1-HOUSE OF REPRESENTATIVES H.B. NO. 1784 THIRTY-FIRST LEGISLATURE, 2022 H.D. 1 STATE OF HAWAII A BILL FOR AN ACT RELATING TO BUILDING INSPECTIONS. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
1+HOUSE OF REPRESENTATIVES H.B. NO. 1784 THIRTY-FIRST LEGISLATURE, 2022 STATE OF HAWAII A BILL FOR AN ACT relating to building inspections. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
22
33 HOUSE OF REPRESENTATIVES H.B. NO. 1784
4-THIRTY-FIRST LEGISLATURE, 2022 H.D. 1
4+THIRTY-FIRST LEGISLATURE, 2022
55 STATE OF HAWAII
66
77 HOUSE OF REPRESENTATIVES
88
99 H.B. NO.
1010
1111 1784
1212
1313 THIRTY-FIRST LEGISLATURE, 2022
1414
15-H.D. 1
15+
1616
1717 STATE OF HAWAII
1818
1919
2020
2121
2222
2323
2424
2525
2626
2727
2828
2929
3030
3131 A BILL FOR AN ACT
3232
3333
3434
3535
3636
3737 relating to building inspections.
3838
3939
4040
4141
4242
4343 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
4444
4545
4646
47- SECTION 1. The legislature finds that the state building code council is charged with safeguarding life, property, and the general welfare by establishing and overseeing the state building codes. However, the codes do not specifically require that the structural integrity of buildings be regularly inspected. As evidenced by the shocking building collapse of the Surfside, Florida condominium building in June 2021, structural concerns may not always be apparent or addressed by general maintenance. The legislature further finds that Hawaii's salty ocean environment can cause building structures to weaken and corrode. The anticipated increase in hurricanes caused by global warming makes ensuring building safety even more essential. The legislature recognizes that some buildings may be planning to undergo renovation and consequently has included the option for a building owner to apply to the state building code council for a waiver where the exterior walls of the building have been substantially restored during the seven years immediately preceding the date of the required inspection. The purpose of this Act is to require that buildings five or more stories in height be periodically inspected to identify issues with their structural integrity. SECTION 2. Chapter 107, Hawaii Revised Statutes, is amended by adding a new section to part II to be appropriately designated and to read as follows: "§107- Periodic inspection of buildings; requirements. (a) Building inspections shall be required as follows: (1) The owner of each affected building shall be responsible for retaining a professional to conduct periodic inspections of exterior walls and any appurtenances thereto and prepare and file a report on the inspection as required by subsection (c); (2) For affected buildings in existence on the effective date of this Act, the first periodic inspection required by this section shall be conducted by December 31, 2026; (3) Following the initial periodic inspection, an affected building shall be periodically inspected and a corresponding report shall be filed on a seven-year cycle; and (4) If all exterior walls of an affected building have been substantially restored during the seven years immediately preceding the date of any required inspection, the owner may apply to the council for a waiver of the required inspection. The owner shall submit with the waiver application any information that the council determines is necessary to enable it to evaluate the request. The council may grant the waiver if it determines that the recent exterior wall restoration obviates the need for an inspection until the next inspection cycle. (b) Procedures for inspections shall be as follows: (1) Before inspecting an affected building, the retained professional shall review previous reports, inspections, and evidence of repairs made during the seven-year period being reported on including confirmation that all areas previously determined to require remediation to be completed during the period being reported on have been addressed; (2) The inspection shall be conducted by or under the supervision of the professional, and performed in accordance with procedures based on ASTM E2270, Standard Practice for Periodic Inspection of Building Facades for Unsafe Conditions. The professional shall determine the scope of the required inspection based on the known history of the affected building, nature of the materials used, and conditions observed; (3) The professional shall determine methods employed in the inspection; provided that the methods shall include a physical, hands-on inspection of the affected building. The professional may use additional methods of inspection as deemed appropriate; provided that a physical inspection from a scaffold or other observation platform shall be required for a representative sample of the exterior wall. The professional shall determine what constitutes a representative sample; (4) The professional shall employ the appropriate professional standard of care to detect distressed conditions including delaminating, separating, spalling, corrosion, splitting or fracturing of material or components, as well as movement or displacement indicative of unsound facade materials or loss of structural support. If a distressed condition is identified, the professional shall order any other inspections and tests that may be required to determine the significance and probable cause of the observed distress; (5) During the course of the inspection, photographs shall be taken or drawings made to properly document the location of all conditions observed that are either unsafe or safe with a repair and maintenance program; and (6) Upon discovery of any unsafe condition the professional shall immediately notify the owner of the affected building by electronic mail, and shall, within twelve hours of discovery, notify the respective county agency with responsibility over planning in writing and in an electronic format determined by the council. (c) Reports shall be prepared as follows: (1) The professional shall submit to the owner of the affected building a written report as to the result of each inspection, certifying that the inspection was performed and completed in accordance with this section, and detailing all conditions not classified as safe. The professional shall also submit a summary of the written report to the council in a form determined by the council. The council may by rule impose a processing fee to cover the cost of report review and evaluation that must be paid upon submission of the summary of the written report. If the report identifies an unsafe condition, the professional shall file the full report with the council in writing and in an electronic format determined by the council within twenty-four hours of completion of the report. The owner or its agent shall retain all written reports submitted pursuant to this subsection and keep them readily available for inspection by the council; (2) The report shall include, on its front page, the name and license number of the professional and be signed, sealed, and dated by the professional in accordance with the professional licensing and registration laws of the State, and shall include the following: (A) The affected building's address and the location from the nearest intersection; (B) The name, mailing address, and telephone number of the owner of the affected building and of the owner's agent or person in charge, possession, or control of the affected building, if any; (C) A description of the affected building, including number of stories, height, plan dimensions, usage, age and type of exterior wall construction, and system of water management; (D) A brief history of any settlements, repairs, and revisions to exterior enclosures, if available; (E) The date of the start and completion of the inspection, a detailed description of the procedures used in making the inspection, and the extent and location of all physical inspections performed; (F) A report of all conditions including but not limited to significant deterioration and movement observed, a statement concerning the apparent water-tightness of the exterior surfaces, and the deleterious effects of exterior appurtenances. The report shall classify each condition as safe, unsafe, or safe with a repair and maintenance program; (G) The probable causes of the reported conditions, to the extent they can be determined; (H) The status of the exterior maintenance; (I) For any conditions listed in the previously filed report as unsafe or as safe with a repair and maintenance program, if applicable, a statement as to whether such conditions have been repaired or maintained as recommended in that report; (J) Recommendations for repairs or maintenance, if appropriate, including the recommended time frame for the repairs or maintenance to be performed; (K) The classification of the affected building as "unsafe", "safe with a repair and maintenance program", or "safe"; (L) Photographs or drawings documenting the locations of any conditions that are either unsafe or safe with a repair and maintenance program; (M) A statement by the professional indicating which repairs or maintenance require the obtaining of work permits prior to their commencement; (N) A statement signed by the owner or agent of the affected building, acknowledging receipt of a copy of the report and acknowledging all required repairs or maintenance, if any, and the recommended time frame for performing those repairs or maintenance; (O) The professional's certification that the physical inspection was performed in accordance with procedures based on ASTM E2270, with applicable rules and regulations, and within the appropriate professional standard of care; (P) The professional's seal and signature; and (Q) Other matters as the council may require; and (3) The professional may submit an amended report within thirty days of the initial submission. The amended report shall clearly indicate any changes from the initial report and all reasons for such changes. (d) Within twenty-four hours of being notified of an unsafe condition by a professional, the owner of the affected building shall take any actions necessary to protect public safety, including but not limited to erecting temporary secure safety railings or barriers, protective sidewalk walk-throughs, fences, and safety netting. These actions shall be considered as an effort to remedy an emergency situation and appropriate permit applications shall be submitted to the council within three days of their commencement. Within ten days of the receipt or filing of a report identifying an unsafe condition, the owner of the affected building shall commence work to correct the condition, and work shall continue without interruption until the unsafe condition has been corrected, unless there has been an unforeseen delay including but not limited to inclement weather or a labor strike. Within two weeks after remediation of the unsafe condition, the professional shall inspect the building again and file a detailed amended report stating the updated condition of the building with the council. (e) The owner of the affected building shall be responsible for ensuring that the conditions described in the report as "safe with a repair and maintenance program" are repaired and the actions identified by the professional are completed within the time frame designated by the professional or by such time as is necessary to prevent a condition from becoming an unsafe condition, whichever is earlier. (f) The council may grant: (1) An extension of time of up to ninety days to begin the repairs required to remove an unsafe condition or to repair a safe with a repair and maintenance program condition after receipt and review of an initial extension application submitted by the professional that includes: (A) Proof that the relevant premises of the affected building have been made safe by means of a temporary secure safety railing or barrier, walk-through, fence, or other appropriate measures; (B) A copy of the contract to perform the work necessary to remedy the unsafe condition; and (C) The professional's estimate of the length of time required for repairs, and a notarized affidavit by the owner of the affected building or its agent that the required repairs will be completed within such time; and (2) A further extension of time shall be considered only upon receipt and review of a further extension application that details that one of the following is met: (A) The work has been substantially completed, but there has been an unforeseen delay in final completion, including but not limited to inclement weather or a labor strike; (B) Unforeseen circumstances relating to the affected building including but not limited to fire or collapse; or (C) The nature of a hazard requires more than ninety days to remediate including but not limited to when building a new wall is required. (g) The owner of the affected building may appeal the findings set forth in the professional's initial report or amended report to the council. The appeal shall be filed within thirty days of the receipt or filing of the report, and shall include a second professional's report. The filing and pendency of the appeal shall stay the requirement for making repairs as set forth in subsection (d), but shall not stay the requirement for taking actions necessary to protect public safety. Upon consideration of any appeal, the council shall issue a recommendation to the building official either to grant the appeal, deny the appeal, or grant the appeal with such proposed modifications to the professional's findings as the board deems consistent with the intent of this section. The building official thereafter shall make the final determination on the appeal. (h) As used in this section: "Affected building" means any building five or more stories in height. "Appurtenance" means an accessory to a building that includes but is not limited to exterior fixtures, flagpoles, signs, parapets, copings, guard rails, window frames (including hardware and lights), window guards, window air conditioners, flower boxes, and similar items. "Professional" means a state licensed professional engineer experienced in the practice of structural engineering or a state licensed architect knowledgeable in the design, construction, and inspection of building exteriors. "Safe" means a condition of an exterior building wall or any appurtenance thereto that is neither unsafe nor safe with a repair and maintenance program. "Safe with a repair and maintenance program" means that the professional does not consider the condition of the affected building's exterior wall or any appurtenance thereto to be unsafe at the time of inspection but requires repairs or maintenance within a time period designated by the professional in order to prevent its deterioration into an unsafe condition. "Unsafe" means a condition of the affected building's exterior wall or any appurtenance thereto or part thereof that is dangerous to persons or property and requires prompt remedial action. (i) The council shall adopt pursuant to chapter 91 to implement this section." SECTION 3. Section 107-24, Hawaii Revised Statutes, is amended to read as follows: "§107-24 Authority and duties of the council. (a) Any law to the contrary notwithstanding, the council shall establish the Hawaii state building codes. (b) The council shall appoint a subcommittee comprising the four council members representing county building officials, whose duty shall be to recommend any necessary or desirable state amendments to the codes and standards identified in section 107-25. Any recommended state amendments shall require the unanimous agreement of the subcommittee. (c) The council shall adopt, amend, or update codes and standards identified in section 107-25 on a staggered basis as established by the council; provided that adoption of a code or standard shall be within two years of the official publication date of the code or standard, pursuant to chapter 92, and exempt from the requirements of chapter 91. If the council does not adopt a code or standard identified in section 107-25 within the two-year time period, that code or standard shall automatically become part of the Hawaii state building code until superseded by the adoption of an amended version of the code or standard by the council pursuant to this subsection. (d) The council may appoint other investigative, technical expertise committees, which may include council members. (e) The council shall consult with general building contractor associations and building trade associations to gather information and recommendations on construction practices and training relevant to building codes and standards. (f) The council may make expenditures for technical references, equipment and supplies, and other operating expenses, and may contract for the conduct of research studies and other technical services. (g) The council may provide education and technical training and administrative assistance in the form of services or grants at the state and county levels relating to the implementation and enforcement of the Hawaii state building codes adopted pursuant to this part. (h) At the end of each fiscal year, the council shall submit a written report to the governor on the council's activities, including the codes and standards adopted, amended, or updated by the council. (i) The council may conduct reviews of periodic inspection reports of certain buildings pursuant to section 107- ." SECTION 4. New statutory material is underscored. SECTION 5. This Act shall take effect on January 1, 2050.
47+ SECTION 1. The legislature finds that the state building code council is charged with safeguarding life, property, and the general welfare by establishing and overseeing the state building codes. However, the codes do not specifically require that the structural integrity of buildings be regularly inspected. As evidenced by the shocking building collapse of the Surfside, Florida condominium building in June 2021, structural concerns may not always be apparent or addressed by general maintenance. The legislature further finds that Hawaii's salty ocean environment can cause building structures to weaken and corrade. The anticipated increase in hurricanes caused by global warming make ensuring building safety even more essential. The legislature recognizes that some buildings may be planning to undergo renovation and consequently has included the option for a building owner to apply to the state building code council for a waiver where the exterior walls of the building have been substantially restored during the seven years immediately preceding the date of the required inspection. The purpose of this Act is to require that buildings five or more stories in height to be periodically inspected to identify issues with their structural integrity. SECTION 2. Chapter 107, Hawaii Revised Statutes, is amended by adding a new section to part II to be appropriately designated and to read as follows: "§107- Periodic inspection of buildings; requirements. (a) Building inspections shall be required as follows: (1) The owner of each affected building shall be responsible for retaining a professional to conduct periodic inspections of exterior walls and any appurtenances thereto and to prepare and file a report on the inspection as required by subsection (c); (2) For affected buildings, the first periodic inspection required by this section shall be conducted by December 31, 2026; (3) Following the initial periodic inspection, an affected building shall be periodically inspected and a corresponding report shall be filed on a seven-year cycle; and (4) If all exterior walls of an affected building have been substantially restored during the seven years immediately preceding the date of any required inspection, the owner may apply to the council for a waiver of the required inspection. The owner shall submit with the waiver application any information that the council determines is necessary to enable it to evaluate the request. The council may grant the waiver if it determines that the recent exterior wall restoration obviates the need for an inspection until the next inspection cycle. (b) Procedures for inspections shall be as follows: (1) Before inspecting an affected building, the retained professional shall review previous reports, inspections, and evidence of repairs made during the five-year period being reported on including confirmation that all areas previously determined to require remediation to be completed during the period being reported on have been addressed; (2) The inspection shall be conducted by or under the supervision of the professional, and performed in accordance with procedures based on ASTM E2270, Standard Practice for Periodic Inspection of Building Facades for Unsafe Conditions. The professional shall determine the scope of the required inspection based on the known history of the affected building, nature of the materials used, and conditions observed; (3) The professional shall determine methods employed in the inspection; provided that the methods shall include a physical, hands-on inspection of the affected building. The professional may use additional methods of inspection as deemed appropriate; provided that a physical inspection from a scaffold or other observation platform is required for a representative sample of the exterior wall. The professional shall determine what constitutes a representative sample; (4) The professional shall employ the appropriate professional standard of care to detect distressed conditions including delaminating, separating, spalling, corrosion, splitting or fracturing of material or components, as well as movement or displacement indicative of unsound facade materials or loss of structural support. If a distressed condition is identified, the professional shall order any other inspections and tests that may be required to determine the significance and probable cause of the observed distress; (5) During the course of the inspection, photographs shall be taken or drawings made to properly document the location of all conditions observed that are either unsafe or safe with a repair and maintenance program; and (6) Upon discovery of any unsafe condition the professional shall immediately notify the owner of the affected building by electronic mail, and shall, within twelve hours of discovery, notify the department in writing and in an electronic format determined by the council. (c) Reports shall be prepared as follows: (1) The professional shall submit to the owner of the affected building a written report as to the result of each inspection, certifying that the inspection was performed and completed in accordance with this section, and detailing all conditions not classified as safe. The professional shall also submit a summary of the written report to the council in a form determined by the council. The council may by rule impose a processing fee to cover the cost of report review and evaluation that must be paid upon submission of the summary of the written report. If the report identifies an unsafe condition, the professional, shall file the full report with the council in writing and in an electronic format determined by the council within twenty-four hours of completion of the report. The owner or its agent shall retain all written reports submitted pursuant to this subsection and keep them readily available for inspection by the council; (2) The report shall include, on its front page, the name and license number of the professional and be signed, sealed, and dated by the professional in accordance with the professional licensing and registration laws of the State, and shall include the following: (A) The affected building's address and the location from the nearest intersection; (B) The name, mailing address, and telephone number of the owner of the affected building and of the owner's agent or person in charge, possession, or control of the affected building, if any; (C) A description of the affected building, including number of stories, height, plan dimensions, usage, age and type of exterior wall construction, and system of water management; (D) A brief history of any settlements, repairs, and revisions to exterior enclosures, if available; (E) The date of the start and completion of the inspection, a detailed description of the procedures used in making the inspection, and the extent and location of all physical inspections performed; (F) A report of all conditions including but not limited to significant deterioration and movement observed as well as a statement concerning the apparent water-tightness of the exterior surfaces, and the deleterious effects of exterior appurtenances. The report shall classify each condition as safe, unsafe, or safe with a repair and maintenance program; (G) The probable causes of the reported conditions, to the extent they can be determined; (H) The status of the exterior maintenance; (I) For any conditions listed in the previously filed report, as unsafe or as safe with a maintenance and repair program, if applicable, a statement as to whether such conditions have been repaired or maintained as recommended in that report; (J) Recommendations for repairs or maintenance, if appropriate, including the recommended time frame for the repairs or maintenance to be performed; (K) The classification of the affected building as "unsafe", "safe with a repair and maintenance program", or "safe"; (L) Photographs or drawings documenting the locations of any conditions that are either unsafe or safe with a repair and maintenance program; (M) A statement by the professional indicating which repairs or maintenance require the obtaining of work permits prior to their commencement; (N) A statement signed by the owner or agent of the affected building, acknowledging receipt of a copy of the report and acknowledging all required repairs or maintenance, if any, and the recommended time frame for performing those repairs or maintenance; (O) The professional's certification that the physical inspection was performed in accordance with procedures based on ASTM E2270, with applicable rules and regulations, and within the appropriate professional standard of care; (P) The professional's seal and signature; and (Q) Other matters as the council may require; and (3) The professional may submit an amended report within thirty days of the initial submission. The amended report shall clearly indicate any changes from the initial report and all reasons for such changes. (d) Within twenty-four hours of being notified of an unsafe condition by a professional, the owner of the affected building shall take any actions necessary to protect public safety, including but not limited to erecting temporary secure safety railings or barriers, protective sidewalk walk-throughs, fences, and safety netting. These actions shall be considered as an effort to remedy an emergency situation and appropriate permit applications shall be submitted to the council within three days of their commencement. Within ten days of the receipt or filing of a report identifying an unsafe condition, the owner of the affected building shall commence work to correct the condition, and work shall continue without interruption until the unsafe condition has been corrected, unless there has been an unforeseen delay including but not limited to inclement weather or a labor strike. Within two weeks after remediation of the unsafe condition, the professional shall inspect the building again and file a detailed amended report stating the updated condition of the building with the council. (e) The owner of the affected building shall be responsible for ensuring that the conditions described in the report as "safe with a repair and maintenance program" are repaired and the actions identified by the professional are completed within the time frame designated by the professional or by such time as is necessary to prevent a condition from becoming an unsafe condition, whichever is earlier. (f) The council may grant: (1) An extension of time of up to ninety days to begin the repairs required to remove an unsafe condition or to repair a safe with a repair and maintenance program condition after receipt and review of an initial extension application submitted by the professional that includes: (A) Proof that the relevant premises of the affected building have been made safe by means of a temporary secure safety railing or barrier, walk-through, fence, or other appropriate measures; (B) A copy of the contract to perform the work necessary to remedy the unsafe condition; and (C) The professional's estimate of the length of time required for repairs, and a notarized affidavit by the owner of the affected building or its agent that the required repairs will be completed within such time; (2) A further extension of time shall be considered only upon receipt and review of a further extension application that details that one of the following is met: (A) The work has been substantially completed, but there has been an unforeseen delay in final completion, including but not limited to inclement weather or a labor strike; (B) Unforeseen circumstances relating to the affected building including but not limited to fire or collapse; or (C) The nature of a hazard requires more than ninety days to remediate including but not limited to when a new wall is required to be built. (g) The owner of the affected building may appeal the findings set forth in the professional's initial report or amended report to the council. The appeal shall be filed within thirty days of the receipt or filing of the report, and shall include a second professional's report. The filing and pendency of the appeal shall stay the requirement for making repairs as set forth in subsection (d), but shall not stay the requirement for taking actions necessary to protect public safety. Upon consideration of any appeal, the council shall issue a recommendation to the building official either to grant the appeal, deny the appeal, or grant the appeal with such proposed modifications to the professional's findings as the board deems consistent with the intent of this section. The building official thereafter shall make the final determination on the appeal. (h) As used in this section: "Affected building" means any building five or more stories in height. "Appurtenance" means an accessory to a building that includes but is not limited to exterior fixtures, flagpoles, signs, parapets, copings, guard rails, window frames (including hardware and lights), window guards, window air conditioners, flower boxes, and similar items. "Professional" means a State of Hawaii licensed professional engineer experienced in the practice of structural engineering or a State of Hawaii licensed architect knowledgeable in the design, construction, and inspection of building exteriors. "Safe" means a condition of an exterior building wall or any appurtenance thereto that is neither unsafe nor safe with a repair and maintenance program. "Safe with a repair and maintenance program" means that the professional does not consider the condition of the affected building's exterior wall or any appurtenance thereto to be unsafe at the time of inspection but requires repairs or maintenance within a time period designated by the professional in order to prevent its deterioration into an unsafe condition. "Unsafe" means a condition of the affected building's exterior wall or any appurtenance thereto or part thereof that is dangerous to persons or property and requires prompt remedial action. (i) The council shall adopt rules in accordance with chapter 91 to implement this section." SECTION 3. New statutory material is underscored. SECTION 4. This Act shall take effect upon its approval. INTRODUCED BY: _____________________________
4848
4949 SECTION 1. The legislature finds that the state building code council is charged with safeguarding life, property, and the general welfare by establishing and overseeing the state building codes. However, the codes do not specifically require that the structural integrity of buildings be regularly inspected. As evidenced by the shocking building collapse of the Surfside, Florida condominium building in June 2021, structural concerns may not always be apparent or addressed by general maintenance.
5050
51- The legislature further finds that Hawaii's salty ocean environment can cause building structures to weaken and corrode. The anticipated increase in hurricanes caused by global warming makes ensuring building safety even more essential. The legislature recognizes that some buildings may be planning to undergo renovation and consequently has included the option for a building owner to apply to the state building code council for a waiver where the exterior walls of the building have been substantially restored during the seven years immediately preceding the date of the required inspection.
51+ The legislature further finds that Hawaii's salty ocean environment can cause building structures to weaken and corrade. The anticipated increase in hurricanes caused by global warming make ensuring building safety even more essential. The legislature recognizes that some buildings may be planning to undergo renovation and consequently has included the option for a building owner to apply to the state building code council for a waiver where the exterior walls of the building have been substantially restored during the seven years immediately preceding the date of the required inspection.
5252
53- The purpose of this Act is to require that buildings five or more stories in height be periodically inspected to identify issues with their structural integrity.
53+ The purpose of this Act is to require that buildings five or more stories in height to be periodically inspected to identify issues with their structural integrity.
5454
5555 SECTION 2. Chapter 107, Hawaii Revised Statutes, is amended by adding a new section to part II to be appropriately designated and to read as follows:
5656
5757 "§107- Periodic inspection of buildings; requirements. (a) Building inspections shall be required as follows:
5858
59- (1) The owner of each affected building shall be responsible for retaining a professional to conduct periodic inspections of exterior walls and any appurtenances thereto and prepare and file a report on the inspection as required by subsection (c);
59+ (1) The owner of each affected building shall be responsible for retaining a professional to conduct periodic inspections of exterior walls and any appurtenances thereto and to prepare and file a report on the inspection as required by subsection (c);
6060
61- (2) For affected buildings in existence on the effective date of this Act, the first periodic inspection required by this section shall be conducted by December 31, 2026;
61+ (2) For affected buildings, the first periodic inspection required by this section shall be conducted by December 31, 2026;
6262
6363 (3) Following the initial periodic inspection, an affected building shall be periodically inspected and a corresponding report shall be filed on a seven-year cycle; and
6464
6565 (4) If all exterior walls of an affected building have been substantially restored during the seven years immediately preceding the date of any required inspection, the owner may apply to the council for a waiver of the required inspection. The owner shall submit with the waiver application any information that the council determines is necessary to enable it to evaluate the request. The council may grant the waiver if it determines that the recent exterior wall restoration obviates the need for an inspection until the next inspection cycle.
6666
6767 (b) Procedures for inspections shall be as follows:
6868
69- (1) Before inspecting an affected building, the retained professional shall review previous reports, inspections, and evidence of repairs made during the seven-year period being reported on including confirmation that all areas previously determined to require remediation to be completed during the period being reported on have been addressed;
69+ (1) Before inspecting an affected building, the retained professional shall review previous reports, inspections, and evidence of repairs made during the five-year period being reported on including confirmation that all areas previously determined to require remediation to be completed during the period being reported on have been addressed;
7070
7171 (2) The inspection shall be conducted by or under the supervision of the professional, and performed in accordance with procedures based on ASTM E2270, Standard Practice for Periodic Inspection of Building Facades for Unsafe Conditions. The professional shall determine the scope of the required inspection based on the known history of the affected building, nature of the materials used, and conditions observed;
7272
73- (3) The professional shall determine methods employed in the inspection; provided that the methods shall include a physical, hands-on inspection of the affected building. The professional may use additional methods of inspection as deemed appropriate; provided that a physical inspection from a scaffold or other observation platform shall be required for a representative sample of the exterior wall. The professional shall determine what constitutes a representative sample;
73+ (3) The professional shall determine methods employed in the inspection; provided that the methods shall include a physical, hands-on inspection of the affected building. The professional may use additional methods of inspection as deemed appropriate; provided that a physical inspection from a scaffold or other observation platform is required for a representative sample of the exterior wall. The professional shall determine what constitutes a representative sample;
7474
7575 (4) The professional shall employ the appropriate professional standard of care to detect distressed conditions including delaminating, separating, spalling, corrosion, splitting or fracturing of material or components, as well as movement or displacement indicative of unsound facade materials or loss of structural support. If a distressed condition is identified, the professional shall order any other inspections and tests that may be required to determine the significance and probable cause of the observed distress;
7676
7777 (5) During the course of the inspection, photographs shall be taken or drawings made to properly document the location of all conditions observed that are either unsafe or safe with a repair and maintenance program; and
7878
79- (6) Upon discovery of any unsafe condition the professional shall immediately notify the owner of the affected building by electronic mail, and shall, within twelve hours of discovery, notify the respective county agency with responsibility over planning in writing and in an electronic format determined by the council.
79+ (6) Upon discovery of any unsafe condition the professional shall immediately notify the owner of the affected building by electronic mail, and shall, within twelve hours of discovery, notify the department in writing and in an electronic format determined by the council.
8080
8181 (c) Reports shall be prepared as follows:
8282
83- (1) The professional shall submit to the owner of the affected building a written report as to the result of each inspection, certifying that the inspection was performed and completed in accordance with this section, and detailing all conditions not classified as safe. The professional shall also submit a summary of the written report to the council in a form determined by the council. The council may by rule impose a processing fee to cover the cost of report review and evaluation that must be paid upon submission of the summary of the written report. If the report identifies an unsafe condition, the professional shall file the full report with the council in writing and in an electronic format determined by the council within twenty-four hours of completion of the report. The owner or its agent shall retain all written reports submitted pursuant to this subsection and keep them readily available for inspection by the council;
83+ (1) The professional shall submit to the owner of the affected building a written report as to the result of each inspection, certifying that the inspection was performed and completed in accordance with this section, and detailing all conditions not classified as safe. The professional shall also submit a summary of the written report to the council in a form determined by the council. The council may by rule impose a processing fee to cover the cost of report review and evaluation that must be paid upon submission of the summary of the written report. If the report identifies an unsafe condition, the professional, shall file the full report with the council in writing and in an electronic format determined by the council within twenty-four hours of completion of the report. The owner or its agent shall retain all written reports submitted pursuant to this subsection and keep them readily available for inspection by the council;
8484
8585 (2) The report shall include, on its front page, the name and license number of the professional and be signed, sealed, and dated by the professional in accordance with the professional licensing and registration laws of the State, and shall include the following:
8686
8787 (A) The affected building's address and the location from the nearest intersection;
8888
8989 (B) The name, mailing address, and telephone number of the owner of the affected building and of the owner's agent or person in charge, possession, or control of the affected building, if any;
9090
9191 (C) A description of the affected building, including number of stories, height, plan dimensions, usage, age and type of exterior wall construction, and system of water management;
9292
9393 (D) A brief history of any settlements, repairs, and revisions to exterior enclosures, if available;
9494
9595 (E) The date of the start and completion of the inspection, a detailed description of the procedures used in making the inspection, and the extent and location of all physical inspections performed;
9696
97- (F) A report of all conditions including but not limited to significant deterioration and movement observed, a statement concerning the apparent water-tightness of the exterior surfaces, and the deleterious effects of exterior appurtenances. The report shall classify each condition as safe, unsafe, or safe with a repair and maintenance program;
97+ (F) A report of all conditions including but not limited to significant deterioration and movement observed as well as a statement concerning the apparent water-tightness of the exterior surfaces, and the deleterious effects of exterior appurtenances. The report shall classify each condition as safe, unsafe, or safe with a repair and maintenance program;
9898
9999 (G) The probable causes of the reported conditions, to the extent they can be determined;
100100
101101 (H) The status of the exterior maintenance;
102102
103- (I) For any conditions listed in the previously filed report as unsafe or as safe with a repair and maintenance program, if applicable, a statement as to whether such conditions have been repaired or maintained as recommended in that report;
103+ (I) For any conditions listed in the previously filed report, as unsafe or as safe with a maintenance and repair program, if applicable, a statement as to whether such conditions have been repaired or maintained as recommended in that report;
104104
105105 (J) Recommendations for repairs or maintenance, if appropriate, including the recommended time frame for the repairs or maintenance to be performed;
106106
107107 (K) The classification of the affected building as "unsafe", "safe with a repair and maintenance program", or "safe";
108108
109109 (L) Photographs or drawings documenting the locations of any conditions that are either unsafe or safe with a repair and maintenance program;
110110
111111 (M) A statement by the professional indicating which repairs or maintenance require the obtaining of work permits prior to their commencement;
112112
113113 (N) A statement signed by the owner or agent of the affected building, acknowledging receipt of a copy of the report and acknowledging all required repairs or maintenance, if any, and the recommended time frame for performing those repairs or maintenance;
114114
115115 (O) The professional's certification that the physical inspection was performed in accordance with procedures based on ASTM E2270, with applicable rules and regulations, and within the appropriate professional standard of care;
116116
117117 (P) The professional's seal and signature; and
118118
119119 (Q) Other matters as the council may require; and
120120
121121 (3) The professional may submit an amended report within thirty days of the initial submission. The amended report shall clearly indicate any changes from the initial report and all reasons for such changes.
122122
123123 (d) Within twenty-four hours of being notified of an unsafe condition by a professional, the owner of the affected building shall take any actions necessary to protect public safety, including but not limited to erecting temporary secure safety railings or barriers, protective sidewalk walk-throughs, fences, and safety netting. These actions shall be considered as an effort to remedy an emergency situation and appropriate permit applications shall be submitted to the council within three days of their commencement. Within ten days of the receipt or filing of a report identifying an unsafe condition, the owner of the affected building shall commence work to correct the condition, and work shall continue without interruption until the unsafe condition has been corrected, unless there has been an unforeseen delay including but not limited to inclement weather or a labor strike. Within two weeks after remediation of the unsafe condition, the professional shall inspect the building again and file a detailed amended report stating the updated condition of the building with the council.
124124
125125 (e) The owner of the affected building shall be responsible for ensuring that the conditions described in the report as "safe with a repair and maintenance program" are repaired and the actions identified by the professional are completed within the time frame designated by the professional or by such time as is necessary to prevent a condition from becoming an unsafe condition, whichever is earlier.
126126
127127 (f) The council may grant:
128128
129129 (1) An extension of time of up to ninety days to begin the repairs required to remove an unsafe condition or to repair a safe with a repair and maintenance program condition after receipt and review of an initial extension application submitted by the professional that includes:
130130
131131 (A) Proof that the relevant premises of the affected building have been made safe by means of a temporary secure safety railing or barrier, walk-through, fence, or other appropriate measures;
132132
133133 (B) A copy of the contract to perform the work necessary to remedy the unsafe condition; and
134134
135- (C) The professional's estimate of the length of time required for repairs, and a notarized affidavit by the owner of the affected building or its agent that the required repairs will be completed within such time; and
135+ (C) The professional's estimate of the length of time required for repairs, and a notarized affidavit by the owner of the affected building or its agent that the required repairs will be completed within such time;
136136
137137 (2) A further extension of time shall be considered only upon receipt and review of a further extension application that details that one of the following is met:
138138
139139 (A) The work has been substantially completed, but there has been an unforeseen delay in final completion, including but not limited to inclement weather or a labor strike;
140140
141141 (B) Unforeseen circumstances relating to the affected building including but not limited to fire or collapse; or
142142
143- (C) The nature of a hazard requires more than ninety days to remediate including but not limited to when building a new wall is required.
143+ (C) The nature of a hazard requires more than ninety days to remediate including but not limited to when a new wall is required to be built.
144144
145145 (g) The owner of the affected building may appeal the findings set forth in the professional's initial report or amended report to the council. The appeal shall be filed within thirty days of the receipt or filing of the report, and shall include a second professional's report. The filing and pendency of the appeal shall stay the requirement for making repairs as set forth in subsection (d), but shall not stay the requirement for taking actions necessary to protect public safety.
146146
147147 Upon consideration of any appeal, the council shall issue a recommendation to the building official either to grant the appeal, deny the appeal, or grant the appeal with such proposed modifications to the professional's findings as the board deems consistent with the intent of this section. The building official thereafter shall make the final determination on the appeal.
148148
149149 (h) As used in this section:
150150
151151 "Affected building" means any building five or more stories in height.
152152
153153 "Appurtenance" means an accessory to a building that includes but is not limited to exterior fixtures, flagpoles, signs, parapets, copings, guard rails, window frames (including hardware and lights), window guards, window air conditioners, flower boxes, and similar items.
154154
155- "Professional" means a state licensed professional engineer experienced in the practice of structural engineering or a state licensed architect knowledgeable in the design, construction, and inspection of building exteriors.
155+ "Professional" means a State of Hawaii licensed professional engineer experienced in the practice of structural engineering or a State of Hawaii licensed architect knowledgeable in the design, construction, and inspection of building exteriors.
156156
157157 "Safe" means a condition of an exterior building wall or any appurtenance thereto that is neither unsafe nor safe with a repair and maintenance program.
158158
159159 "Safe with a repair and maintenance program" means that the professional does not consider the condition of the affected building's exterior wall or any appurtenance thereto to be unsafe at the time of inspection but requires repairs or maintenance within a time period designated by the professional in order to prevent its deterioration into an unsafe condition.
160160
161161 "Unsafe" means a condition of the affected building's exterior wall or any appurtenance thereto or part thereof that is dangerous to persons or property and requires prompt remedial action.
162162
163- (i) The council shall adopt pursuant to chapter 91 to implement this section."
163+ (i) The council shall adopt rules in accordance with chapter 91 to implement this section."
164164
165- SECTION 3. Section 107-24, Hawaii Revised Statutes, is amended to read as follows:
165+ SECTION 3. New statutory material is underscored.
166166
167- "§107-24 Authority and duties of the council. (a) Any law to the contrary notwithstanding, the council shall establish the Hawaii state building codes.
168-
169- (b) The council shall appoint a subcommittee comprising the four council members representing county building officials, whose duty shall be to recommend any necessary or desirable state amendments to the codes and standards identified in section 107-25. Any recommended state amendments shall require the unanimous agreement of the subcommittee.
170-
171- (c) The council shall adopt, amend, or update codes and standards identified in section 107-25 on a staggered basis as established by the council; provided that adoption of a code or standard shall be within two years of the official publication date of the code or standard, pursuant to chapter 92, and exempt from the requirements of chapter 91. If the council does not adopt a code or standard identified in section 107-25 within the two-year time period, that code or standard shall automatically become part of the Hawaii state building code until superseded by the adoption of an amended version of the code or standard by the council pursuant to this subsection.
172-
173- (d) The council may appoint other investigative, technical expertise committees, which may include council members.
174-
175- (e) The council shall consult with general building contractor associations and building trade associations to gather information and recommendations on construction practices and training relevant to building codes and standards.
176-
177- (f) The council may make expenditures for technical references, equipment and supplies, and other operating expenses, and may contract for the conduct of research studies and other technical services.
178-
179- (g) The council may provide education and technical training and administrative assistance in the form of services or grants at the state and county levels relating to the implementation and enforcement of the Hawaii state building codes adopted pursuant to this part.
180-
181- (h) At the end of each fiscal year, the council shall submit a written report to the governor on the council's activities, including the codes and standards adopted, amended, or updated by the council.
182-
183- (i) The council may conduct reviews of periodic inspection reports of certain buildings pursuant to section 107- ."
184-
185- SECTION 4. New statutory material is underscored.
186-
187- SECTION 5. This Act shall take effect on January 1, 2050.
167+ SECTION 4. This Act shall take effect upon its approval.
188168
189169
190170
191- Report Title: Buildings; Inspections; Structural Integrity; State Building Code; State Building Code Council Description: Requires periodic inspections of certain walls and appurtenances of buildings five or more stories in height. Requires the state building code council to review the periodic inspection reports. Effective 1/1/2050. (HD1) The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
171+INTRODUCED BY: _____________________________
172+
173+INTRODUCED BY:
174+
175+_____________________________
176+
177+
178+
179+
180+
181+ Report Title: Buildings; Inspections; Structural Integrity; State Building Code Description: Requires periodic inspections of certain walls and appurtenances of buildings five or more stories in height. The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
182+
183+
192184
193185
194186
195187 Report Title:
196188
197-Buildings; Inspections; Structural Integrity; State Building Code; State Building Code Council
189+Buildings; Inspections; Structural Integrity; State Building Code
198190
199191
200192
201193 Description:
202194
203-Requires periodic inspections of certain walls and appurtenances of buildings five or more stories in height. Requires the state building code council to review the periodic inspection reports. Effective 1/1/2050. (HD1)
195+Requires periodic inspections of certain walls and appurtenances of buildings five or more stories in height.
204196
205197
206198
207199
208200
209201
210202
211203 The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.