1-General Assembly Substitute Bill No. 5370
2-February Session, 2018 *_____HB05370GL____031618____*
1+General Assembly Raised Bill No. 5370
2+February Session, 2018 LCO No. 1738
3+ *01738_______GL_*
4+Referred to Committee on GENERAL LAW
5+Introduced by:
6+(GL)
37
48 General Assembly
59
6-Substitute Bill No. 5370
10+Raised Bill No. 5370
711
812 February Session, 2018
913
10-*_____HB05370GL____031618____*
14+LCO No. 1738
15+
16+*01738_______GL_*
17+
18+Referred to Committee on GENERAL LAW
19+
20+Introduced by:
21+
22+(GL)
1123
1224 AN ACT CONCERNING CHANGE ORDERS IN CONSTRUCTION CONTRACTS.
1325
1426 Be it enacted by the Senate and House of Representatives in General Assembly convened:
1527
1628 Section 1. Subsection (a) of section 42-158j of the 2018 supplement to the general statutes is repealed and the following is substituted in lieu thereof (Effective October 1, 2018):
1729
18-(a) Each construction contract shall contain the following provisions: (1) A requirement that the owner pay any amounts due to any contractor in a direct contractual relationship with the owner, or due to any subcontractor or supplier in a direct contractual relationship with the contractor, whether for labor performed or materials furnished, not later than thirty days after the date any written request for such payment has been made to the owner by such contractor, subcontractor or supplier; (2) a requirement that the contractor pay any amounts due any subcontractor or supplier, whether for labor performed or materials furnished, not later than thirty days after the date the contractor receives payment from the owner which encompasses labor performed or materials furnished by such subcontractor or supplier; [and] (3) a requirement that the contractor shall include in each of its subcontracts a provision requiring each subcontractor and supplier to pay any amounts due any of its subcontractors or suppliers, whether for labor performed or materials furnished, not later than thirty days after the date such subcontractor or supplier receives a payment from the contractor which encompasses labor performed or materials furnished by such subcontractor or supplier; and (4) a requirement that, for all pending or approved change orders or directives to perform extra work totaling twenty-five thousand dollars or more, the minimum allowable rate of overhead and profit to be paid to any contractor or subcontractor who performs such extra work shall be not less than fifteen per cent of the total value of such extra work, including, but not limited to, the costs of all labor, direct supervision, material and equipment required to perform such extra work.
30+(a) Each construction contract shall contain the following provisions: (1) A requirement that the owner pay any amounts due to any contractor in a direct contractual relationship with the owner, or due to any subcontractor or supplier in a direct contractual relationship with the contractor, whether for labor performed or materials furnished, not later than thirty days after the date any written request for such payment has been made to the owner by such contractor, subcontractor or supplier; (2) a requirement that the contractor pay any amounts due any subcontractor or supplier, whether for labor performed or materials furnished, not later than thirty days after the date the contractor receives payment from the owner which encompasses labor performed or materials furnished by such subcontractor or supplier; [and] (3) a requirement that the contractor shall include in each of its subcontracts a provision requiring each subcontractor and supplier to pay any amounts due any of its subcontractors or suppliers, whether for labor performed or materials furnished, not later than thirty days after the date such subcontractor or supplier receives a payment from the contractor which encompasses labor performed or materials furnished by such subcontractor or supplier; and (4) a requirement that, for all pending or approved change orders or directives to perform extra work, the minimum allowable rate of overhead and profit to be paid to any contractor or subcontractor who performs such extra work shall be not less than fifteen per cent of the total value of such extra work, including, but not limited to, the costs of all labor, direct supervision, material and equipment required to perform such extra work.
1931
2032 Sec. 2. Section 49-41b of the general statutes is repealed and the following is substituted in lieu thereof (Effective October 1, 2018):
2133
2234 When any public work is awarded by a contract for which a payment bond is required by section 49-41 and such contract contains a provision requiring the general or prime contractor under such contract to furnish a performance bond in the full amount of the contract price, the following shall apply:
2335
2436 (1) In the case of a contract advertised by the Department of Administrative Services or any other state agency, except as specified in subdivision (2) of this section, (A) the awarding authority shall not withhold more than seven and one-half per cent from any periodic or final payment which is otherwise properly due to the general or prime contractor under the terms of such contract, provided, when fifty per cent of the contract is completed, said amount shall be reduced to five per cent, and (B) any such general or prime contractor shall not withhold from any subcontractor more than (i) seven and one-half per cent from any periodic or final payment which is otherwise due to the subcontractor, or (ii) the amount withheld by the awarding authority from such general or prime contractor under subparagraph (A) of this subdivision, whichever is less, provided, when fifty per cent of the contract is completed, said amount shall be reduced to five per cent. Payment shall be made not later than ninety days after a complete application for payment demonstrating that fifty per cent contract completion has been submitted to the awarding authority. Notwithstanding the provisions of this subdivision (1), the awarding authority shall establish an early release program with respect to periodic payments by general or prime contractors to subcontractors.
2537
2638 (2) In the case of a contract advertised by the state Department of Transportation, (A) the department shall not withhold more than two and one-half per cent from any periodic or final payment which is otherwise properly due to the general or prime contractor under the terms of such contract, and (B) any such general or prime contractor shall not withhold more than two and one-half per cent from any periodic or final payment which is otherwise due to any subcontractor.
2739
2840 (3) If the awarding authority is a municipality, (A) the municipality shall not withhold more than five per cent from any periodic or final payment which is otherwise properly due to the general or prime contractor under the terms of such contract, and (B) any such general or prime contractor shall not withhold more than five per cent from any periodic or final payment which is otherwise due to any subcontractor.
2941
30-(4) In the case of a contract advertised by the Department of Administrative Services or any other state agency, except the state Department of Transportation, or if the awarding authority is a municipality or a municipal agency, a requirement that, for all pending or approved change orders or directives to perform extra work totaling twenty-five thousand dollars or more pursuant to the contract, the minimum allowable rate of overhead and profit to be paid to any contractor or subcontractor who performs such extra work shall be not less than fifteen per cent of the total value of such extra work, including, but not limited to, the costs of all labor, direct supervision, material and equipment required to perform such extra work.
42+(4) In the case of a contract advertised by the Department of Administrative Services or any other state agency, except the state Department of Transportation, or if the awarding authority is a municipality or a municipal agency, a requirement that, for all pending or approved change orders or directives to perform extra work pursuant to the contract, the minimum allowable rate of overhead and profit to be paid to any contractor or subcontractor who performs such extra work shall be not less than fifteen per cent of the total value of such extra work, including, but not limited to, the costs of all labor, direct supervision, material and equipment required to perform such extra work.
3143
3244
3345
3446
3547 This act shall take effect as follows and shall amend the following sections:
3648 Section 1 October 1, 2018 42-158j(a)
3749 Sec. 2 October 1, 2018 49-41b
3850
3951 This act shall take effect as follows and shall amend the following sections:
4052
4153 Section 1
4254
4355 October 1, 2018
4456
4557 42-158j(a)
4658
4759 Sec. 2
4860
4961 October 1, 2018
5062
5163 49-41b
5264
65+Statement of Purpose:
5366
67+To require a minimum amount be included in private and public commercial construction contracts for work performed pursuant to a change order.
5468
55-GL Joint Favorable Subst.
56-
57-GL
58-
59-Joint Favorable Subst.
69+[Proposed deletions are enclosed in brackets. Proposed additions are indicated by underline, except that when the entire text of a bill or resolution or a section of a bill or resolution is new, it is not underlined.]