewable generation.Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified. The commissions Electric Rule 21 establishes a tariff that describes the interconnection, operating, and metering requirements of generation facilities to be connected to an electrical corporations distribution system.This bill would require the commission, on or before June 1 of each year, to submit a report to the Legislature on timelines for the interconnection of customer-sited energy generation and storage resources, as specified. The bill would require the commission to consider the negligent exceedance, as defined, of an interconnection timeline, as defined, by an electrical corporation to be a failure to comply with a rule of the commission and subject to a penalty. The bill would require an electrical corporation to provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within 3 business days.This bill would require the commission, on or before March 31, 2024, to commence the consideration of adopting mechanisms, as provided, for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers. The bill would require the commission, in considering the adoption of mechanisms, to create process improvements to, and potential timelines for, Electric Rule 21 to address certain types of delays.Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the this bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: YES Bill TextThe people of the State of California do enact as follows:SECTION 1. Section 769.4 is added to the Public Utilities Code, to read:769.4. (a) On or before March 31, 2024, the commission shall commence, in a new proceeding or in a new phase of an existing proceeding related to Electric Rule 21, the consideration of adopting mechanisms for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers.(b) In considering the adoption of the mechanisms pursuant to subdivision (a), the commission shall create process improvements to, and potential timelines for, Electric Rule 21 to address the following types of delays:(1) Delays between submittal of an application for interconnection of a customer-sited renewable generator and the electrical corporations determination that the application is valid and complete.(2) Delays between submittal of local government inspection approval of a customer-sited renewable generator and the electrical corporations issuance of permission to operate the generator.(3) Delays in the electrical corporation scheduling an inspection of a customer-sited renewable generator when electrical corporation inspection is required.SEC. 2. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.SECTION 1.Section 769.4 is added to the Public Utilities Code, to read:769.4.(a)For purposes of this section, the following definitions apply:(1)Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2)Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b)The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c)(1)An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2)The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).SEC. 2.Section 913.10 is added to the Public Utilities Code, to read:913.10.(a)For purposes of this section, the following definitions apply:(1)Interconnection timeline means the same as defined in Section 769.4.(2)Negligent exceedance means the same as defined in Section 769.4.(b)On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1)Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2)The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3)The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4)A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5)Penalties assessed for violating interconnection timelines.SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIII B of the California Constitution.
1+CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 643Introduced by Assembly Member BermanFebruary 09, 2023 An act to add Sections 769.4 and 913.10 to the Public Utilities Code, relating to electricity.LEGISLATIVE COUNSEL'S DIGESTAB 643, as introduced, Berman. Electricity: interconnection timelines: report.Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified.This bill would require the commission, on or before June 1 of each year, to submit a report to the Legislature on timelines for the interconnection of customer-sited energy generation and storage resources, as specified. The bill would require the commission to consider the negligent exceedance, as defined, of an interconnection timeline, as defined, by an electrical corporation to be a failure to comply with a rule of the commission and subject to a penalty. The bill would require an electrical corporation to provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within 3 business days.Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: YES Bill TextThe people of the State of California do enact as follows:SECTION 1. Section 769.4 is added to the Public Utilities Code, to read:769.4. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2) Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b) The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c) (1) An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2) The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).SEC. 2. Section 913.10 is added to the Public Utilities Code, to read:913.10. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means the same as defined in Section 769.4.(2) Negligent exceedance means the same as defined in Section 769.4.(b) On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1) Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2) The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3) The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4) A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5) Penalties assessed for violating interconnection timelines.SEC. 3. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
22
3- Amended IN Assembly May 01, 2023 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 643Introduced by Assembly Member BermanFebruary 09, 2023 An act to add Sections 769.4 and 913.10 Section 769.4 to the Public Utilities Code, relating to electricity.LEGISLATIVE COUNSEL'S DIGESTAB 643, as amended, Berman. Electricity: interconnection timelines: report. Electric Rule 21: interconnection: distributed renewable generation.Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified. The commissions Electric Rule 21 establishes a tariff that describes the interconnection, operating, and metering requirements of generation facilities to be connected to an electrical corporations distribution system.This bill would require the commission, on or before June 1 of each year, to submit a report to the Legislature on timelines for the interconnection of customer-sited energy generation and storage resources, as specified. The bill would require the commission to consider the negligent exceedance, as defined, of an interconnection timeline, as defined, by an electrical corporation to be a failure to comply with a rule of the commission and subject to a penalty. The bill would require an electrical corporation to provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within 3 business days.This bill would require the commission, on or before March 31, 2024, to commence the consideration of adopting mechanisms, as provided, for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers. The bill would require the commission, in considering the adoption of mechanisms, to create process improvements to, and potential timelines for, Electric Rule 21 to address certain types of delays.Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the this bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: YES
3+ CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION Assembly Bill No. 643Introduced by Assembly Member BermanFebruary 09, 2023 An act to add Sections 769.4 and 913.10 to the Public Utilities Code, relating to electricity.LEGISLATIVE COUNSEL'S DIGESTAB 643, as introduced, Berman. Electricity: interconnection timelines: report.Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified.This bill would require the commission, on or before June 1 of each year, to submit a report to the Legislature on timelines for the interconnection of customer-sited energy generation and storage resources, as specified. The bill would require the commission to consider the negligent exceedance, as defined, of an interconnection timeline, as defined, by an electrical corporation to be a failure to comply with a rule of the commission and subject to a penalty. The bill would require an electrical corporation to provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within 3 business days.Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.Digest Key Vote: MAJORITY Appropriation: NO Fiscal Committee: YES Local Program: YES
44
5- Amended IN Assembly May 01, 2023
65
7-Amended IN Assembly May 01, 2023
6+
7+
88
99 CALIFORNIA LEGISLATURE 20232024 REGULAR SESSION
1010
1111 Assembly Bill
1212
1313 No. 643
1414
1515 Introduced by Assembly Member BermanFebruary 09, 2023
1616
1717 Introduced by Assembly Member Berman
1818 February 09, 2023
1919
20- An act to add Sections 769.4 and 913.10 Section 769.4 to the Public Utilities Code, relating to electricity.
20+ An act to add Sections 769.4 and 913.10 to the Public Utilities Code, relating to electricity.
2121
2222 LEGISLATIVE COUNSEL'S DIGEST
2323
2424 ## LEGISLATIVE COUNSEL'S DIGEST
2525
26-AB 643, as amended, Berman. Electricity: interconnection timelines: report. Electric Rule 21: interconnection: distributed renewable generation.
26+AB 643, as introduced, Berman. Electricity: interconnection timelines: report.
2727
28-Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified. The commissions Electric Rule 21 establishes a tariff that describes the interconnection, operating, and metering requirements of generation facilities to be connected to an electrical corporations distribution system.This bill would require the commission, on or before June 1 of each year, to submit a report to the Legislature on timelines for the interconnection of customer-sited energy generation and storage resources, as specified. The bill would require the commission to consider the negligent exceedance, as defined, of an interconnection timeline, as defined, by an electrical corporation to be a failure to comply with a rule of the commission and subject to a penalty. The bill would require an electrical corporation to provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within 3 business days.This bill would require the commission, on or before March 31, 2024, to commence the consideration of adopting mechanisms, as provided, for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers. The bill would require the commission, in considering the adoption of mechanisms, to create process improvements to, and potential timelines for, Electric Rule 21 to address certain types of delays.Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the this bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.
28+Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified.This bill would require the commission, on or before June 1 of each year, to submit a report to the Legislature on timelines for the interconnection of customer-sited energy generation and storage resources, as specified. The bill would require the commission to consider the negligent exceedance, as defined, of an interconnection timeline, as defined, by an electrical corporation to be a failure to comply with a rule of the commission and subject to a penalty. The bill would require an electrical corporation to provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within 3 business days.Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the bill would impose a state-mandated local program.The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.This bill would provide that no reimbursement is required by this act for a specified reason.
2929
30-Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified. The commissions Electric Rule 21 establishes a tariff that describes the interconnection, operating, and metering requirements of generation facilities to be connected to an electrical corporations distribution system.
30+Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission to make various reports to the Legislature, including a report on the progress made toward modernizing the states distribution and transmission grid and the impacts of distributed energy resources on the states distribution and transmission grid, as specified.
3131
3232 This bill would require the commission, on or before June 1 of each year, to submit a report to the Legislature on timelines for the interconnection of customer-sited energy generation and storage resources, as specified. The bill would require the commission to consider the negligent exceedance, as defined, of an interconnection timeline, as defined, by an electrical corporation to be a failure to comply with a rule of the commission and subject to a penalty. The bill would require an electrical corporation to provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within 3 business days.
3333
34-
35-
36-This bill would require the commission, on or before March 31, 2024, to commence the consideration of adopting mechanisms, as provided, for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers. The bill would require the commission, in considering the adoption of mechanisms, to create process improvements to, and potential timelines for, Electric Rule 21 to address certain types of delays.
37-
3834 Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
3935
40-Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the this bill would impose a state-mandated local program.
36+Because the provisions of this bill would be a part of the act and a violation of a commission action implementing its requirements would be a crime, the bill would impose a state-mandated local program.
4137
4238 The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
4339
4440 This bill would provide that no reimbursement is required by this act for a specified reason.
4541
4642 ## Digest Key
4743
4844 ## Bill Text
4945
50-The people of the State of California do enact as follows:SECTION 1. Section 769.4 is added to the Public Utilities Code, to read:769.4. (a) On or before March 31, 2024, the commission shall commence, in a new proceeding or in a new phase of an existing proceeding related to Electric Rule 21, the consideration of adopting mechanisms for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers.(b) In considering the adoption of the mechanisms pursuant to subdivision (a), the commission shall create process improvements to, and potential timelines for, Electric Rule 21 to address the following types of delays:(1) Delays between submittal of an application for interconnection of a customer-sited renewable generator and the electrical corporations determination that the application is valid and complete.(2) Delays between submittal of local government inspection approval of a customer-sited renewable generator and the electrical corporations issuance of permission to operate the generator.(3) Delays in the electrical corporation scheduling an inspection of a customer-sited renewable generator when electrical corporation inspection is required.SEC. 2. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.SECTION 1.Section 769.4 is added to the Public Utilities Code, to read:769.4.(a)For purposes of this section, the following definitions apply:(1)Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2)Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b)The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c)(1)An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2)The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).SEC. 2.Section 913.10 is added to the Public Utilities Code, to read:913.10.(a)For purposes of this section, the following definitions apply:(1)Interconnection timeline means the same as defined in Section 769.4.(2)Negligent exceedance means the same as defined in Section 769.4.(b)On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1)Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2)The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3)The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4)A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5)Penalties assessed for violating interconnection timelines.SEC. 3.No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIII B of the California Constitution.
46+The people of the State of California do enact as follows:SECTION 1. Section 769.4 is added to the Public Utilities Code, to read:769.4. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2) Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b) The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c) (1) An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2) The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).SEC. 2. Section 913.10 is added to the Public Utilities Code, to read:913.10. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means the same as defined in Section 769.4.(2) Negligent exceedance means the same as defined in Section 769.4.(b) On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1) Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2) The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3) The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4) A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5) Penalties assessed for violating interconnection timelines.SEC. 3. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
5147
5248 The people of the State of California do enact as follows:
5349
5450 ## The people of the State of California do enact as follows:
5551
56-SECTION 1. Section 769.4 is added to the Public Utilities Code, to read:769.4. (a) On or before March 31, 2024, the commission shall commence, in a new proceeding or in a new phase of an existing proceeding related to Electric Rule 21, the consideration of adopting mechanisms for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers.(b) In considering the adoption of the mechanisms pursuant to subdivision (a), the commission shall create process improvements to, and potential timelines for, Electric Rule 21 to address the following types of delays:(1) Delays between submittal of an application for interconnection of a customer-sited renewable generator and the electrical corporations determination that the application is valid and complete.(2) Delays between submittal of local government inspection approval of a customer-sited renewable generator and the electrical corporations issuance of permission to operate the generator.(3) Delays in the electrical corporation scheduling an inspection of a customer-sited renewable generator when electrical corporation inspection is required.
52+SECTION 1. Section 769.4 is added to the Public Utilities Code, to read:769.4. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2) Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b) The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c) (1) An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2) The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).
5753
5854 SECTION 1. Section 769.4 is added to the Public Utilities Code, to read:
5955
6056 ### SECTION 1.
6157
62-769.4. (a) On or before March 31, 2024, the commission shall commence, in a new proceeding or in a new phase of an existing proceeding related to Electric Rule 21, the consideration of adopting mechanisms for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers.(b) In considering the adoption of the mechanisms pursuant to subdivision (a), the commission shall create process improvements to, and potential timelines for, Electric Rule 21 to address the following types of delays:(1) Delays between submittal of an application for interconnection of a customer-sited renewable generator and the electrical corporations determination that the application is valid and complete.(2) Delays between submittal of local government inspection approval of a customer-sited renewable generator and the electrical corporations issuance of permission to operate the generator.(3) Delays in the electrical corporation scheduling an inspection of a customer-sited renewable generator when electrical corporation inspection is required.
58+769.4. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2) Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b) The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c) (1) An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2) The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).
6359
64-769.4. (a) On or before March 31, 2024, the commission shall commence, in a new proceeding or in a new phase of an existing proceeding related to Electric Rule 21, the consideration of adopting mechanisms for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers.(b) In considering the adoption of the mechanisms pursuant to subdivision (a), the commission shall create process improvements to, and potential timelines for, Electric Rule 21 to address the following types of delays:(1) Delays between submittal of an application for interconnection of a customer-sited renewable generator and the electrical corporations determination that the application is valid and complete.(2) Delays between submittal of local government inspection approval of a customer-sited renewable generator and the electrical corporations issuance of permission to operate the generator.(3) Delays in the electrical corporation scheduling an inspection of a customer-sited renewable generator when electrical corporation inspection is required.
60+769.4. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2) Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b) The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c) (1) An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2) The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).
6561
66-769.4. (a) On or before March 31, 2024, the commission shall commence, in a new proceeding or in a new phase of an existing proceeding related to Electric Rule 21, the consideration of adopting mechanisms for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers.(b) In considering the adoption of the mechanisms pursuant to subdivision (a), the commission shall create process improvements to, and potential timelines for, Electric Rule 21 to address the following types of delays:(1) Delays between submittal of an application for interconnection of a customer-sited renewable generator and the electrical corporations determination that the application is valid and complete.(2) Delays between submittal of local government inspection approval of a customer-sited renewable generator and the electrical corporations issuance of permission to operate the generator.(3) Delays in the electrical corporation scheduling an inspection of a customer-sited renewable generator when electrical corporation inspection is required.
62+769.4. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.(2) Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.(b) The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.(c) (1) An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.(2) The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).
6763
6864
6965
70-769.4. (a) On or before March 31, 2024, the commission shall commence, in a new proceeding or in a new phase of an existing proceeding related to Electric Rule 21, the consideration of adopting mechanisms for distributed renewable generation interconnections to enforce timelines, reduce administrative burden, and provide transparency and certainty to customers.
66+769.4. (a) For purposes of this section, the following definitions apply:
7167
72-(b) In considering the adoption of the mechanisms pursuant to subdivision (a), the commission shall create process improvements to, and potential timelines for, Electric Rule 21 to address the following types of delays:
68+(1) Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.
7369
74-(1) Delays between submittal of an application for interconnection of a customer-sited renewable generator and the electrical corporations determination that the application is valid and complete.
70+(2) Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.
7571
76-(2) Delays between submittal of local government inspection approval of a customer-sited renewable generator and the electrical corporations issuance of permission to operate the generator.
72+(b) The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.
7773
78-(3) Delays in the electrical corporation scheduling an inspection of a customer-sited renewable generator when electrical corporation inspection is required.
74+(c) (1) An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.
7975
80-SEC. 2. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
76+(2) The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).
8177
82-SEC. 2. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
78+SEC. 2. Section 913.10 is added to the Public Utilities Code, to read:913.10. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means the same as defined in Section 769.4.(2) Negligent exceedance means the same as defined in Section 769.4.(b) On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1) Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2) The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3) The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4) A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5) Penalties assessed for violating interconnection timelines.
8379
84-SEC. 2. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
80+SEC. 2. Section 913.10 is added to the Public Utilities Code, to read:
8581
8682 ### SEC. 2.
8783
84+913.10. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means the same as defined in Section 769.4.(2) Negligent exceedance means the same as defined in Section 769.4.(b) On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1) Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2) The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3) The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4) A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5) Penalties assessed for violating interconnection timelines.
85+
86+913.10. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means the same as defined in Section 769.4.(2) Negligent exceedance means the same as defined in Section 769.4.(b) On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1) Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2) The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3) The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4) A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5) Penalties assessed for violating interconnection timelines.
87+
88+913.10. (a) For purposes of this section, the following definitions apply:(1) Interconnection timeline means the same as defined in Section 769.4.(2) Negligent exceedance means the same as defined in Section 769.4.(b) On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:(1) Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.(2) The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.(3) The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.(4) A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.(5) Penalties assessed for violating interconnection timelines.
8889
8990
9091
91-
92-(a)For purposes of this section, the following definitions apply:
93-
94-
95-
96-(1)Interconnection timeline means a timeline established by the commission for a step in the process of reviewing interconnection applications.
97-
98-
99-
100-(2)Negligent exceedance means the exceedance of an interconnection timeline by an electrical corporation that does not result from unresponsiveness by the customer and is not justified by characteristics of a project that are uniquely time-consuming compared to typical interconnection requests.
101-
102-
103-
104-(b)The commission shall consider a negligent exceedance of an established interconnection timeline to be a failure to comply with a rule, subject to Section 2107.
105-
106-
107-
108-(c)(1)An electrical corporation shall provide a substantial response to any queries from an interconnection applicant related to the completeness of the application and the submission of supporting information to pending applications within three business days.
109-
110-
111-
112-(2)The commission may impose fines pursuant to Section 2107 for an electrical corporation that routinely violates the timeline in paragraph (1).
113-
114-
115-
116-
117-
118-
119-
120-(a)For purposes of this section, the following definitions apply:
121-
122-
92+913.10. (a) For purposes of this section, the following definitions apply:
12393
12494 (1) Interconnection timeline means the same as defined in Section 769.4.
12595
126-
127-
12896 (2) Negligent exceedance means the same as defined in Section 769.4.
129-
130-
13197
13298 (b) On or before June 1 of each year, the commission shall submit a report to the Legislature, in compliance with Section 9795 of the Government Code, on timelines for the interconnection of customer-sited energy generation and storage resources. The report shall contain all of the following information, and any related information that the commission deems relevant:
13399
134-
135-
136100 (1) Compliance with interconnection timelines, disaggregated by projects larger than 30 kilowatts and projects smaller than 30 kilowatts.
137-
138-
139101
140102 (2) The timeliness of electrical corporations in completing steps in the process of reviewing interconnection applications that do not have defined interconnection timelines.
141103
142-
143-
144104 (3) The number of interconnection requests initially received in each of the past five years, the number of requests withdrawn, and the number of requests granted permission to operate.
145-
146-
147105
148106 (4) A summary of challenges in reducing the amount of time for interconnection review, and the improvements to the interconnection review process that occurred in the previous year.
149107
150-
151-
152108 (5) Penalties assessed for violating interconnection timelines.
153109
110+SEC. 3. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
154111
112+SEC. 3. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
155113
114+SEC. 3. No reimbursement is required by this act pursuant to Section 6 of Article XIIIB of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIIIB of the California Constitution.
156115
157-
158-No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because the only costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIII B of the California Constitution.
116+### SEC. 3.