7 | | - | ONCERNING THE RELOCATION OF UTILITY FACILITIES IN A LOCAL |
---|
8 | | - | GOVERNMENT RIGHT |
---|
9 | | - | -OF-WAY. |
---|
10 | | - | Be it enacted by the General Assembly of the State of Colorado: |
---|
11 | | - | SECTION 1. Legislative declaration. (1) The general assembly |
---|
12 | | - | finds and declares that: |
---|
13 | | - | (a) Colorado statutes outline the use of public highways for the |
---|
14 | | - | operation and maintenance of the transportation system, and utilities must |
---|
15 | | - | be constructed so as not to obstruct or hinder the usual travel on such |
---|
16 | | - | highways, as described in section 38-5-101, Colorado Revised Statutes; |
---|
17 | | - | (b) From time to time, local governments provide improvements to |
---|
18 | | - | their transportation systems through projects within their jurisdictions; |
---|
19 | | - | (c) The scheduling and timely performance of a road improvement |
---|
20 | | - | NOTE: This bill has been prepared for the signatures of the appropriate legislative |
---|
21 | | - | officers and the Governor. To determine whether the Governor has signed the bill |
---|
22 | | - | or taken other action on it, please consult the legislative status sheet, the legislative |
---|
23 | | - | history, or the Session Laws. |
---|
24 | | - | ________ |
---|
25 | | - | Capital letters or bold & italic numbers indicate new material added to existing law; dashes |
---|
26 | | - | through words or numbers indicate deletions from existing law and such material is not part of |
---|
27 | | - | the act. project partially depends on coordination with utility companies for the |
---|
28 | | - | prompt performance of utility relocation work necessitated by construction |
---|
29 | | - | of the road improvement project; |
---|
30 | | - | (d) Increased coordination between local governments and utility |
---|
31 | | - | companies is in the public interest, and prompt performance of utility |
---|
32 | | - | relocation work according to the project schedule will reduce delays and the |
---|
33 | | - | costs of construction; |
---|
34 | | - | (e) Colorado statute outlines this type of coordination between the |
---|
35 | | - | regional transportation district and utility companies in section 32-9-119.1, |
---|
36 | | - | Colorado Revised Statutes; |
---|
37 | | - | (f) Colorado statute outlines this type of coordination between the |
---|
38 | | - | Colorado department of transportation and utility companies in section |
---|
39 | | - | 43-1-1411, Colorado Revised Statutes; and |
---|
40 | | - | (g) Construction-related delays to road improvement projects can |
---|
41 | | - | cost local governments millions of dollars of unbudgeted and unanticipated |
---|
42 | | - | costs, thereby affecting the taxpayers of that community. |
---|
43 | | - | SECTION 2. In Colorado Revised Statutes, add 38-5-109 as |
---|
44 | | - | follows: |
---|
45 | | - | 38-5-109. Utility relocation clearance letter - definitions. (1) A |
---|
46 | | - | S |
---|
47 | | - | USED IN THIS SECTION |
---|
48 | | - | , UNLESS THE CONTEXT OTHERWISE REQUIRES : |
---|
49 | | - | (a) "C |
---|
50 | | - | LEARANCE LETTER" MEANS A WRITTEN AGREEMENT BETWEEN |
---|
51 | | - | A LOCAL GOVERNMENT PROPOSING A ROAD IMPROVEMENT PROJECT AND A |
---|
52 | | - | UTILITY COMPANY |
---|
53 | | - | , IN WHICH THE UTILITY COMPANY AND THE LOCAL |
---|
54 | | - | GOVERNMENT MUTUALLY ESTABLISH THE SCOPE |
---|
55 | | - | , CONDITIONS, AND |
---|
56 | | - | SCHEDULE FOR THE UTILITY RELOCATION REQUIRED FOR THE ROAD |
---|
57 | | - | IMPROVEMENT PROJECT |
---|
58 | | - | . |
---|
59 | | - | (b) "F |
---|
60 | | - | ORCE MAJEURE" MEANS FIRE, EXPLOSION, FLOODS, ACTION OF |
---|
61 | | - | THE ELEMENTS |
---|
62 | | - | , STRIKE, LABOR DISPUTES , INTERRUPTION OF |
---|
63 | | - | TRANSPORTATION |
---|
64 | | - | , RATIONING, SHORTAGE OF EQUIPMENT OR MATERIALS , |
---|
65 | | - | COURT ACTION, ILLEGALITY, UNUSUALLY SEVERE WEATHER , ACT OF GOD, |
---|
66 | | - | ACT OF WAR OR TERRORISM , EPIDEMICS OR PANDEMICS, QUARANTINES, |
---|
67 | | - | SEASONAL LIMITATIONS ON UTILITY OPERATIONS , OR ANY OTHER CAUSE |
---|
68 | | - | PAGE 2-HOUSE BILL 24-1266 THAT IS BEYOND THE REASONABLE CONTROL OF THE ENTITY PERFORMING |
---|
69 | | - | THE UTILITY RELOCATION |
---|
70 | | - | . |
---|
71 | | - | (c) "H |
---|
72 | | - | AZARDOUS MATERIAL" MEANS ANY SUBSTANCE, POLLUTANT, |
---|
73 | | - | CONTAMINANT, CHEMICAL, MATERIAL, OR WASTE, OR ANY SOIL OR WATER |
---|
74 | | - | CONTAMINATED WITH SUCH HAZARDOUS MATERIAL |
---|
75 | | - | , THAT IS: |
---|
76 | | - | (I) I |
---|
77 | | - | NCLUDED IN THE DEFINITION OF HAZARDOUS SUBSTANCE , |
---|
78 | | - | HAZARDOUS WASTE, TOXIC SUBSTANCE, HAZARDOUS POLLUTANT , TOXIC |
---|
79 | | - | POLLUTANT |
---|
80 | | - | , NONHAZARDOUS WASTE , OR UNIVERSAL WASTE, AS REGULATED |
---|
81 | | - | BY ANY APPLICABLE ENVIRONMENTAL LAW |
---|
82 | | - | ; OR |
---|
83 | | - | (II) TOXIC, EXPLOSIVE, CORROSIVE, FLAMMABLE, IGNITABLE, |
---|
84 | | - | INFECTIOUS, RADIOACTIVE, CARCINOGENIC, MUTAGENIC, OR THAT |
---|
85 | | - | OTHERWISE POSES A HAZARD TO LIVING THINGS OR THE ENVIRONMENT |
---|
86 | | - | . |
---|
87 | | - | (d) "L |
---|
88 | | - | OCAL GOVERNMENT " MEANS A STATUTORY OR HOME RULE |
---|
89 | | - | COUNTY |
---|
90 | | - | , CITY AND COUNTY, MUNICIPALITY, OR TOWN, EXCLUDING A LOCAL |
---|
91 | | - | GOVERNMENT THAT HAS GRANTED A FRANCHISE TO A UTILITY COMPANY |
---|
92 | | - | PURSUANT TO SECTION |
---|
93 | | - | 31-32-101 OR ARTICLE XX OF THE STATE |
---|
94 | | - | CONSTITUTION |
---|
95 | | - | . |
---|
96 | | - | (e) "P |
---|
97 | | - | LANS AND SPECIFICATIONS" MEANS THE PLANS, DRAWINGS, |
---|
98 | | - | AND SPECIFICATIONS DESIGNED AND ENGINEERED BY A LOCAL GOVERNMENT |
---|
99 | | - | OR ITS CONTRACTOR |
---|
100 | | - | , WHICH ARE NECESSARY TO COMPLETE THE ROAD |
---|
101 | | - | IMPROVEMENT PROJECT IN ACCORDANCE WITH APPLICABLE LAWS |
---|
102 | | - | , RULES, |
---|
103 | | - | AND REGULATIONS. |
---|
104 | | - | (f) "P |
---|
105 | | - | RIVATE PROJECT RELOCATION" MEANS ANY CONSTRUCTION OR |
---|
106 | | - | RECONSTRUCTION PROJECT FOR THE ADJUSTMENT |
---|
107 | | - | , EXPANSION, OR |
---|
108 | | - | REALIGNMENT OF A PUBLIC ROADWAY OR PUBLIC RIGHT |
---|
109 | | - | -OF-WAY THAT: |
---|
110 | | - | (I) R |
---|
111 | | - | EQUIRES THE REMOVAL , RELOCATION, OR ALTERATION OF |
---|
112 | | - | UTILITY FACILITIES |
---|
113 | | - | ; |
---|
114 | | - | (II) I |
---|
115 | | - | S NECESSARY TO FACILITATE THE DEVELOPMENT OF PRIVATE |
---|
116 | | - | PROPERTY |
---|
117 | | - | ; AND |
---|
118 | | - | (III) IS REQUIRED BY REASON OF A LOCAL GOVERNMENT ZONING , |
---|
119 | | - | APPROVAL, OR OTHER LAND USE REGULATION PERMITTING REQUIREMENT . |
---|
120 | | - | PAGE 3-HOUSE BILL 24-1266 (g) "PROMPT PERFORMANCE " MEANS ACTING IN GOOD FAITH AND |
---|
121 | | - | MAKING ALL REASONABLE EFFORTS TO PERFORM THE SPECIFIC ACTIONS AND |
---|
122 | | - | OBLIGATIONS SET FORTH IN A CLEARANCE LETTER |
---|
123 | | - | , EXCEPT AS MAY BE |
---|
124 | | - | EXCUSED BY SUBSEQUENT AGREEMENT BETWEEN THE UTILITY COMPANY |
---|
125 | | - | AND THE LOCAL GOVERNMENT TO WHICH THE CLEARANCE LETTER APPLIES |
---|
126 | | - | . |
---|
127 | | - | (h) "P |
---|
128 | | - | UBLIC ROADWAY" MEANS PROPERTY CONTROLLED BY A LOCAL |
---|
129 | | - | GOVERNMENT THAT IS ACQUIRED |
---|
130 | | - | , DEDICATED, OR RESERVED FOR THE |
---|
131 | | - | CONSTRUCTION |
---|
132 | | - | , OPERATION, AND MAINTENANCE OF A STREET OR PUBLIC |
---|
133 | | - | HIGHWAY AND THAT IS OPEN TO PUBLIC TRAVEL OR ANY OTHER PUBLIC |
---|
134 | | - | HIGHWAY ESTABLISHED BY LAW |
---|
135 | | - | . |
---|
136 | | - | (i) (I) "R |
---|
137 | | - | OAD IMPROVEMENT PROJECT " MEANS ANY CONSTRUCTION |
---|
138 | | - | OR RECONSTRUCTION PROJECT FOR THE ADJUSTMENT |
---|
139 | | - | , EXPANSION, OR |
---|
140 | | - | REALIGNMENT OF A PUBLIC ROADWAY OR PUBLIC RIGHT |
---|
141 | | - | -OF-WAY, INCLUDING |
---|
142 | | - | BUT NOT LIMITED TO MAINTENANCE |
---|
143 | | - | , REPLACEMENT, BRIDGE, CULVERT, OR |
---|
144 | | - | TRAFFIC SIGNAL PROJECTS |
---|
145 | | - | . |
---|
146 | | - | (II) "R |
---|
147 | | - | OAD IMPROVEMENT PROJECT " DOES NOT INCLUDE A PROJECT |
---|
148 | | - | ON |
---|
149 | | - | , ALONG, OR IN A PUBLIC OR STATE HIGHWAY OR ROADWAY UNDER THE |
---|
150 | | - | CONTROL OF THE |
---|
151 | | - | COLORADO DEPARTMENT OF TRANSPORTATION UNLESS A |
---|
152 | | - | LOCAL GOVERNMENT PERFORMS THE CONSTRUCTION OR RECONSTRUCTION |
---|
153 | | - | AS PART OF A PROJECT UNDER THE DIRECTION OF THE LOCAL GOVERNMENT |
---|
154 | | - | AND PURSUANT TO AN AGREEMENT WITH THE |
---|
155 | | - | COLORADO DEPARTMENT OF |
---|
156 | | - | TRANSPORTATION |
---|
157 | | - | . |
---|
158 | | - | (j) "U |
---|
159 | | - | TILITY COMPANY" MEANS AN INVESTOR-OWNED ELECTRIC OR |
---|
160 | | - | GAS UTILITY COMPANY WITH MORE THAN TWO HUNDRED FIFTY THOUSAND |
---|
161 | | - | RETAIL CUSTOMERS |
---|
162 | | - | . |
---|
163 | | - | (k) "U |
---|
164 | | - | TILITY CONFLICT" MEANS CIRCUMSTANCES IN WHICH A |
---|
165 | | - | PROPOSED ROAD IMPROVEMENT PROJECT BRINGS UTILITY FACILITIES OUT OF |
---|
166 | | - | COMPLIANCE WITH REGULATORY AGENCY STANDARDS OR EXISTING UTILITY |
---|
167 | | - | FACILITIES PRECLUDE OR HINDER THE CONSTRUCTION OF A ROAD |
---|
168 | | - | IMPROVEMENT PROJECT |
---|
169 | | - | . |
---|
170 | | - | (l) "U |
---|
171 | | - | TILITY FACILITIES" MEANS ANY LINES OF ELECTRIC LIGHT OR |
---|
172 | | - | WIRE |
---|
173 | | - | , POWER, OR PIPELINE OF A UTILITY COMPANY AND ANY RELATED |
---|
174 | | - | SUPPORT STRUCTURES |
---|
175 | | - | , ATTACHMENTS, APPURTENANCES, EQUIPMENT, |
---|
176 | | - | VALVES, CABLE, OR CONDUIT FOR THE LINES, WIRES, OR PIPELINES. "UTILITY |
---|
177 | | - | PAGE 4-HOUSE BILL 24-1266 FACILITIES" INCLUDE BOTH THOSE ABOVE AND BELOW GROUND . |
---|
178 | | - | (m) "U |
---|
179 | | - | TILITY RELOCATION" OR "RELOCATION OF UTILITY FACILITIES" |
---|
180 | | - | MEANS THE REMOVAL, RELOCATION, OR ALTERATION OF UTILITY FACILITIES |
---|
181 | | - | NECESSARY TO RESOLVE A UTILITY CONFLICT CAUSED BY A ROAD |
---|
182 | | - | IMPROVEMENT PROJECT FUNDED IN FULL OR IN PART BY A LOCAL |
---|
183 | | - | GOVERNMENT OR WITH STATE |
---|
184 | | - | , FEDERAL, OR OTHER PUBLIC MONEY; EXCEPT |
---|
185 | | - | THAT |
---|
186 | | - | "UTILITY RELOCATION" DOES NOT INCLUDE A PRIVATE PROJECT |
---|
187 | | - | RELOCATION |
---|
188 | | - | . |
---|
189 | | - | (2) (a) I |
---|
190 | | - | F A LOCAL GOVERNMENT E NGAGES IN OR PROPOSES TO |
---|
191 | | - | ENGAGE IN A ROAD IMPROVEMENT PROJECT THAT MAY REQUIRE THE |
---|
192 | | - | RELOCATION OF UTILITY FACILITIES DUE TO A UTILITY CONFLICT |
---|
193 | | - | , THE LOCAL |
---|
194 | | - | GOVERNMENT SHALL |
---|
195 | | - | : |
---|
196 | | - | (I) N |
---|
197 | | - | OTIFY THE NOTIFICATION ASSOCIATION, CREATED IN SECTION |
---|
198 | | - | 9-1.5-105 (1), WITH AN ENGINEERING OR SUBSURFACE UTILITY ENGINEERING |
---|
199 | | - | NOTIFICATION TO IDENTIFY EACH UTILITY COMPANY THAT HAS UTILITY |
---|
200 | | - | FACILITIES IN THE AREA OF THE ROAD IMPROVEMENT PROJECT |
---|
201 | | - | ; AND |
---|
202 | | - | (II) ELECTRONICALLY NOTIFY IN WRITING EACH UTILITY COMPANY |
---|
203 | | - | IDENTIFIED PURSUANT TO SUBSECTION |
---|
204 | | - | (2)(a)(I) OF THIS SECTION. THE |
---|
205 | | - | NOTICE PROVIDED MUST FOLLOW THE REQUIREMENTS OF SUBSECTION |
---|
206 | | - | (2)(b) |
---|
207 | | - | OF THIS SECTION. |
---|
208 | | - | (b) T |
---|
209 | | - | HE NOTICE REQUIRED BY SUBSECTION (2)(a)(II) OF THIS SECTION |
---|
210 | | - | MUST INCLUDE THE FOLLOWING INFORMATION |
---|
211 | | - | : |
---|
212 | | - | (I) A |
---|
213 | | - | N EXPLANATION OF THE PROPOSED DESIGN OF THE ROAD |
---|
214 | | - | IMPROVEMENT PROJECT |
---|
215 | | - | , INCLUDING INFORMATION ON FUNDING ; |
---|
216 | | - | (II) A |
---|
217 | | - | NY POTENTIAL UTILITY CONFLICT THAT MAY BE CREATED BY |
---|
218 | | - | THE ROAD IMPROVEMENT PROJECT |
---|
219 | | - | ; |
---|
220 | | - | (III) T |
---|
221 | | - | HE ESTIMATED TIMELINE AND DURATION OF THE ROAD |
---|
222 | | - | IMPROVEMENT PROJECT |
---|
223 | | - | ; |
---|
224 | | - | (IV) T |
---|
225 | | - | HE ESTIMATED TIME FRAME IN WHICH THE UTILITY |
---|
226 | | - | RELOCATION SHOULD BE COMPLETED |
---|
227 | | - | ; |
---|
228 | | - | PAGE 5-HOUSE BILL 24-1266 (V) THE FEDERAL IDENTIFYING PROJECT NUMBER , IF APPLICABLE; |
---|
229 | | - | AND |
---|
230 | | - | (VI) WHETHER THE UTILITY COMPANY MAY QUALIFY FOR |
---|
231 | | - | ASSISTANCE TO OFFSET EXPENSES INCURRED IN RELOCATING ITS UTILITY |
---|
232 | | - | FACILITIES TO ACCOMMODATE THE PROPOSED ROAD IMPROVEMENT PROJECT |
---|
233 | | - | . |
---|
234 | | - | (c) T |
---|
235 | | - | HE LOCAL GOVERNMENT SHALL GIVE THE NOTICE REQUIRED BY |
---|
236 | | - | SUBSECTION |
---|
237 | | - | (2)(a)(II) OF THIS SECTION TO THE UTILITY COMPANY AS EARLY |
---|
238 | | - | AS PRACTICABLE AND |
---|
239 | | - | : |
---|
| 13 | + | ONCERNING THE RELOCATION OF UT ILITY FACILITIES IN A LOCAL101 |
---|
| 14 | + | GOVERNMENT RIGHT -OF-WAY.102 |
---|
| 15 | + | Bill Summary |
---|
| 16 | + | (Note: This summary applies to this bill as introduced and does |
---|
| 17 | + | not reflect any amendments that may be subsequently adopted. If this bill |
---|
| 18 | + | passes third reading in the house of introduction, a bill summary that |
---|
| 19 | + | applies to the reengrossed version of this bill will be available at |
---|
| 20 | + | http://leg.colorado.gov |
---|
| 21 | + | .) |
---|
| 22 | + | The bill requires local governments to notify affected utility |
---|
| 23 | + | companies of road improvement projects and establishes the process by |
---|
| 24 | + | which local governments and utility companies may enter into agreements |
---|
| 25 | + | governing the relocation of utility facilities. The bill requires local |
---|
| 26 | + | governments and utility companies to coordinate on road improvement |
---|
| 27 | + | projects necessitating the removal, relocation, or alteration of utility lines |
---|
| 28 | + | SENATE |
---|
| 29 | + | 3rd Reading Unamended |
---|
| 30 | + | April 22, 2024 |
---|
| 31 | + | SENATE |
---|
| 32 | + | Amended 2nd Reading |
---|
| 33 | + | April 19, 2024 |
---|
| 34 | + | HOUSE |
---|
| 35 | + | 3rd Reading Unamended |
---|
| 36 | + | March 18, 2024 |
---|
| 37 | + | HOUSE |
---|
| 38 | + | Amended 2nd Reading |
---|
| 39 | + | March 15, 2024 |
---|
| 40 | + | HOUSE SPONSORSHIP |
---|
| 41 | + | Hamrick and Frizell, Bird, Lindsay, Marshall, Ricks, Snyder, Soper, Story, Taggart, |
---|
| 42 | + | Valdez, Vigil, Weinberg |
---|
| 43 | + | SENATE SPONSORSHIP |
---|
| 44 | + | Zenzinger, |
---|
| 45 | + | Shading denotes HOUSE amendment. Double underlining denotes SENATE amendment. |
---|
| 46 | + | Capital letters or bold & italic numbers indicate new material to be added to existing law. |
---|
| 47 | + | Dashes through the words or numbers indicate deletions from existing law. in a local government's right-of-way and to commit to a schedule for |
---|
| 48 | + | utility relocation by means of either a utility relocation agreement or a |
---|
| 49 | + | clearance letter. If the actions of a utility company unreasonably delay the |
---|
| 50 | + | utility relocation schedule or the schedule of the road improvement |
---|
| 51 | + | project, the utility company must pay for the costs associated with the |
---|
| 52 | + | delay. The bill does not alter the terms of any franchises or licenses |
---|
| 53 | + | granted pursuant to statute or the state constitution. |
---|
| 54 | + | Be it enacted by the General Assembly of the State of Colorado:1 |
---|
| 55 | + | SECTION 1. Legislative declaration. (1) The general assembly2 |
---|
| 56 | + | finds and declares that:3 |
---|
| 57 | + | (a) Colorado statutes outline the use of public highways for the4 |
---|
| 58 | + | operation and maintenance of the transportation system, and utilities must5 |
---|
| 59 | + | be constructed so as not to obstruct or hinder the usual travel on such6 |
---|
| 60 | + | highways, as described in section 38-5-101, Colorado Revised Statutes;7 |
---|
| 61 | + | (b) From time to time, local governments provide improvements8 |
---|
| 62 | + | to their transportation systems through projects within their jurisdictions;9 |
---|
| 63 | + | (c) The scheduling and timely performance of a road improvement10 |
---|
| 64 | + | project partially depends on coordination with utility companies for the11 |
---|
| 65 | + | prompt performance of utility relocation work necessitated by12 |
---|
| 66 | + | construction of the road improvement project;13 |
---|
| 67 | + | (d) Increased coordination between local governments and utility14 |
---|
| 68 | + | companies is in the public interest, and prompt performance of utility15 |
---|
| 69 | + | relocation work according to the project schedule will reduce delays and16 |
---|
| 70 | + | the costs of construction;17 |
---|
| 71 | + | (e) Colorado statute outlines this type of coordination between the18 |
---|
| 72 | + | regional transportation district and utility companies in section19 |
---|
| 73 | + | 32-9-119.1, Colorado Revised Statutes;20 |
---|
| 74 | + | (f) Colorado statute outlines this type of coordination between the21 |
---|
| 75 | + | Colorado department of transportation and utility companies in section22 |
---|
| 76 | + | 1266-2- 43-1-1411, Colorado Revised Statutes; and1 |
---|
| 77 | + | (g) Construction-related delays to road improvement projects can2 |
---|
| 78 | + | cost local governments millions of dollars of unbudgeted and3 |
---|
| 79 | + | unanticipated costs, thereby affecting the taxpayers of that community.4 |
---|
| 80 | + | SECTION 2. In Colorado Revised Statutes, add 38-5-109 as5 |
---|
| 81 | + | follows:6 |
---|
| 82 | + | 38-5-109. Utility relocation clearance letter - definitions.7 |
---|
| 83 | + | (1) AS USED IN THIS SECTION, UNLESS THE CONTEXT OTHERWISE8 |
---|
| 84 | + | REQUIRES:9 |
---|
| 85 | + | (a) "CLEARANCE LETTER" MEANS A WRITTEN AGREEMENT10 |
---|
| 86 | + | BETWEEN A LOCAL GOVERNMENT PROPOSING A ROAD IMPROVEMENT11 |
---|
| 87 | + | PROJECT AND A UTILITY COMPANY, IN WHICH THE UTILITY COMPANY AND12 |
---|
| 88 | + | THE LOCAL GOVERNMENT MUTUALLY ESTABLISH THE SCOPE, CONDITIONS,13 |
---|
| 89 | + | AND SCHEDULE FOR THE UTILITY RELOCATION REQUIRED FOR THE ROAD14 |
---|
| 90 | + | IMPROVEMENT PROJECT.15 |
---|
| 91 | + | (b) "FORCE MAJEURE" MEANS FIRE, EXPLOSION, FLOODS, ACTION16 |
---|
| 92 | + | OF THE ELEMENTS , STRIKE, LABOR DISPUTES, INTERRUPTION OF17 |
---|
| 93 | + | TRANSPORTATION, RATIONING, SHORTAGE OF EQUIPMENT OR MATERIALS,18 |
---|
| 94 | + | COURT ACTION, ILLEGALITY, UNUSUALLY SEVERE WEATHER, ACT OF GOD,19 |
---|
| 95 | + | ACT OF WAR OR TERRORISM, EPIDEMICS OR PANDEMICS, QUARANTINES,20 |
---|
| 96 | + | SEASONAL LIMITATIONS ON UTILITY OPERATIONS, OR ANY OTHER CAUSE21 |
---|
| 97 | + | THAT IS BEYOND THE REASONABLE CONTROL OF THE ENTITY PERFORMING22 |
---|
| 98 | + | THE UTILITY RELOCATION.23 |
---|
| 99 | + | (c) "HAZARDOUS MATERIAL" MEANS ANY SUBSTANCE, POLLUTANT,24 |
---|
| 100 | + | CONTAMINANT, CHEMICAL, MATERIAL, OR WASTE, OR ANY SOIL OR WATER25 |
---|
| 101 | + | CONTAMINATED WITH SUCH HAZARDOUS MATERIAL , THAT IS:26 |
---|
| 102 | + | (I) INCLUDED IN THE DEFINITION OF HAZARDOUS SUBSTANCE,27 |
---|
| 103 | + | 1266 |
---|
| 104 | + | -3- HAZARDOUS WASTE, TOXIC SUBSTANCE, HAZARDOUS POLLUTANT, TOXIC1 |
---|
| 105 | + | POLLUTANT, NONHAZARDOUS WASTE , OR UNIVERSAL WASTE, AS2 |
---|
| 106 | + | REGULATED BY ANY APPLICABLE ENVIRONMENTAL LAW ; OR3 |
---|
| 107 | + | (II) TOXIC, EXPLOSIVE, CORROSIVE, FLAMMABLE, IGNITABLE,4 |
---|
| 108 | + | INFECTIOUS, RADIOACTIVE, CARCINOGENIC, MUTAGENIC, OR THAT5 |
---|
| 109 | + | OTHERWISE POSES A HAZARD TO LIVING THINGS OR THE ENVIRONMENT .6 |
---|
| 110 | + | (d) "LOCAL GOVERNMENT" MEANS A STATUTORY OR HOME RULE7 |
---|
| 111 | + | COUNTY, CITY AND COUNTY, MUNICIPALITY, OR TOWN, EXCLUDING A8 |
---|
| 112 | + | LOCAL GOVERNMENT THAT HAS GRANTED A FRANCHISE TO A UTILITY9 |
---|
| 113 | + | COMPANY PURSUANT TO SECTION 31-32-101 OR ARTICLE XX OF THE10 |
---|
| 114 | + | STATE CONSTITUTION.11 |
---|
| 115 | + | (e) "PLANS AND SPECIFICATIONS" MEANS THE PLANS, DRAWINGS,12 |
---|
| 116 | + | AND SPECIFICATIONS DESIGNED AND ENGINEERED BY A LOCAL13 |
---|
| 117 | + | GOVERNMENT OR ITS CONTRACTOR, WHICH ARE NECESSARY TO COMPLETE14 |
---|
| 118 | + | THE ROAD IMPROVEMENT PROJECT IN ACCORDANCE WITH APPLICABLE15 |
---|
| 119 | + | LAWS, RULES, AND REGULATIONS.16 |
---|
| 120 | + | (f) "PRIVATE PROJECT RELOCATION" MEANS ANY CONSTRUCTION17 |
---|
| 121 | + | OR RECONSTRUCTION PROJECT FOR THE ADJUSTMENT, EXPANSION, OR18 |
---|
| 122 | + | REALIGNMENT OF A PUBLIC ROADWAY OR PUBLIC RIGHT -OF-WAY THAT:19 |
---|
| 123 | + | (I) REQUIRES THE REMOVAL, RELOCATION, OR ALTERATION OF20 |
---|
| 124 | + | UTILITY FACILITIES;21 |
---|
| 125 | + | (II) IS NECESSARY TO FACILITATE THE DEVELOPMENT OF PRIVATE22 |
---|
| 126 | + | PROPERTY; AND23 |
---|
| 127 | + | (III) IS REQUIRED BY REASON OF A LOCAL GOVERNMENT ZONING ,24 |
---|
| 128 | + | APPROVAL, OR OTHER LAND USE REGULATION PERMITTING REQUIREMENT.25 |
---|
| 129 | + | (g) "PROMPT PERFORMANCE" MEANS ACTING IN GOOD FAITH AND26 |
---|
| 130 | + | MAKING ALL REASONABLE EFFORTS TO PERFORM THE SPECIFIC ACTIONS27 |
---|
| 131 | + | 1266 |
---|
| 132 | + | -4- AND OBLIGATIONS SET FORTH IN A CLEARANCE LETTER, EXCEPT AS MAY BE1 |
---|
| 133 | + | EXCUSED BY SUBSEQUENT AGREEMENT BETWEEN THE UTILITY COMPANY2 |
---|
| 134 | + | AND THE LOCAL GOVERNMENT TO WHICH THE CLEARANCE LETTER APPLIES .3 |
---|
| 135 | + | (h) "PUBLIC ROADWAY" MEANS PROPERTY CONTROLLED BY A4 |
---|
| 136 | + | LOCAL GOVERNMENT THAT IS ACQUIRED , DEDICATED, OR RESERVED FOR5 |
---|
| 137 | + | THE CONSTRUCTION, OPERATION, AND MAINTENANCE OF A STREET OR6 |
---|
| 138 | + | PUBLIC HIGHWAY AND THAT IS OPEN TO PUBLIC TRAVEL OR ANY OTHER7 |
---|
| 139 | + | PUBLIC HIGHWAY ESTABLISHED BY LAW .8 |
---|
| 140 | + | (i) (I) "ROAD IMPROVEMENT PROJECT" MEANS ANY CONSTRUCTION9 |
---|
| 141 | + | OR RECONSTRUCTION PROJECT FOR THE ADJUSTMENT, EXPANSION, OR10 |
---|
| 142 | + | REALIGNMENT OF A PUBLIC ROADWAY OR PUBLIC RIGHT-OF-WAY,11 |
---|
| 143 | + | INCLUDING BUT NOT LIMITED TO MAINTENANCE, REPLACEMENT, BRIDGE,12 |
---|
| 144 | + | CULVERT, OR TRAFFIC SIGNAL PROJECTS.13 |
---|
| 145 | + | (II) "ROAD IMPROVEMENT PROJECT" DOES NOT INCLUDE A PROJECT14 |
---|
| 146 | + | ON, ALONG, OR IN A PUBLIC OR STATE HIGHWAY OR ROADWAY UNDER THE15 |
---|
| 147 | + | CONTROL OF THE COLORADO DEPARTMENT OF TRANSPORTATION UNLESS16 |
---|
| 148 | + | A LOCAL GOVERNMENT PERFORMS THE CONSTRUCTION OR17 |
---|
| 149 | + | RECONSTRUCTION AS PART OF A PROJECT UNDER THE DIRECTION OF THE18 |
---|
| 150 | + | LOCAL GOVERNMENT AND PURSUANT TO AN AGREEMENT WITH THE19 |
---|
| 151 | + | COLORADO DEPARTMENT OF TRANSPORTATION .20 |
---|
| 152 | + | (j) "UTILITY COMPANY" MEANS AN INVESTOR-OWNED ELECTRIC OR21 |
---|
| 153 | + | GAS UTILITY COMPANY WITH MORE THAN TWO HUNDRED FIFTY THOUSAND22 |
---|
| 154 | + | RETAIL CUSTOMERS.23 |
---|
| 155 | + | (k) "UTILITY CONFLICT" MEANS CIRCUMSTANCES IN WHICH A24 |
---|
| 156 | + | PROPOSED ROAD IMPROVEMENT PROJECT BRINGS UTILITY FACILITIES OUT25 |
---|
| 157 | + | OF COMPLIANCE WITH REGULATORY AGENCY STANDARDS OR EXISTING26 |
---|
| 158 | + | UTILITY FACILITIES PRECLUDE OR HINDER THE CONSTRUCTION OF A ROAD27 |
---|
| 159 | + | 1266 |
---|
| 160 | + | -5- IMPROVEMENT PROJECT.1 |
---|
| 161 | + | (l) "UTILITY FACILITIES" MEANS ANY LINES OF ELECTRIC LIGHT OR2 |
---|
| 162 | + | WIRE, POWER, OR PIPELINE OF A UTILITY COMPANY AND ANY RELATED3 |
---|
| 163 | + | SUPPORT STRUCTURES, ATTACHMENTS, APPURTENANCES, EQUIPMENT,4 |
---|
| 164 | + | VALVES, CABLE, OR CONDUIT FOR THE LINES, WIRES, OR PIPELINES.5 |
---|
| 165 | + | "UTILITY FACILITIES" INCLUDE BOTH THOSE ABOVE AND BELOW GROUND.6 |
---|
| 166 | + | (m) "UTILITY RELOCATION" OR "RELOCATION OF UTILITY7 |
---|
| 167 | + | FACILITIES" MEANS THE REMOVAL, RELOCATION, OR ALTERATION OF8 |
---|
| 168 | + | UTILITY FACILITIES NECESSARY TO RESOLVE A UTILITY CONFLICT CAUSED9 |
---|
| 169 | + | BY A ROAD IMPROVEMENT PROJECT FUNDED IN FULL OR IN PART BY A10 |
---|
| 170 | + | LOCAL GOVERNMENT OR WITH STATE, FEDERAL, OR OTHER PUBLIC MONEY;11 |
---|
| 171 | + | EXCEPT THAT "UTILITY RELOCATION" DOES NOT INCLUDE A PRIVATE12 |
---|
| 172 | + | PROJECT RELOCATION.13 |
---|
| 173 | + | (2) (a) IF A LOCAL GOVERNMENT ENGAGES IN OR PROPOSES TO14 |
---|
| 174 | + | ENGAGE IN A ROAD IMPROVEMENT PROJECT THAT MAY REQUIRE THE15 |
---|
| 175 | + | RELOCATION OF UTILITY FACILITIES DUE TO A UTILITY CONFLICT , THE16 |
---|
| 176 | + | LOCAL GOVERNMENT SHALL :17 |
---|
| 177 | + | (I) NOTIFY THE NOTIFICATION ASSOCIATION, CREATED IN SECTION18 |
---|
| 178 | + | 9-1.5-105 (1), WITH AN ENGINEERING OR SUBSURFACE UTILITY19 |
---|
| 179 | + | ENGINEERING NOTIFICATION TO IDENTIFY EACH UTILITY COMPANY THAT20 |
---|
| 180 | + | HAS UTILITY FACILITIES IN THE AREA OF THE ROAD IMPROVEMENT21 |
---|
| 181 | + | PROJECT; AND22 |
---|
| 182 | + | (II) ELECTRONICALLY NOTIFY IN WRITING EACH UTILITY COMPANY23 |
---|
| 183 | + | IDENTIFIED PURSUANT TO SUBSECTION (2)(a)(I) OF THIS SECTION. THE24 |
---|
| 184 | + | NOTICE PROVIDED MUST FOLLOW THE REQUIREMENTS OF SUBSECTION25 |
---|
| 185 | + | (2)(b) OF THIS SECTION.26 |
---|
| 186 | + | (b) THE NOTICE REQUIRED BY SUBSECTION (2)(a)(II) OF THIS27 |
---|
| 187 | + | 1266 |
---|
| 188 | + | -6- SECTION MUST INCLUDE THE FOLLOWING INFORMATION :1 |
---|
| 189 | + | (I) AN EXPLANATION OF THE PROPOSED DESIGN OF THE ROAD2 |
---|
| 190 | + | IMPROVEMENT PROJECT, INCLUDING INFORMATION ON FUNDING ;3 |
---|
| 191 | + | (II) ANY POTENTIAL UTILITY CONFLICT THAT MAY BE CREATED BY4 |
---|
| 192 | + | THE ROAD IMPROVEMENT PROJECT ;5 |
---|
| 193 | + | (III) THE ESTIMATED TIMELINE AND DURATION OF THE ROAD6 |
---|
| 194 | + | IMPROVEMENT PROJECT;7 |
---|
| 195 | + | (IV) THE ESTIMATED TIME FRAME IN WHICH THE UTILITY8 |
---|
| 196 | + | RELOCATION SHOULD BE COMPLETED ;9 |
---|
| 197 | + | (V) THE FEDERAL IDENTIFYING PROJECT NUMBER, IF APPLICABLE;10 |
---|
| 198 | + | AND11 |
---|
| 199 | + | (VI) WHETHER THE UTILITY COMPANY MAY QUALIFY FOR12 |
---|
| 200 | + | ASSISTANCE TO OFFSET EXPENSES INCURRED IN RELOCATING ITS UTILITY13 |
---|
| 201 | + | FACILITIES TO ACCOMMODATE THE PROPOSED ROAD IMPROVEMENT14 |
---|
| 202 | + | PROJECT.15 |
---|
| 203 | + | (c) THE LOCAL GOVERNMENT SHALL GIVE THE NOTICE REQUIRED16 |
---|
| 204 | + | BY SUBSECTION (2)(a)(II) OF THIS SECTION TO THE UTILITY COMPANY AS17 |
---|
| 205 | + | EARLY AS PRACTICABLE AND:18 |
---|
280 | | - | F UTILITY FACILITIES WERE NOT PREVIOUSLY IDENTIFIED AND |
---|
281 | | - | PAGE 6-HOUSE BILL 24-1266 RESULT IN A NEWLY DISCOVERED UTILITY CONFLICT , THE LOCAL |
---|
282 | | - | GOVERNMENT |
---|
283 | | - | , THE AFFECTED UTILITY COMPANY , AND THE THIRD-PARTY |
---|
284 | | - | CONTRACTOR |
---|
285 | | - | , AS APPLICABLE, SHALL CONFER WITHIN FORTY-EIGHT HOURS |
---|
286 | | - | OF DISCOVERY TO DETERMINE APPROPRIATE RELOCATION PROCEDURES |
---|
287 | | - | . |
---|
288 | | - | (II) W |
---|
289 | | - | ITHIN TEN BUSINESS DAYS OF THE DISCOVERY OF THE UTILITY |
---|
290 | | - | CONFLICT |
---|
291 | | - | , THE LOCAL GOVERNMENT AND THE AFFECTED UTILITY COMPANY |
---|
292 | | - | SHALL NEGOTIATE A CLEARANCE LETTER PURSUANT TO SUBSECTION |
---|
293 | | - | (3) OF |
---|
294 | | - | THIS SECTION |
---|
295 | | - | . |
---|
296 | | - | (3) (a) T |
---|
297 | | - | O FACILITATE A UTILITY RELOCATION , A LOCAL |
---|
298 | | - | GOVERNMENT AND AN AFFECTED UTILITY COMPANY SHALL NEGOTIATE IN |
---|
299 | | - | GOOD FAITH AND SHALL ENTER INTO A MUTUALLY AGREEABLE CLEARANCE |
---|
300 | | - | LETTER |
---|
301 | | - | . |
---|
302 | | - | (b) T |
---|
303 | | - | HE CLEARANCE LETTER MUST INCLUDE : |
---|
304 | | - | (I) A |
---|
305 | | - | N ACKNOWLEDGMENT BY THE LOCAL GOVERNMENT AND THE |
---|
306 | | - | UTILITY COMPANY THAT A UTILITY CONFLICT EXISTS |
---|
307 | | - | ; |
---|
308 | | - | (II) T |
---|
309 | | - | HE SCOPE OF THE UTILITY RELOCATION, INCLUDING THE EXTENT |
---|
310 | | - | OF THE UTILITY FACILITIES NEEDING TO BE RELOCATED AS EVIDENCED BY |
---|
311 | | - | THE PLANS AND SPECIFICATIONS |
---|
312 | | - | ; |
---|
313 | | - | (III) W |
---|
314 | | - | HETHER THE UTILITY RELOCATION WILL BE PERFORMED BY |
---|
315 | | - | THE UTILITY COMPANY OR BY A THIRD |
---|
316 | | - | -PARTY CONTRACTOR AGREED TO BY |
---|
317 | | - | THE UTILITY COMPANY |
---|
318 | | - | ; |
---|
319 | | - | (IV) R |
---|
320 | | - | EQUIREMENTS FOR COORDINATION AMONG THE LOCAL |
---|
321 | | - | GOVERNMENT |
---|
322 | | - | , THE UTILITY COMPANY, AND ANY THIRD-PARTY CONTRACTOR |
---|
323 | | - | THROUGHOUT THE ROAD IMPROVEMENT PROJECT AND UTILITY RELOCATION |
---|
324 | | - | , |
---|
325 | | - | INCLUDING THROUGHOUT ANY PREREQUISITE WORK THAT NEEDS TO OCCUR |
---|
326 | | - | BEFORE THE UTILITY RELOCATION |
---|
327 | | - | ; |
---|
328 | | - | (V) W |
---|
329 | | - | HICH ENTITY IS RESPONSIBLE FOR TRAFFIC MANAGEMENT |
---|
330 | | - | DURING THE UTILITY RELOCATION |
---|
331 | | - | ; |
---|
332 | | - | (VI) T |
---|
333 | | - | HE NUMBER OF DAYS OF NOTICE THAT THE LOCAL |
---|
334 | | - | GOVERNMENT MUST GIVE TO THE UTILITY COMPANY AHEAD OF THE DATE BY |
---|
335 | | - | WHICH THE UTILITY RELOCATION MUST BE STARTED IN ORDER TO ADHERE TO |
---|
336 | | - | PAGE 7-HOUSE BILL 24-1266 THE ROAD IMPROVEMENT PROJECT SCHEDULE ; |
---|
337 | | - | (VII) A |
---|
338 | | - | N ESTIMATED SCHEDULE FOR THE PERFORMANCE OF THE |
---|
339 | | - | UTILITY RELOCATION |
---|
340 | | - | , INCLUDING THE DURATION OF THE UTILITY |
---|
341 | | - | RELOCATION |
---|
342 | | - | ; |
---|
343 | | - | (VIII) A |
---|
344 | | - | REQUIREMENT OF PROMPT PERFORMANCE OF THE UTILITY |
---|
345 | | - | RELOCATION BY THE UTILITY COMPANY IF THE UTILITY COMPANY IS |
---|
346 | | - | PERFORMING THE UTILITY RELOCATION OR BY THE THIRD |
---|
347 | | - | -PARTY |
---|
348 | | - | CONTRACTOR AGREED TO BY THE UTILITY COMPANY TO PERFORM THE |
---|
349 | | - | UTILITY RELOCATION |
---|
350 | | - | , EXCEPT WHEN PERFORMANCE IS EXCUSED DUE TO |
---|
351 | | - | FORCE MAJEURE |
---|
352 | | - | , THE DISCOVERY OF HAZARDOUS MATERIAL IN THE PUBLIC |
---|
353 | | - | ROADWAY |
---|
354 | | - | , OR A CHANGE IN THE SCOPE OR AGREED-TO SCHEDULE OF A ROAD |
---|
355 | | - | IMPROVEMENT PROJECT OR THE PLANS AND SPECIFICATIONS THAT AFFECTS |
---|
356 | | - | THE UTILITY FACILITIES |
---|
357 | | - | ; |
---|
358 | | - | (IX) A |
---|
359 | | - | REQUIREMENT OF PAYMENT BY THE UTILITY COMPANY FOR |
---|
360 | | - | ACTUAL DAMAGES CAUSED BY THE UTILITY COMPANY |
---|
361 | | - | 'S DELAY IN THE |
---|
362 | | - | PERFORMANCE OF THE UTILITY RELOCATION OR INTERFERENCE WITH THE |
---|
363 | | - | PERFORMANCE OF THE UTILITY RELOCATION BY ANY CONTRACTOR NOT |
---|
364 | | - | HIRED BY THE UTILITY COMPANY |
---|
365 | | - | ; EXCEPT THAT DELAY OR INTERFERENCE |
---|
366 | | - | CAUSED BY THE FOLLOWING WILL NOT BE CHARGED TO THE UTILITY |
---|
367 | | - | COMPANY |
---|
368 | | - | : |
---|
369 | | - | (A) A |
---|
370 | | - | FORCE MAJEURE; |
---|
371 | | - | (B) T |
---|
372 | | - | HE DISCOVERY OF HAZARDOUS MATERIAL IN THE PUBLIC |
---|
373 | | - | ROADWAY |
---|
374 | | - | ; OR |
---|
375 | | - | (C) A CHANGE IN THE SCOPE OR AGREED-TO SCHEDULE OF A ROAD |
---|
376 | | - | IMPROVEMENT PROJECT OR THE PLANS AND SPECIFICATIONS THAT AFFECTS |
---|
377 | | - | THE UTILITY FACILITIES AND THE UTILITY COMPANY |
---|
378 | | - | 'S ABILITY TO PERFORM |
---|
379 | | - | THE RELOCATION WORK AS ESTABLISHED IN THE CLEARANCE LETTER |
---|
380 | | - | ; |
---|
381 | | - | (X) A |
---|
382 | | - | REQUIREMENT THAT THE LOCAL GOVERNMENT , AT ITS SOLE |
---|
383 | | - | COST |
---|
384 | | - | , SURVEY AND STAKE THE LOCATION WHERE THE UTILITY FACILITIES |
---|
385 | | - | WILL BE LOCATED PRIOR TO THE BEGINNING OF THE UTILITY RELOCATION |
---|
386 | | - | , |
---|
387 | | - | AND THAT THE COST OF ANY REQUIRED RE-STAKING DUE TO THE ACTIONS OF |
---|
388 | | - | A UTILITY COMPANY OR ITS CONTRACTOR BE PAID BY THE UTILITY COMPANY |
---|
389 | | - | ; |
---|
390 | | - | PAGE 8-HOUSE BILL 24-1266 (XI) A REQUIREMENT THAT, UPON THE DISCOVERY OF HAZARDOUS |
---|
391 | | - | MATERIAL IN A PUBLIC ROADWAY IN CONNECTION WITH UTILITY |
---|
392 | | - | RELOCATION |
---|
393 | | - | , THE UTILITY RELOCATION WORK CEASE UNTIL THE LOCAL |
---|
394 | | - | GOVERNMENT TAKES NECESSARY STEPS TO PROVIDE A UTILITY CORRIDOR |
---|
395 | | - | FREE FROM HAZARDOUS MATERIAL |
---|
396 | | - | , AND THAT THE LOCAL GOVERNMENT IS |
---|
397 | | - | RESPONSIBLE FOR THE MANAGEMENT |
---|
398 | | - | , TRANSPORTATION, AND DISPOSAL OF |
---|
399 | | - | ANY SOIL FROM THE PUBLIC RIGHT |
---|
400 | | - | -OF-WAY CONTAMINATED WITH |
---|
401 | | - | HAZARDOUS MATERIAL |
---|
402 | | - | ; |
---|
403 | | - | (XII) A |
---|
404 | | - | REQUIREMENT THAT ALL DESIGN AND CONSTRUCTION OF THE |
---|
405 | | - | UTILITY RELOCATION ARE SUBJECT TO REVIEW AND APPROVAL BY ENGINEERS |
---|
406 | | - | FOR THE LOCAL GOVERNMENT AND FOR THE UTILITY COMPANY |
---|
407 | | - | ; AND |
---|
408 | | - | (XIII) A DISPUTE RESOLUTION PROVISION THAT INCLUDES |
---|
409 | | - | MECHANISMS FOR NOTICE OF A FAILURE TO PERFORM IN ACCORDANCE WITH |
---|
410 | | - | THE CLEARANCE LETTER AND FOR A REASONABLE OPPORTUNITY TO CURE |
---|
411 | | - | . |
---|
412 | | - | (c) (I) T |
---|
413 | | - | HE CLEARANCE LETTER MAY ALLOW FOR UTILITY COMPANY |
---|
414 | | - | BETTERMENT AT THE EXPENSE OF THE UTILITY COMPANY |
---|
415 | | - | ; EXCEPT THAT ANY |
---|
416 | | - | UTILITY COMPANY BETTERMENT MUST NOT MATERIALLY DELAY THE UTILITY |
---|
417 | | - | RELOCATION |
---|
418 | | - | . |
---|
419 | | - | (II) A |
---|
420 | | - | S USED IN THIS SUBSECTION (3)(c), "UTILITY COMPANY |
---|
421 | | - | BETTERMENT |
---|
422 | | - | " MEANS ANY UPGRADE OF THE UTILITY FACILITIES BEING |
---|
423 | | - | RELOCATED THAT IS NOT ATTRIBUTABLE TO THE ROAD IMPROVEMENT |
---|
424 | | - | PROJECT AND THAT IS MADE SOLELY FOR THE BENEFIT AND AT THE ELECTION |
---|
425 | | - | OF THE AFFECTED UTILITY COMPANY |
---|
426 | | - | . |
---|
427 | | - | (4) (a) U |
---|
428 | | - | PON BEING PROVIDED WRITTEN DOCUMENTATION OF THE |
---|
429 | | - | HORIZONTAL AND VERTICAL LOCATIONS OF THE RELOCATED UTILITY |
---|
430 | | - | FACILITIES AND A STATEMENT BY THE UTILITY COMPANY OR ITS |
---|
431 | | - | CONTRACTOR THAT THE UTILITY FACILITIES ARE RELOCATED IN |
---|
432 | | - | ACCORDANCE WITH THE APPROVED UTILITY RELOCATION PLANS |
---|
433 | | - | , A LOCAL |
---|
434 | | - | GOVERNMENT SHALL COMPLETE ITS REVIEW OF THE COMPLETED UTILITY |
---|
435 | | - | RELOCATION AND PROVIDE A WRITTEN DETERMINATION OF WHETHER IT |
---|
436 | | - | ACCEPTS OR REJECTS THE COMPLETED UTILITY RELOCATION WITHIN |
---|
437 | | - | FOURTEEN CALENDAR DAYS OF COMPLETION OF THE RELOCATION OR RECEIPT |
---|
438 | | - | OF THE DOCUMENTATION INDICATING THE LOCATION OF THE RELOCATED |
---|
439 | | - | UTILITY FACILITIES FROM THE UTILITY COMPANY |
---|
440 | | - | , WHICHEVER IS LATER. |
---|
441 | | - | PAGE 9-HOUSE BILL 24-1266 (b) IF THE LOCAL GOVERNMENT ACCEPTS THE UTILITY RELOCATION , |
---|
442 | | - | THE LOCAL GOVERNMENT SHALL PROVIDE ITS WRITTEN ACCEPTANCE OF THE |
---|
443 | | - | UTILITY RELOCATION TO THE UTILITY COMPANY |
---|
444 | | - | . |
---|
445 | | - | (c) (I) I |
---|
446 | | - | F THE LOCAL GOVERNMENT REJECTS THE UTILITY |
---|
447 | | - | RELOCATION |
---|
448 | | - | , THE LOCAL GOVERNMENT SHALL PROVIDE ITS WRITTEN |
---|
449 | | - | REJECTION AND REASONING TO THE UTILITY COMPANY |
---|
450 | | - | . |
---|
451 | | - | (II) T |
---|
452 | | - | HE UTILITY COMPANY SHALL PROMPTLY MAKE THE NECESSARY |
---|
453 | | - | CHANGES TO THE UTILITY RELOCATION IDENTIFIED IN THE WRITTEN |
---|
454 | | - | REJECTION TO CONFORM WITH THE PLANS AND SPECIFICATIONS IDENTIFIED |
---|
455 | | - | IN THE CLEARANCE LETTER |
---|
456 | | - | . THE UTILITY COMPANY IS RESPONSIBLE FOR |
---|
457 | | - | PAYMENT OF ACTUAL DAMAGES CAUSED BY ANY DELAY IN THE ROAD |
---|
458 | | - | IMPROVEMENT PROJECT SCHEDULE AS A RESULT OF THE NECESSARY |
---|
459 | | - | CHANGES TO THE UTILITY RELOCATION TO BRING THE RELOCATION INTO |
---|
460 | | - | COMPLIANCE WITH THE PLANS AND SPECIFICATIONS IDENTIFIED IN THE |
---|
461 | | - | CLEARANCE LETTER |
---|
462 | | - | . |
---|
463 | | - | (d) I |
---|
464 | | - | F THE LOCAL GOVERNMENT FAILS TO TIMELY PROVIDE THE |
---|
465 | | - | WRITTEN DETERMINATION REQUIRED BY SUBSECTION |
---|
466 | | - | (4)(a) OF THIS SECTION, |
---|
467 | | - | THE UTILITY RELOCATION IS DEEMED ACCEPTED . |
---|
468 | | - | (e) A |
---|
469 | | - | UTILITY COMPANY SHALL NOT BE REQUIRED TO PAY FOR |
---|
470 | | - | RELOCATION OF PREVIOUSLY RELOCATED UTILITY FACILITIES WITHIN TWO |
---|
471 | | - | YEARS FOLLOWING THE ACCEPTANCE OF THE PREVIOUS UTILITY RELOCATION |
---|
472 | | - | BY THE LOCAL GOVERNMENT PURSUANT TO THIS SUBSECTION |
---|
473 | | - | (4), EXCEPT IN |
---|
474 | | - | THE EVENT OF AN EMERGENCY |
---|
475 | | - | . |
---|
476 | | - | (5) A |
---|
477 | | - | LOCAL GOVERNMENT MAY , AFTER OPPORTUNITY FOR RELIEF |
---|
478 | | - | BETWEEN THE LOCAL GOVERNMENT AND THE UTILITY COMPANY PURSUANT |
---|
479 | | - | TO THE DISPUTE RESOLUTION PROCESS OUTLINED IN THE CLEARANCE LETTER |
---|
480 | | - | , |
---|
481 | | - | WITHHOLD ISSUANCE OF A PERMIT FOR THE LOCATION OR INSTALLATION OF |
---|
482 | | - | OTHER UTILITY FACILITIES IN A PUBLIC ROADWAY TO A UTILITY COMPANY |
---|
483 | | - | UNTIL THE DISPUTE IS RESOLVED |
---|
484 | | - | , WHICH MAY INCLUDE PAYMENT TO THE |
---|
485 | | - | LOCAL GOVERNMENT FOR ANY ACTUAL DAMAGES CAUSED BY THE UTILITY |
---|
486 | | - | COMPANY |
---|
487 | | - | 'S DELAY IN THE PERFORMANCE OF A UTILITY RELOCATION . |
---|
488 | | - | (6) W |
---|
489 | | - | HEN NECESSARY AND FEASIBLE AND AFTER MUTUAL |
---|
490 | | - | AGREEMENT WITH AN AFFECTED UTILITY COMPANY |
---|
491 | | - | , A LOCAL GOVERNMENT |
---|
492 | | - | MAY OBTAIN ADDITIONAL PUBLIC RIGHTS |
---|
493 | | - | -OF-WAY OR EASEMENTS TO |
---|
494 | | - | PAGE 10-HOUSE BILL 24-1266 ACCOMMODATE A UTILITY RELOCATION . THE LOCAL GOVERNMENT IS |
---|
495 | | - | RESPONSIBLE FOR THE COST OF OBTAINING ANY ADDITIONAL RIGHT |
---|
496 | | - | -OF-WAY |
---|
497 | | - | UNLESS THE ADDITIONAL RIGHT |
---|
498 | | - | -OF-WAY IS ONLY NEEDED TO ACCOMMODATE |
---|
499 | | - | A UTILITY COMPANY B ETTERMENT AND IS NOT REQUIRED FOR A ROAD |
---|
500 | | - | IMPROVEMENT PROJECT |
---|
501 | | - | . |
---|
502 | | - | (7) A |
---|
503 | | - | LOCAL GOVERNMENT AND AN AFFECTED UTILITY COMPANY |
---|
504 | | - | SHALL MAKE ARRANGEMENTS FOR FUNDING ANY UTILITY RELOCATION AS |
---|
505 | | - | SPECIFIED IN ANY EASEMENTS |
---|
506 | | - | , LICENSES, OR OTHER PROPERTY INTERESTS OR |
---|
507 | | - | RIGHTS OF USE HELD BY THE LOCAL GOVERNMENT OR THE UTILITY COMPANY |
---|
508 | | - | . |
---|
509 | | - | T |
---|
510 | | - | HE RECOVERY OF UNDERGROUND UTILITY LOCATE COSTS , AS INCURRED BY |
---|
511 | | - | THE UTILITY COMPANY |
---|
512 | | - | , MUST OCCUR THROUGH APPROPRIATE RATE |
---|
513 | | - | ADJUSTMENT CLAUSES |
---|
514 | | - | . |
---|
515 | | - | (8) N |
---|
516 | | - | O PARTY OTHER THAN THE OWNER OF THE UTILITY FACILITIES |
---|
517 | | - | MAY RELOCATE UTILITY FACILITIES WITHOUT THE EXPRESS CONSENT OF THE |
---|
518 | | - | AFFECTED UTILITY COMPANY |
---|
519 | | - | . |
---|
520 | | - | (9) N |
---|
521 | | - | OTHING IN THIS SECTION: |
---|
522 | | - | (a) A |
---|
523 | | - | LTERS OR DIMINISHES THE AUTHORITY OF A LOCAL |
---|
524 | | - | GOVERNMENT TO LAWFULLY EXERCISE ITS POLICE POWERS WITH RESPECT TO |
---|
525 | | - | THE RELOCATION OF UTILITY FACILITIES WITHIN THE LOCAL GOVERNMENT |
---|
526 | | - | BOUNDARIES |
---|
527 | | - | ; |
---|
528 | | - | (b) A |
---|
529 | | - | LTERS EXISTING PROPERTY AGREEMENTS , LICENSES, FRANCHISE |
---|
530 | | - | AGREEMENTS |
---|
531 | | - | , OR OTHER VESTED INTERESTS OF A LOCAL GOVERNMENT OR |
---|
532 | | - | A UTILITY COMPANY ESTABLISHED IN THE EXISTING PROPERTY AGREEMENT |
---|
533 | | - | , |
---|
534 | | - | LICENSE, FRANCHISE AGREEMENT, OR OTHER VESTED INTEREST, INCLUDING |
---|
535 | | - | THE OBLIGATION TO PAY FOR UTILITY RELOCATION |
---|
536 | | - | ; |
---|
537 | | - | (c) A |
---|
538 | | - | LTERS THE TERMS OF ANY FRANCHISE OR LICENSE GRANTED |
---|
539 | | - | PURSUANT TO SECTION |
---|
540 | | - | 31-32-101 OR ARTICLE XX OF THE STATE |
---|
541 | | - | CONSTITUTION |
---|
542 | | - | ; |
---|
543 | | - | (d) A |
---|
544 | | - | LTERS OR DIMINISHES THE LOCAL GOVERNMENT 'S ABILITY TO |
---|
545 | | - | RECOVER COSTS OR DAMAGES FROM ANY PARTY RESPONSIBLE FOR |
---|
546 | | - | HAZARDOUS MATERIAL DISCOVERED IN A PUBLIC ROADWAY |
---|
547 | | - | ; |
---|
548 | | - | (e) A |
---|
549 | | - | LTERS OR DIMINISHES THE UTILITY COMPANY 'S ABILITY TO |
---|
550 | | - | PAGE 11-HOUSE BILL 24-1266 RECOVER COSTS OR DAMAGES RESULTING FROM THE DISCOVERY OF |
---|
551 | | - | HAZARDOUS MATERIAL |
---|
552 | | - | , PREVIOUSLY UNIDENTIFIED UTILITY CONFLICTS, OR |
---|
553 | | - | THE ACTS OR OMISSIONS OF A THIRD PARTY |
---|
554 | | - | ; |
---|
555 | | - | (f) A |
---|
556 | | - | LTERS ANY COMMON LAW OF THE STATE ALLOCATING THE COST |
---|
557 | | - | OF UTILITY RELOCATION WITHIN A PUBLIC RIGHT |
---|
558 | | - | -OF-WAY; OR |
---|
559 | | - | (g) PREVENTS A LOCAL GOVERNMENT FROM PURSUING ALTERNATIVE |
---|
560 | | - | ARRANGEMENTS FOR ROAD IMPROVEMENT PROJECTS |
---|
561 | | - | , IN WHICH CASE |
---|
562 | | - | SUBSECTIONS |
---|
563 | | - | (2) THROUGH (8) OF THIS SECTION DO NOT APPLY. |
---|
564 | | - | SECTION 3. Act subject to petition - effective date - |
---|
565 | | - | applicability. (1) This act takes effect at 12:01 a.m. on the day following |
---|
566 | | - | the expiration of the ninety-day period after final adjournment of the |
---|
567 | | - | general assembly; except that, if a referendum petition is filed pursuant to |
---|
568 | | - | section 1 (3) of article V of the state constitution against this act or an item, |
---|
569 | | - | section, or part of this act within such period, then the act, item, section, or |
---|
570 | | - | part will not take effect unless approved by the people at the general |
---|
571 | | - | election to be held in November 2024 and, in such case, will take effect on |
---|
572 | | - | the date of the official declaration of the vote thereon by the governor. |
---|
573 | | - | PAGE 12-HOUSE BILL 24-1266 (2) This act applies to utility relocation work commencing on or |
---|
574 | | - | after the applicable effective date of this act. |
---|
575 | | - | ____________________________ ____________________________ |
---|
576 | | - | Julie McCluskie Steve Fenberg |
---|
577 | | - | SPEAKER OF THE HOUSE PRESIDENT OF |
---|
578 | | - | OF REPRESENTATIVES THE SENATE |
---|
579 | | - | ____________________________ ____________________________ |
---|
580 | | - | Robin Jones Cindi L. Markwell |
---|
581 | | - | CHIEF CLERK OF THE HOUSE SECRETARY OF |
---|
582 | | - | OF REPRESENTATIVES THE SENATE |
---|
583 | | - | APPROVED________________________________________ |
---|
584 | | - | (Date and Time) |
---|
585 | | - | _________________________________________ |
---|
586 | | - | Jared S. Polis |
---|
587 | | - | GOVERNOR OF THE STATE OF COLORADO |
---|
588 | | - | PAGE 13-HOUSE BILL 24-1266 |
---|
| 235 | + | F UTILITY FACILITIES WERE NOT PREVIOUSLY IDENTIFIED |
---|
| 236 | + | 15 |
---|
| 237 | + | AND RESULT IN A NEWLY DISCOVERED UTILITY CONFLICT , THE LOCAL16 |
---|
| 238 | + | GOVERNMENT, THE AFFECTED UTILITY COMPANY, AND THE THIRD-PARTY17 |
---|
| 239 | + | CONTRACTOR, AS APPLICABLE, SHALL CONFER WITHIN FORTY-EIGHT HOURS18 |
---|
| 240 | + | OF DISCOVERY TO DETERMINE APPROPRIATE RELOCATION PROCEDURES .19 |
---|
| 241 | + | (II) WITHIN TEN BUSINESS DAYS OF THE DISCOVERY OF THE20 |
---|
| 242 | + | UTILITY CONFLICT, THE LOCAL GOVERNMENT AND THE AFFECTED UTILITY21 |
---|
| 243 | + | COMPANY SHALL NEGOTIATE A CLEARANCE LETTER PURSUANT TO22 |
---|
| 244 | + | SUBSECTION (3) OF THIS SECTION.23 |
---|
| 245 | + | (3) (a) TO FACILITATE A UTILITY RELOCATION , A LOCAL24 |
---|
| 246 | + | GOVERNMENT AND AN AFFECTED UTILITY COMPANY SHALL NEGOTIATE IN25 |
---|
| 247 | + | GOOD FAITH AND SHALL ENTER INTO A MUTUALLY AGREEABLE CLEARANCE26 |
---|
| 248 | + | LETTER.27 |
---|
| 249 | + | 1266 |
---|
| 250 | + | -8- (b) THE CLEARANCE LETTER MUST INCLUDE :1 |
---|
| 251 | + | (I) AN ACKNOWLEDGMENT BY THE LOCAL GOVERNMENT AND THE2 |
---|
| 252 | + | UTILITY COMPANY THAT A UTILITY CONFLICT EXISTS ;3 |
---|
| 253 | + | (II) THE SCOPE OF THE UTILITY RELOCATION, INCLUDING THE4 |
---|
| 254 | + | EXTENT OF THE UTILITY FACILITIES NEEDING TO BE RELOCATED AS5 |
---|
| 255 | + | EVIDENCED BY THE PLANS AND SPECIFICATIONS ;6 |
---|
| 256 | + | (III) WHETHER THE UTILITY RELOCATION WILL BE PERFORMED BY7 |
---|
| 257 | + | THE UTILITY COMPANY OR BY A THIRD-PARTY CONTRACTOR AGREED TO BY8 |
---|
| 258 | + | THE UTILITY COMPANY;9 |
---|
| 259 | + | (IV) REQUIREMENTS FOR COORDINATION AMONG THE LOCAL10 |
---|
| 260 | + | GOVERNMENT, THE UTILITY COMPANY, AND ANY THIRD -PARTY11 |
---|
| 261 | + | CONTRACTOR THROUGHOUT THE ROAD IMPROVEMENT PROJECT AND12 |
---|
| 262 | + | UTILITY RELOCATION, INCLUDING THROUGHOUT ANY PREREQUISITE WORK13 |
---|
| 263 | + | THAT NEEDS TO OCCUR BEFORE THE UTILITY RELOCATION ;14 |
---|
| 264 | + | (V) WHICH ENTITY IS RESPONSIBLE FOR TRAFFIC MANAGEMENT15 |
---|
| 265 | + | DURING THE UTILITY RELOCATION;16 |
---|
| 266 | + | (VI) THE NUMBER OF DAYS OF NOTICE THAT THE LOCAL17 |
---|
| 267 | + | GOVERNMENT MUST GIVE TO THE UTILITY COMPANY AHEAD OF THE DATE18 |
---|
| 268 | + | BY WHICH THE UTILITY RELOCATION MUST BE STARTED IN ORDER TO19 |
---|
| 269 | + | ADHERE TO THE ROAD IMPROVEMENT PROJECT SCHEDULE ;20 |
---|
| 270 | + | (VII) AN ESTIMATED SCHEDULE FOR THE PERFORMANCE OF THE21 |
---|
| 271 | + | UTILITY RELOCATION, INCLUDING THE DURATION OF THE UTILITY22 |
---|
| 272 | + | RELOCATION;23 |
---|
| 273 | + | (VIII) A REQUIREMENT OF PROMPT PERFORMANCE OF THE UTILITY24 |
---|
| 274 | + | RELOCATION BY THE UTILITY COMPANY IF THE UTILITY COMPANY IS25 |
---|
| 275 | + | PERFORMING THE UTILITY RELOCATION OR BY THE THIRD -PARTY26 |
---|
| 276 | + | CONTRACTOR AGREED TO BY THE UTILITY COMPANY TO PERFORM THE27 |
---|
| 277 | + | 1266 |
---|
| 278 | + | -9- UTILITY RELOCATION, EXCEPT WHEN PERFORMANCE IS EXCUSED DUE TO1 |
---|
| 279 | + | FORCE MAJEURE, THE DISCOVERY OF HAZARDOUS MATERIAL IN THE PUBLIC2 |
---|
| 280 | + | ROADWAY, OR A CHANGE IN THE SCOPE OR AGREED-TO SCHEDULE OF A3 |
---|
| 281 | + | ROAD IMPROVEMENT PROJECT OR THE PLANS AND SPECIFICATIONS THAT4 |
---|
| 282 | + | AFFECTS THE UTILITY FACILITIES;5 |
---|
| 283 | + | (IX) A REQUIREMENT OF PAYMENT BY THE UTILITY COMPANY FOR6 |
---|
| 284 | + | ACTUAL DAMAGES CAUSED BY THE UTILITY COMPANY'S DELAY IN THE7 |
---|
| 285 | + | PERFORMANCE OF THE UTILITY RELOCATION OR INTERFERENCE WITH THE8 |
---|
| 286 | + | PERFORMANCE OF THE UTILITY RELOCATION BY ANY CONTRACTOR NOT9 |
---|
| 287 | + | HIRED BY THE UTILITY COMPANY; EXCEPT THAT DELAY OR INTERFERENCE10 |
---|
| 288 | + | CAUSED BY THE FOLLOWING WILL NOT BE CHARGED TO THE UTILITY11 |
---|
| 289 | + | COMPANY:12 |
---|
| 290 | + | (A) A FORCE MAJEURE; 13 |
---|
| 291 | + | (B) THE DISCOVERY OF HAZARDOUS MATERIAL IN THE PUBLIC14 |
---|
| 292 | + | ROADWAY; OR15 |
---|
| 293 | + | (C) A CHANGE IN THE SCOPE OR AGREED-TO SCHEDULE OF A ROAD16 |
---|
| 294 | + | IMPROVEMENT PROJECT OR THE PLANS AND SPECIFICATIONS THAT AFFECTS17 |
---|
| 295 | + | THE UTILITY FACILITIES AND THE UTILITY COMPANY'S ABILITY TO PERFORM18 |
---|
| 296 | + | THE RELOCATION WORK AS ESTABLISHED IN THE CLEARANCE LETTER ;19 |
---|
| 297 | + | (X) A REQUIREMENT THAT THE LOCAL GOVERNMENT, AT ITS SOLE20 |
---|
| 298 | + | COST, SURVEY AND STAKE THE LOCATION WHERE THE UTILITY FACILITIES21 |
---|
| 299 | + | WILL BE LOCATED PRIOR TO THE BEGINNING OF THE UTILITY RELOCATION,22 |
---|
| 300 | + | AND THAT THE COST OF ANY REQUIRED RE-STAKING DUE TO THE ACTIONS23 |
---|
| 301 | + | OF A UTILITY COMPANY OR ITS CONTRACTOR BE PAID BY THE UTILITY24 |
---|
| 302 | + | COMPANY;25 |
---|
| 303 | + | (XI) A REQUIREMENT THAT, UPON THE DISCOVERY OF HAZARDOUS26 |
---|
| 304 | + | MATERIAL IN A PUBLIC ROADWAY IN CONNECTION WITH UTILITY27 |
---|
| 305 | + | 1266 |
---|
| 306 | + | -10- RELOCATION, THE UTILITY RELOCATION WORK CEASE UNTIL THE LOCAL1 |
---|
| 307 | + | GOVERNMENT TAKES NECESSARY STEPS TO PROVIDE A UTILITY CORRIDOR2 |
---|
| 308 | + | FREE FROM HAZARDOUS MATERIAL , AND THAT THE LOCAL GOVERNMENT3 |
---|
| 309 | + | IS RESPONSIBLE FOR THE MANAGEMENT , TRANSPORTATION, AND DISPOSAL4 |
---|
| 310 | + | OF ANY SOIL FROM THE PUBLIC RIGHT-OF-WAY CONTAMINATED WITH5 |
---|
| 311 | + | HAZARDOUS MATERIAL ;6 |
---|
| 312 | + | (XII) A REQUIREMENT THAT ALL DESIGN AND CONSTRUCTION OF7 |
---|
| 313 | + | THE UTILITY RELOCATION ARE SUBJECT TO REVIEW AND APPROVAL BY8 |
---|
| 314 | + | ENGINEERS FOR THE LOCAL GOVERNMENT AND FOR THE UTILITY9 |
---|
| 315 | + | COMPANY; AND10 |
---|
| 316 | + | (XIII) A DISPUTE RESOLUTION PROVISION THAT INCLUDES11 |
---|
| 317 | + | MECHANISMS FOR NOTICE OF A FAILURE TO PERFORM IN ACCORDANCE12 |
---|
| 318 | + | WITH THE CLEARANCE LETTER AND FOR A REASONABLE OPPORTUNITY TO13 |
---|
| 319 | + | CURE.14 |
---|
| 320 | + | (c) (I) THE CLEARANCE LETTER MAY ALLOW FOR UTILITY15 |
---|
| 321 | + | COMPANY BETTERMENT AT THE EXPENSE OF THE UTILITY COMPANY;16 |
---|
| 322 | + | EXCEPT THAT ANY UTILITY COMPANY BETTERMENT MUST NOT17 |
---|
| 323 | + | MATERIALLY DELAY THE UTILITY RELOCATION .18 |
---|
| 324 | + | (II) AS USED IN THIS SUBSECTION (3)(c), "UTILITY COMPANY19 |
---|
| 325 | + | BETTERMENT" MEANS ANY UPGRADE OF THE UTILITY FACILITIES BEING20 |
---|
| 326 | + | RELOCATED THAT IS NOT ATTRIBUTABLE TO THE ROAD IMPROVEMENT21 |
---|
| 327 | + | PROJECT AND THAT IS MADE SOLELY FOR THE BENEFIT AND AT THE22 |
---|
| 328 | + | ELECTION OF THE AFFECTED UTILITY COMPANY .23 |
---|
| 329 | + | (4) (a) UPON BEING PROVIDED WRITTEN DOCUMENTATION OF THE24 |
---|
| 330 | + | HORIZONTAL AND VERTICAL LOCATIONS OF THE RELOCATED UTILITY25 |
---|
| 331 | + | FACILITIES AND A STATEMENT BY THE UTILITY COMPANY OR ITS26 |
---|
| 332 | + | CONTRACTOR THAT THE UTILITY FACILITIES ARE RELOCATED IN27 |
---|
| 333 | + | 1266 |
---|
| 334 | + | -11- ACCORDANCE WITH THE APPROVED UTILITY RELOCATION PLANS , A LOCAL1 |
---|
| 335 | + | GOVERNMENT SHALL COMPLETE ITS REVIEW OF THE COMPLETED UTILITY2 |
---|
| 336 | + | RELOCATION AND PROVIDE A WRITTEN DETERMINATION OF WHETHER IT3 |
---|
| 337 | + | ACCEPTS OR REJECTS THE COMPLETED UTILITY RELOCATION WITHIN4 |
---|
| 338 | + | FOURTEEN CALENDAR DAYS OF COMPLETION OF THE RELOCATION OR5 |
---|
| 339 | + | RECEIPT OF THE DOCUMENTATION INDICATING THE LOCATION OF THE6 |
---|
| 340 | + | RELOCATED UTILITY FACILITIES FROM THE UTILITY COMPANY , WHICHEVER7 |
---|
| 341 | + | IS LATER.8 |
---|
| 342 | + | (b) IF THE LOCAL GOVERNMENT ACCEPTS THE UTILITY9 |
---|
| 343 | + | RELOCATION, THE LOCAL GOVERNMENT SHALL PROVIDE ITS WRITTEN10 |
---|
| 344 | + | ACCEPTANCE OF THE UTILITY RELOCATION TO THE UTILITY COMPANY .11 |
---|
| 345 | + | (c) (I) IF THE LOCAL GOVERNMENT REJECTS THE UTILITY12 |
---|
| 346 | + | RELOCATION, THE LOCAL GOVERNMENT SHALL PROVIDE ITS WRITTEN13 |
---|
| 347 | + | REJECTION AND REASONING TO THE UTILITY COMPANY .14 |
---|
| 348 | + | (II) THE UTILITY COMPANY SHALL PROMPTLY MAKE THE15 |
---|
| 349 | + | NECESSARY CHANGES TO THE UTILITY RELOCATION IDENTIFIED IN THE16 |
---|
| 350 | + | WRITTEN REJECTION TO CONFORM WITH THE PLANS AND SPECIFICATIONS17 |
---|
| 351 | + | IDENTIFIED IN THE CLEARANCE LETTER. THE UTILITY COMPANY IS18 |
---|
| 352 | + | RESPONSIBLE FOR PAYMENT OF ACTUAL DAMAGES CAUSED BY ANY DELAY19 |
---|
| 353 | + | IN THE ROAD IMPROVEMENT PROJECT SCHEDULE AS A RESULT OF THE20 |
---|
| 354 | + | NECESSARY CHANGES TO THE UTILITY RELOCATION TO BRING THE21 |
---|
| 355 | + | RELOCATION INTO COMPLIANCE WITH THE PLANS AND SPECIFICATIONS22 |
---|
| 356 | + | IDENTIFIED IN THE CLEARANCE LETTER.23 |
---|
| 357 | + | (d) IF THE LOCAL GOVERNMENT FAILS TO TIMELY PROVIDE THE24 |
---|
| 358 | + | WRITTEN DETERMINATION REQUIRED BY SUBSECTION (4)(a) OF THIS25 |
---|
| 359 | + | SECTION, THE UTILITY RELOCATION IS DEEMED ACCEPTED .26 |
---|
| 360 | + | (e) A UTILITY COMPANY SHALL NOT BE REQUIRED TO PAY FOR27 |
---|
| 361 | + | 1266 |
---|
| 362 | + | -12- RELOCATION OF PREVIOUSLY RELOCATED UTILITY FACILITIES WITHIN TWO1 |
---|
| 363 | + | YEARS FOLLOWING THE ACCEPTANCE OF THE PREVIOUS UTILITY2 |
---|
| 364 | + | RELOCATION BY THE LOCAL GOVERNMENT PURSUANT TO THIS SUBSECTION3 |
---|
| 365 | + | (4), EXCEPT IN THE EVENT OF AN EMERGENCY .4 |
---|
| 366 | + | (5) A LOCAL GOVERNMENT MAY, AFTER OPPORTUNITY FOR RELIEF5 |
---|
| 367 | + | BETWEEN THE LOCAL GOVERNMENT AND THE UTILITY COMPANY6 |
---|
| 368 | + | PURSUANT TO THE DISPUTE RESOLUTION PROCESS OUTLINED IN THE7 |
---|
| 369 | + | CLEARANCE LETTER, WITHHOLD ISSUANCE OF A PERMIT FOR THE LOCATION8 |
---|
| 370 | + | OR INSTALLATION OF OTHER UTILITY FACILITIES IN A PUBLIC ROADWAY TO9 |
---|
| 371 | + | A UTILITY COMPANY UNTIL THE DISPUTE IS RESOLVED, WHICH MAY10 |
---|
| 372 | + | INCLUDE PAYMENT TO THE LOCAL GOVERNMENT FOR ANY ACTUAL11 |
---|
| 373 | + | DAMAGES CAUSED BY THE UTILITY COMPANY'S DELAY IN THE12 |
---|
| 374 | + | PERFORMANCE OF A UTILITY RELOCATION .13 |
---|
| 375 | + | (6) WHEN NECESSARY AND FEASIBLE AND AFTER MUTUAL14 |
---|
| 376 | + | AGREEMENT WITH AN AFFECTED UTILITY COMPANY , A LOCAL15 |
---|
| 377 | + | GOVERNMENT MAY OBTAIN ADDITIONAL PUBLIC RIGHTS -OF-WAY OR16 |
---|
| 378 | + | EASEMENTS TO ACCOMMODATE A UTILITY RELOCATION . THE LOCAL17 |
---|
| 379 | + | GOVERNMENT IS RESPONSIBLE FOR THE COST OF OBTAINING ANY18 |
---|
| 380 | + | ADDITIONAL RIGHT-OF-WAY UNLESS THE ADDITIONAL RIGHT-OF-WAY IS19 |
---|
| 381 | + | ONLY NEEDED TO ACCOMMODATE A UTILITY COMPANY BETTERMENT AND20 |
---|
| 382 | + | IS NOT REQUIRED FOR A ROAD IMPROVEMENT PROJECT .21 |
---|
| 383 | + | (7) A LOCAL GOVERNMENT AND AN AFFECTED UTILITY COMPANY22 |
---|
| 384 | + | SHALL MAKE ARRANGEMENTS FOR FUNDING ANY UTILITY RELOCATION AS23 |
---|
| 385 | + | SPECIFIED IN ANY EASEMENTS, LICENSES, OR OTHER PROPERTY INTERESTS24 |
---|
| 386 | + | OR RIGHTS OF USE HELD BY THE LOCAL GOVERNMENT OR THE UTILITY25 |
---|
| 387 | + | COMPANY. THE RECOVERY OF UNDERGROUND UTILITY LOCATE COSTS, AS26 |
---|
| 388 | + | INCURRED BY THE UTILITY COMPANY, MUST OCCUR THROUGH27 |
---|
| 389 | + | 1266 |
---|
| 390 | + | -13- APPROPRIATE RATE ADJUSTMENT CLAUSES .1 |
---|
| 391 | + | (8) NO PARTY OTHER THAN THE OWNER OF THE UTILITY FACILITIES2 |
---|
| 392 | + | MAY RELOCATE UTILITY FACILITIES WITHOUT THE EXPRESS CONSENT OF3 |
---|
| 393 | + | THE AFFECTED UTILITY COMPANY .4 |
---|
| 394 | + | (9) NOTHING IN THIS SECTION:5 |
---|
| 395 | + | (a) ALTERS OR DIMINISHES THE AUTHORITY OF A LOCAL6 |
---|
| 396 | + | GOVERNMENT TO LAWFULLY EXERCISE ITS POLICE POWERS WITH RESPECT7 |
---|
| 397 | + | TO THE RELOCATION OF UTILITY FACILITIES WITHIN THE LOCAL8 |
---|
| 398 | + | GOVERNMENT BOUNDARIES ;9 |
---|
| 399 | + | (b) ALTERS EXISTING PROPERTY AGREEMENTS, LICENSES,10 |
---|
| 400 | + | FRANCHISE AGREEMENTS, OR OTHER VESTED INTERESTS OF A LOCAL11 |
---|
| 401 | + | GOVERNMENT OR A UTILITY COMPANY ESTABLISHED IN THE EXISTING12 |
---|
| 402 | + | PROPERTY AGREEMENT, LICENSE, FRANCHISE AGREEMENT, OR OTHER13 |
---|
| 403 | + | VESTED INTEREST, INCLUDING THE OBLIGATION TO PAY FOR UTILITY14 |
---|
| 404 | + | RELOCATION;15 |
---|
| 405 | + | (c) ALTERS THE TERMS OF ANY FRANCHISE OR LICENSE GRANTED16 |
---|
| 406 | + | PURSUANT TO SECTION 31-32-101 OR ARTICLE XX OF THE STATE17 |
---|
| 407 | + | CONSTITUTION;18 |
---|
| 408 | + | (d) ALTERS OR DIMINISHES THE LOCAL GOVERNMENT'S ABILITY TO19 |
---|
| 409 | + | RECOVER COSTS OR DAMAGES FROM ANY PARTY RESPONSIBLE FOR20 |
---|
| 410 | + | HAZARDOUS MATERIAL DISCOVERED IN A PUBLIC ROADWAY ;21 |
---|
| 411 | + | (e) ALTERS OR DIMINISHES THE UTILITY COMPANY 'S ABILITY TO22 |
---|
| 412 | + | RECOVER COSTS OR DAMAGES RESULTING FROM THE DISCOVERY OF23 |
---|
| 413 | + | HAZARDOUS MATERIAL, PREVIOUSLY UNIDENTIFIED UTILITY CONFLICTS,24 |
---|
| 414 | + | OR THE ACTS OR OMISSIONS OF A THIRD PARTY; 25 |
---|
| 415 | + | (f) ALTERS ANY COMMON LAW OF THE STATE ALLOCATING THE26 |
---|
| 416 | + | COST OF UTILITY RELOCATION WITHIN A PUBLIC RIGHT -OF-WAY; OR27 |
---|
| 417 | + | 1266 |
---|
| 418 | + | -14- (g) PREVENTS A LOCAL GOVERNMENT FROM PURSUING1 |
---|
| 419 | + | ALTERNATIVE ARRANGEMENTS FOR ROAD IMPROVEMENT PROJECTS , IN2 |
---|
| 420 | + | WHICH CASE SUBSECTIONS (2) THROUGH (8) OF THIS SECTION DO NOT3 |
---|
| 421 | + | APPLY.4 |
---|
| 422 | + | SECTION 3. Act subject to petition - effective date -5 |
---|
| 423 | + | applicability. (1) This act takes effect at 12:01 a.m. on the day following6 |
---|
| 424 | + | the expiration of the ninety-day period after final adjournment of the7 |
---|
| 425 | + | general assembly; except that, if a referendum petition is filed pursuant8 |
---|
| 426 | + | to section 1 (3) of article V of the state constitution against this act or an9 |
---|
| 427 | + | item, section, or part of this act within such period, then the act, item,10 |
---|
| 428 | + | section, or part will not take effect unless approved by the people at the11 |
---|
| 429 | + | general election to be held in November 2024 and, in such case, will take12 |
---|
| 430 | + | effect on the date of the official declaration of the vote thereon by the13 |
---|
| 431 | + | governor.14 |
---|
| 432 | + | (2) This act applies to utility relocation work commencing on or15 |
---|
| 433 | + | after the applicable effective date of this act.16 |
---|
| 434 | + | 1266 |
---|