25 | | - | Section 1. Section 42-158j of the general statutes is repealed and the 1 |
---|
26 | | - | following is substituted in lieu thereof (Effective October 1, 2025): 2 |
---|
27 | | - | (a) Each construction contract shall contain the following provisions: 3 |
---|
28 | | - | (1) A requirement that the owner pay [any] all amounts due to any 4 |
---|
29 | | - | contractor in a direct contractual relationship with the owner, or due to 5 |
---|
30 | | - | any subcontractor or supplier in a direct contractual relationship with 6 |
---|
31 | | - | the contractor, whether for labor performed or materials furnished, not 7 |
---|
32 | | - | later than thirty days after the date any written request for such 8 |
---|
33 | | - | payment has been made to the owner by such contractor, subcontractor 9 |
---|
34 | | - | or supplier; (2) a requirement that the contractor pay [any] all amounts 10 |
---|
35 | | - | due any subcontractor or supplier, whether for labor performed or 11 |
---|
36 | | - | materials furnished, not later than [twenty-five] seven days after the 12 |
---|
37 | | - | date the contractor receives payment from the owner which 13 |
---|
38 | | - | encompasses labor performed or materials furnished by such 14 |
---|
39 | | - | subcontractor or supplier or sixty days after the date the subcontractor 15 |
---|
40 | | - | Committee Bill No. 5685 |
---|
41 | | - | |
---|
42 | | - | |
---|
43 | | - | LCO No. 5155 2 of 5 |
---|
44 | | - | |
---|
45 | | - | or supplier performed such labor or furnished such materials, 16 |
---|
46 | | - | whichever occurs first; and (3) a requirement that the contractor shall 17 |
---|
47 | | - | include in each of its subcontracts a provision requiring each 18 |
---|
48 | | - | subcontractor and supplier to pay [any] all amounts due any of its 19 |
---|
49 | | - | subcontractors or suppliers, whether for labor performed or materials 20 |
---|
50 | | - | furnished, not later than twenty-five days after the date such 21 |
---|
51 | | - | [subcontractor or supplier receives a payment from the contractor which 22 |
---|
52 | | - | encompasses] labor was performed or materials were furnished by such 23 |
---|
53 | | - | subcontractor or supplier. 24 |
---|
54 | | - | (b) Each payment requisition submitted by a contractor or 25 |
---|
55 | | - | subcontractor in accordance with the requirements of subsection (a) of 26 |
---|
56 | | - | this section shall include a statement showing the status of all pending 27 |
---|
57 | | - | construction change orders, other pending change directives and 28 |
---|
58 | | - | approved changes to the original contract or subcontract. Such 29 |
---|
59 | | - | statement shall identify the pending construction change orders and 30 |
---|
60 | | - | other pending change directives, and shall include the date such change 31 |
---|
61 | | - | orders and directives were initiated, the costs associated with their 32 |
---|
62 | | - | performance and a description of any work completed. As used in this 33 |
---|
63 | | - | section, "pending construction change order" or "other pending change 34 |
---|
64 | | - | directive" means an authorized directive for extra work that has been 35 |
---|
65 | | - | issued to a contractor or a subcontractor. 36 |
---|
66 | | - | (c) (1) If payment is not made by an owner in accordance with the 37 |
---|
67 | | - | requirements of subdivision (1) of subsection (a) of this section or any 38 |
---|
68 | | - | applicable construction contract, such contractor, subcontractor or 39 |
---|
69 | | - | supplier shall set forth its claim against the owner through notice by 40 |
---|
70 | | - | registered or certified mail. All amounts due from the owner pursuant 41 |
---|
71 | | - | to this subsection and subdivision (1) of subsection (a) of this section 42 |
---|
72 | | - | shall be limited to the amount owed to the contractor by the owner for 43 |
---|
73 | | - | work performed under the contract at the date such notice is provided. 44 |
---|
74 | | - | (2) If payment is not made by a contractor in accordance with the 45 |
---|
75 | | - | requirements of subdivision (2) of subsection (a) of this section or any 46 |
---|
76 | | - | applicable construction contract, the subcontractor or supplier shall set 47 |
---|
77 | | - | Committee Bill No. 5685 |
---|
78 | | - | |
---|
79 | | - | |
---|
80 | | - | LCO No. 5155 3 of 5 |
---|
81 | | - | |
---|
82 | | - | forth its claim against the contractor through notice by registered or 48 |
---|
83 | | - | certified mail. 49 |
---|
84 | | - | (3) If payment is not made by a subcontractor or supplier in 50 |
---|
85 | | - | accordance with the provisions of subdivision (3) of subsection (a) of 51 |
---|
86 | | - | this section, the subcontractor or supplier to whom money is owed shall 52 |
---|
87 | | - | set forth its claim against the subcontractor or supplier who has failed 53 |
---|
88 | | - | to comply with the provisions of said subdivision (3) through notice by 54 |
---|
89 | | - | registered or certified mail. 55 |
---|
90 | | - | (4) Ten days after the receipt of any notice specified in subdivisions 56 |
---|
91 | | - | (1), (2) and (3) of this subsection, the owner, contractor, subcontractor or 57 |
---|
92 | | - | supplier, as the case may be, shall be liable for interest on the amount 58 |
---|
93 | | - | due and owing at the rate of one per cent per month. Such interest shall 59 |
---|
94 | | - | accrue beginning on the date any such notice is received. In addition, 60 |
---|
95 | | - | such owner, contractor, subcontractor or supplier, upon written 61 |
---|
96 | | - | demand from the party providing such notice, shall be required to place 62 |
---|
97 | | - | funds in the amount of the claim, plus such interest of one per cent per 63 |
---|
98 | | - | month, in an interest-bearing escrow account in a bank in this state, 64 |
---|
99 | | - | provided such owner, contractor, subcontractor or supplier may refuse 65 |
---|
100 | | - | to place the funds in escrow on the grounds that the party making such 66 |
---|
101 | | - | demand has not substantially performed the work or supplied the 67 |
---|
102 | | - | materials according to the terms of the construction contract or that the 68 |
---|
103 | | - | funds so demanded are not due under the owner's contract with the 69 |
---|
104 | | - | contractor. In the event that such owner, contractor, subcontractor or 70 |
---|
105 | | - | supplier refuses to place such funds in escrow and such owner, 71 |
---|
106 | | - | contractor, subcontractor or supplier is found to have unreasonably 72 |
---|
107 | | - | withheld payment due a party providing such notice, such owner, 73 |
---|
108 | | - | contractor, subcontractor or supplier shall be liable to the party making 74 |
---|
109 | | - | demand for payment of such funds and for reasonable attorneys' fees 75 |
---|
110 | | - | plus interest on the amount due and owing at the rate of one per cent 76 |
---|
111 | | - | per month. In addition, any owner, contractor, subcontractor or supplier 77 |
---|
112 | | - | who is found to have withheld payments to a party providing such 78 |
---|
113 | | - | notice in bad faith shall be liable for ten per cent damages. 79 |
---|
114 | | - | Committee Bill No. 5685 |
---|
115 | | - | |
---|
116 | | - | |
---|
117 | | - | LCO No. 5155 4 of 5 |
---|
118 | | - | |
---|
119 | | - | (d) No payment may be withheld from a subcontractor or supplier 80 |
---|
120 | | - | for work performed or materials furnished because of a dispute between 81 |
---|
121 | | - | a contractor and another contractor, subcontractor or supplier. 82 |
---|
122 | | - | (e) This section shall not be construed to prohibit progress payments 83 |
---|
123 | | - | prior to final payment of the contract and is applicable to all 84 |
---|
124 | | - | subcontractors and suppliers for material or labor whether they have 85 |
---|
125 | | - | contracted directly with the contractor or with some other subcontractor 86 |
---|
126 | | - | on the work. Each owner that enters into a contract under this section 87 |
---|
127 | | - | and fails or neglects to make payment to a contractor for labor and 88 |
---|
128 | | - | materials supplied under a contract, as required pursuant to this section, 89 |
---|
129 | | - | shall, upon demand of any person who has not been paid by the 90 |
---|
130 | | - | contractor for such labor and materials supplied in the performance of 91 |
---|
131 | | - | the work under the contract, promptly pay the person for such labor or 92 |
---|
132 | | - | materials. Demand for payment shall be served on the owner and a copy 93 |
---|
133 | | - | of each demand shall be sent to the contractor by certified mail, return 94 |
---|
134 | | - | receipt requested to any address at which the owner and contractor 95 |
---|
135 | | - | conduct business. If the owner fails to make such payment, the person 96 |
---|
136 | | - | shall have a direct right of action against the owner in the superior court 97 |
---|
137 | | - | for the judicial district in which the project is located. The owner's 98 |
---|
138 | | - | obligations for direct payments to the contractor, subcontractors or 99 |
---|
139 | | - | suppliers giving notice pursuant to this section shall be limited to the 100 |
---|
140 | | - | amount owed to the contractor by the owner for work performed under 101 |
---|
141 | | - | the contract at the date such notice is provided. 102 |
---|
142 | | - | (f) Any provision in a construction contract that violates the 103 |
---|
143 | | - | provisions of this section or purports to waive or release any right of a 104 |
---|
144 | | - | contractor, subcontractor or supplier under this section shall be void 105 |
---|
145 | | - | and of no effect. 106 |
---|
146 | | - | This act shall take effect as follows and shall amend the following |
---|
147 | | - | sections: |
---|
148 | | - | |
---|
149 | | - | Section 1 October 1, 2025 42-158j |
---|
150 | | - | |
---|
151 | | - | Committee Bill No. 5685 |
---|
152 | | - | |
---|
153 | | - | |
---|
154 | | - | LCO No. 5155 5 of 5 |
---|
155 | | - | |
---|
| 24 | + | That (1) the general statutes be amended to prohibit the use of pay-if-1 |
---|
| 25 | + | paid clauses in construction contracts, and (2) section 42-158j of the 2 |
---|
| 26 | + | general statutes be amended to ensure payment from a contractor to a 3 |
---|
| 27 | + | subcontractor is made (A) not later than seven days after the date the 4 |
---|
| 28 | + | contractor receives payment from the owner that encompasses labor 5 |
---|
| 29 | + | performed or materials furnished by the subcontractor, or (B) sixty days 6 |
---|
| 30 | + | after the date of satisfactory completion of the labor performed or 7 |
---|
| 31 | + | materials furnished by the subcontractor, whichever is sooner. 8 |
---|