1 | 1 | | HOUSE OF REPRESENTATIVES H.B. NO. 2001 THIRTY-FIRST LEGISLATURE, 2022 STATE OF HAWAII A BILL FOR AN ACT rELATING TO capital improvement projects for the benefit of the twenty-first representative district. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII: |
---|
2 | 2 | | |
---|
3 | 3 | | HOUSE OF REPRESENTATIVES H.B. NO. 2001 |
---|
4 | 4 | | THIRTY-FIRST LEGISLATURE, 2022 |
---|
5 | 5 | | STATE OF HAWAII |
---|
6 | 6 | | |
---|
7 | 7 | | HOUSE OF REPRESENTATIVES |
---|
8 | 8 | | |
---|
9 | 9 | | H.B. NO. |
---|
10 | 10 | | |
---|
11 | 11 | | 2001 |
---|
12 | 12 | | |
---|
13 | 13 | | THIRTY-FIRST LEGISLATURE, 2022 |
---|
14 | 14 | | |
---|
15 | 15 | | |
---|
16 | 16 | | |
---|
17 | 17 | | STATE OF HAWAII |
---|
18 | 18 | | |
---|
19 | 19 | | |
---|
20 | 20 | | |
---|
21 | 21 | | |
---|
22 | 22 | | |
---|
23 | 23 | | |
---|
24 | 24 | | |
---|
25 | 25 | | |
---|
26 | 26 | | |
---|
27 | 27 | | |
---|
28 | 28 | | |
---|
29 | 29 | | |
---|
30 | 30 | | |
---|
31 | 31 | | A BILL FOR AN ACT |
---|
32 | 32 | | |
---|
33 | 33 | | |
---|
34 | 34 | | |
---|
35 | 35 | | |
---|
36 | 36 | | |
---|
37 | 37 | | rELATING TO capital improvement projects for the benefit of the twenty-first representative district. |
---|
38 | 38 | | |
---|
39 | 39 | | |
---|
40 | 40 | | |
---|
41 | 41 | | |
---|
42 | 42 | | |
---|
43 | 43 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII: |
---|
44 | 44 | | |
---|
45 | 45 | | |
---|
46 | 46 | | |
---|
47 | 47 | | SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $10,400,000 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of financing capital improvement projects for the twenty-first representative district, as follows: To be expended by the department of education: A. Ala Wai elementary school, Oahu Plans, design, equipment, and construction to extend walkways in front of six classroom buildings to provide additional space for outdoor learning. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $197,000 Total funding $200,000 B. Kaimuki middle school, Oahu Plans, design, equipment, and construction to expand parking lot. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $1,597,000 Total funding $1,600,000 C. Kaimuki middle school, Oahu Plans, design, equipment, and construction add a non-covered walkway from the cafeteria to the physical education building. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $197,000 Total funding $200,000 D. Kaimuki high school, Oahu Plans, design, equipment, and construction to install Cisco phones on campus. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $247,000 Total funding $250,000 E. Kaimuki high school, Oahu Plans, design, equipment, and construction to replace all cabling (horizontal and backbone), install Informacast (paging), install speakers throughout the campus, and replace the uninterruptible power supply in all buildings' intermediate distribution frame and main distribution frame. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $797,000 Total funding $800,000 F. Kuhio elementary school, Oahu Plans, design, equipment, and construction to repave the parking lot and repair damage caused by tree roots. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $ 97,000 Total funding $100,000 G. Kuhio elementary school, Oahu Plans, design, equipment, and construction to repaint the interior of the cafeteria. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $47,000 Total funding $50,000 H. Kuhio elementary school, Oahu Plans, design, equipment, and construction for the installation of lighting for the campus and the installation of a security system. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $497,000 Total funding $500,000 I. Lunalilo elementary school, Oahu Design and construction for covered multipurpose space, campus security improvements, and ground and infrastructure improvements. Design $ 500,000 Construction $3,000,000 Total funding $3,500,000 J. Liholiho elementary school, Oahu Plans, design, equipment, and construction for a concrete pad over grassy area. Plans $ 1,000 Design $ 1,000 Equipment $ 1,000 Construction $ 997,000 Total funding $1,000,000 K. Washington middle school, Oahu Design, equipment, and construction for telecom infrastructure update. Design $ 200,000 Equipment $ 200,000 Construction $1,800,000 Total funding $2,200,000 SECTION 2. The appropriation made for the capital improvement project authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date. SECTION 3. The sums appropriated shall be expended by the department of education for the purposes of this Act. SECTION 4. This Act shall take effect on July 1, 2022. INTRODUCED BY: _____________________________ |
---|
48 | 48 | | |
---|
49 | 49 | | SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $10,400,000 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of financing capital improvement projects for the twenty-first representative district, as follows: |
---|
50 | 50 | | |
---|
51 | 51 | | To be expended by the department of education: |
---|
52 | 52 | | |
---|
53 | 53 | | A. Ala Wai elementary school, Oahu |
---|
54 | 54 | | |
---|
55 | 55 | | Plans, design, equipment, and construction to extend walkways in front of six classroom buildings to provide additional space for outdoor learning. |
---|
56 | 56 | | |
---|
57 | 57 | | Plans $ 1,000 |
---|
58 | 58 | | |
---|
59 | 59 | | Design $ 1,000 |
---|
60 | 60 | | |
---|
61 | 61 | | Equipment $ 1,000 |
---|
62 | 62 | | |
---|
63 | 63 | | Construction $197,000 |
---|
64 | 64 | | |
---|
65 | 65 | | Total funding $200,000 |
---|
66 | 66 | | |
---|
67 | 67 | | B. Kaimuki middle school, Oahu |
---|
68 | 68 | | |
---|
69 | 69 | | Plans, design, equipment, and construction to expand parking lot. |
---|
70 | 70 | | |
---|
71 | 71 | | Plans $ 1,000 |
---|
72 | 72 | | |
---|
73 | 73 | | Design $ 1,000 |
---|
74 | 74 | | |
---|
75 | 75 | | Equipment $ 1,000 |
---|
76 | 76 | | |
---|
77 | 77 | | Construction $1,597,000 |
---|
78 | 78 | | |
---|
79 | 79 | | Total funding $1,600,000 |
---|
80 | 80 | | |
---|
81 | 81 | | C. Kaimuki middle school, Oahu |
---|
82 | 82 | | |
---|
83 | 83 | | Plans, design, equipment, and construction add a non-covered walkway from the cafeteria to the physical education building. |
---|
84 | 84 | | |
---|
85 | 85 | | Plans $ 1,000 |
---|
86 | 86 | | |
---|
87 | 87 | | Design $ 1,000 |
---|
88 | 88 | | |
---|
89 | 89 | | Equipment $ 1,000 |
---|
90 | 90 | | |
---|
91 | 91 | | Construction $197,000 |
---|
92 | 92 | | |
---|
93 | 93 | | Total funding $200,000 |
---|
94 | 94 | | |
---|
95 | 95 | | D. Kaimuki high school, Oahu |
---|
96 | 96 | | |
---|
97 | 97 | | Plans, design, equipment, and construction to install Cisco phones on campus. |
---|
98 | 98 | | |
---|
99 | 99 | | Plans $ 1,000 |
---|
100 | 100 | | |
---|
101 | 101 | | Design $ 1,000 |
---|
102 | 102 | | |
---|
103 | 103 | | Equipment $ 1,000 |
---|
104 | 104 | | |
---|
105 | 105 | | Construction $247,000 |
---|
106 | 106 | | |
---|
107 | 107 | | Total funding $250,000 |
---|
108 | 108 | | |
---|
109 | 109 | | E. Kaimuki high school, Oahu |
---|
110 | 110 | | |
---|
111 | 111 | | Plans, design, equipment, and construction to replace all cabling (horizontal and backbone), install Informacast (paging), install speakers throughout the campus, and replace the uninterruptible power supply in all buildings' intermediate distribution frame and main distribution frame. |
---|
112 | 112 | | |
---|
113 | 113 | | Plans $ 1,000 |
---|
114 | 114 | | |
---|
115 | 115 | | Design $ 1,000 |
---|
116 | 116 | | |
---|
117 | 117 | | Equipment $ 1,000 |
---|
118 | 118 | | |
---|
119 | 119 | | Construction $797,000 |
---|
120 | 120 | | |
---|
121 | 121 | | Total funding $800,000 |
---|
122 | 122 | | |
---|
123 | 123 | | F. Kuhio elementary school, Oahu |
---|
124 | 124 | | |
---|
125 | 125 | | Plans, design, equipment, and construction to repave the parking lot and repair damage caused by tree roots. |
---|
126 | 126 | | |
---|
127 | 127 | | Plans $ 1,000 |
---|
128 | 128 | | |
---|
129 | 129 | | Design $ 1,000 |
---|
130 | 130 | | |
---|
131 | 131 | | Equipment $ 1,000 |
---|
132 | 132 | | |
---|
133 | 133 | | Construction $ 97,000 |
---|
134 | 134 | | |
---|
135 | 135 | | Total funding $100,000 |
---|
136 | 136 | | |
---|
137 | 137 | | G. Kuhio elementary school, Oahu |
---|
138 | 138 | | |
---|
139 | 139 | | Plans, design, equipment, and construction to repaint the interior of the cafeteria. |
---|
140 | 140 | | |
---|
141 | 141 | | Plans $ 1,000 |
---|
142 | 142 | | |
---|
143 | 143 | | Design $ 1,000 |
---|
144 | 144 | | |
---|
145 | 145 | | Equipment $ 1,000 |
---|
146 | 146 | | |
---|
147 | 147 | | Construction $47,000 |
---|
148 | 148 | | |
---|
149 | 149 | | Total funding $50,000 |
---|
150 | 150 | | |
---|
151 | 151 | | H. Kuhio elementary school, Oahu |
---|
152 | 152 | | |
---|
153 | 153 | | Plans, design, equipment, and construction for the installation of lighting for the campus and the installation of a security system. |
---|
154 | 154 | | |
---|
155 | 155 | | Plans $ 1,000 |
---|
156 | 156 | | |
---|
157 | 157 | | Design $ 1,000 |
---|
158 | 158 | | |
---|
159 | 159 | | Equipment $ 1,000 |
---|
160 | 160 | | |
---|
161 | 161 | | Construction $497,000 |
---|
162 | 162 | | |
---|
163 | 163 | | Total funding $500,000 |
---|
164 | 164 | | |
---|
165 | 165 | | I. Lunalilo elementary school, Oahu |
---|
166 | 166 | | |
---|
167 | 167 | | Design and construction for covered multipurpose space, campus security improvements, and ground and infrastructure improvements. |
---|
168 | 168 | | |
---|
169 | 169 | | Design $ 500,000 |
---|
170 | 170 | | |
---|
171 | 171 | | Construction $3,000,000 |
---|
172 | 172 | | |
---|
173 | 173 | | Total funding $3,500,000 |
---|
174 | 174 | | |
---|
175 | 175 | | J. Liholiho elementary school, Oahu |
---|
176 | 176 | | |
---|
177 | 177 | | Plans, design, equipment, and construction for a concrete pad over grassy area. |
---|
178 | 178 | | |
---|
179 | 179 | | Plans $ 1,000 |
---|
180 | 180 | | |
---|
181 | 181 | | Design $ 1,000 |
---|
182 | 182 | | |
---|
183 | 183 | | Equipment $ 1,000 |
---|
184 | 184 | | |
---|
185 | 185 | | Construction $ 997,000 |
---|
186 | 186 | | |
---|
187 | 187 | | Total funding $1,000,000 |
---|
188 | 188 | | |
---|
189 | 189 | | K. Washington middle school, Oahu |
---|
190 | 190 | | |
---|
191 | 191 | | Design, equipment, and construction for telecom infrastructure update. |
---|
192 | 192 | | |
---|
193 | 193 | | Design $ 200,000 |
---|
194 | 194 | | |
---|
195 | 195 | | Equipment $ 200,000 |
---|
196 | 196 | | |
---|
197 | 197 | | Construction $1,800,000 |
---|
198 | 198 | | |
---|
199 | 199 | | Total funding $2,200,000 |
---|
200 | 200 | | |
---|
201 | 201 | | SECTION 2. The appropriation made for the capital improvement project authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date. |
---|
202 | 202 | | |
---|
203 | 203 | | SECTION 3. The sums appropriated shall be expended by the department of education for the purposes of this Act. |
---|
204 | 204 | | |
---|
205 | 205 | | SECTION 4. This Act shall take effect on July 1, 2022. |
---|
206 | 206 | | |
---|
207 | 207 | | |
---|
208 | 208 | | |
---|
209 | 209 | | INTRODUCED BY: _____________________________ |
---|
210 | 210 | | |
---|
211 | 211 | | INTRODUCED BY: |
---|
212 | 212 | | |
---|
213 | 213 | | _____________________________ |
---|
214 | 214 | | |
---|
215 | 215 | | |
---|
216 | 216 | | |
---|
217 | 217 | | |
---|
218 | 218 | | |
---|
219 | 219 | | Report Title: CIP; 21st Representative District; GO Bonds; Appropriation Description: Authorizes the issuance of general obligation bonds and appropriates moneys for capital improvement projects for the benefit of the 21st Representative District. The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent. |
---|
220 | 220 | | |
---|
221 | 221 | | |
---|
222 | 222 | | |
---|
223 | 223 | | |
---|
224 | 224 | | |
---|
225 | 225 | | Report Title: |
---|
226 | 226 | | |
---|
227 | 227 | | CIP; 21st Representative District; GO Bonds; Appropriation |
---|
228 | 228 | | |
---|
229 | 229 | | |
---|
230 | 230 | | |
---|
231 | 231 | | Description: |
---|
232 | 232 | | |
---|
233 | 233 | | Authorizes the issuance of general obligation bonds and appropriates moneys for capital improvement projects for the benefit of the 21st Representative District. |
---|
234 | 234 | | |
---|
235 | 235 | | |
---|
236 | 236 | | |
---|
237 | 237 | | |
---|
238 | 238 | | |
---|
239 | 239 | | |
---|
240 | 240 | | |
---|
241 | 241 | | The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent. |
---|