Hawaii 2022 Regular Session

Hawaii House Bill HB2001 Latest Draft

Bill / Introduced Version Filed 01/24/2022

                            HOUSE OF REPRESENTATIVES   H.B. NO.   2001     THIRTY-FIRST LEGISLATURE, 2022         STATE OF HAWAII                                A BILL FOR AN ACT     rELATING TO capital improvement projects for the benefit of the twenty-first representative district.     BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:   

HOUSE OF REPRESENTATIVES H.B. NO. 2001
THIRTY-FIRST LEGISLATURE, 2022
STATE OF HAWAII

HOUSE OF REPRESENTATIVES

H.B. NO.

2001

THIRTY-FIRST LEGISLATURE, 2022

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

rELATING TO capital improvement projects for the benefit of the twenty-first representative district.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 

      SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $10,400,000 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of financing capital improvement projects for the twenty-first representative district, as follows:      To be expended by the department of education:      A.   Ala Wai elementary school, Oahu           Plans, design, equipment, and construction to extend walkways in front of six classroom buildings to provide additional space for outdoor learning.           Plans                                        $  1,000           Design                                       $  1,000           Equipment                                    $  1,000           Construction                                 $197,000                Total funding                           $200,000      B.   Kaimuki middle school, Oahu           Plans, design, equipment, and construction to expand parking lot.           Plans                                      $    1,000           Design                                     $    1,000           Equipment                                  $    1,000           Construction                               $1,597,000                Total funding                         $1,600,000      C.   Kaimuki middle school, Oahu           Plans, design, equipment, and construction add a non-covered walkway from the cafeteria to the physical education building.           Plans                                        $  1,000           Design                                       $  1,000           Equipment                                    $  1,000           Construction                                 $197,000                Total funding                           $200,000      D.   Kaimuki high school, Oahu           Plans, design, equipment, and construction to install Cisco phones on campus.           Plans                                        $  1,000           Design                                       $  1,000           Equipment                                    $  1,000           Construction                                 $247,000                Total funding                           $250,000      E.   Kaimuki high school, Oahu           Plans, design, equipment, and construction to replace all cabling (horizontal and backbone), install Informacast (paging), install speakers throughout the campus, and replace the uninterruptible power supply in all buildings' intermediate distribution frame and main distribution frame.           Plans                                        $  1,000           Design                                       $  1,000           Equipment                                    $  1,000           Construction                                 $797,000                Total funding                           $800,000      F.   Kuhio elementary school, Oahu           Plans, design, equipment, and construction to repave the parking lot and repair damage caused by tree roots.           Plans                                        $  1,000           Design                                       $  1,000           Equipment                                    $  1,000           Construction                                 $ 97,000                Total funding                           $100,000      G.   Kuhio elementary school, Oahu           Plans, design, equipment, and construction to repaint the interior of the cafeteria.           Plans                                        $ 1,000           Design                                       $ 1,000           Equipment                                    $ 1,000           Construction                                 $47,000                Total funding                           $50,000      H.   Kuhio elementary school, Oahu           Plans, design, equipment, and construction for the installation of lighting for the campus and the installation of a security system.           Plans                                        $  1,000           Design                                       $  1,000           Equipment                                    $  1,000           Construction                                 $497,000                Total funding                           $500,000      I.   Lunalilo elementary school, Oahu           Design and construction for covered multipurpose space, campus security improvements, and ground and infrastructure improvements.           Design                                    $  500,000           Construction                               $3,000,000                Total funding                         $3,500,000      J.   Liholiho elementary school, Oahu           Plans, design, equipment, and construction for a concrete pad over grassy area.           Plans                                     $    1,000           Design                                    $    1,000           Equipment                                 $    1,000           Construction                               $  997,000                Total funding                         $1,000,000      K.   Washington middle school, Oahu           Design, equipment, and construction for telecom infrastructure update.           Design                                    $  200,000           Equipment                                 $  200,000           Construction                               $1,800,000                Total funding                         $2,200,000      SECTION 2.  The appropriation made for the capital improvement project authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.      SECTION 3.  The sums appropriated shall be expended by the department of education for the purposes of this Act.      SECTION 4.  This Act shall take effect on July 1, 2022.      INTRODUCED BY:   _____________________________              

     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $10,400,000 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of financing capital improvement projects for the twenty-first representative district, as follows:

     To be expended by the department of education:

     A.   Ala Wai elementary school, Oahu

          Plans, design, equipment, and construction to extend walkways in front of six classroom buildings to provide additional space for outdoor learning.

          Plans                                        $  1,000

          Design                                       $  1,000

          Equipment                                    $  1,000

          Construction                                 $197,000

               Total funding                           $200,000

     B.   Kaimuki middle school, Oahu

          Plans, design, equipment, and construction to expand parking lot.

          Plans                                      $    1,000

          Design                                     $    1,000

          Equipment                                  $    1,000

          Construction                               $1,597,000

               Total funding                         $1,600,000

     C.   Kaimuki middle school, Oahu

          Plans, design, equipment, and construction add a non-covered walkway from the cafeteria to the physical education building.

          Plans                                        $  1,000

          Design                                       $  1,000

          Equipment                                    $  1,000

          Construction                                 $197,000

               Total funding                           $200,000

     D.   Kaimuki high school, Oahu

          Plans, design, equipment, and construction to install Cisco phones on campus.

          Plans                                        $  1,000

          Design                                       $  1,000

          Equipment                                    $  1,000

          Construction                                 $247,000

               Total funding                           $250,000

     E.   Kaimuki high school, Oahu

          Plans, design, equipment, and construction to replace all cabling (horizontal and backbone), install Informacast (paging), install speakers throughout the campus, and replace the uninterruptible power supply in all buildings' intermediate distribution frame and main distribution frame.

          Plans                                        $  1,000

          Design                                       $  1,000

          Equipment                                    $  1,000

          Construction                                 $797,000

               Total funding                           $800,000

     F.   Kuhio elementary school, Oahu

          Plans, design, equipment, and construction to repave the parking lot and repair damage caused by tree roots.

          Plans                                        $  1,000

          Design                                       $  1,000

          Equipment                                    $  1,000

          Construction                                 $ 97,000

               Total funding                           $100,000

     G.   Kuhio elementary school, Oahu

          Plans, design, equipment, and construction to repaint the interior of the cafeteria.

          Plans                                        $ 1,000

          Design                                       $ 1,000

          Equipment                                    $ 1,000

          Construction                                 $47,000

               Total funding                           $50,000

     H.   Kuhio elementary school, Oahu

          Plans, design, equipment, and construction for the installation of lighting for the campus and the installation of a security system.

          Plans                                        $  1,000

          Design                                       $  1,000

          Equipment                                    $  1,000

          Construction                                 $497,000

               Total funding                           $500,000

     I.   Lunalilo elementary school, Oahu

          Design and construction for covered multipurpose space, campus security improvements, and ground and infrastructure improvements.

          Design                                    $  500,000

          Construction                               $3,000,000

               Total funding                         $3,500,000

     J.   Liholiho elementary school, Oahu

          Plans, design, equipment, and construction for a concrete pad over grassy area.

          Plans                                     $    1,000

          Design                                    $    1,000

          Equipment                                 $    1,000

          Construction                               $  997,000

               Total funding                         $1,000,000

     K.   Washington middle school, Oahu

          Design, equipment, and construction for telecom infrastructure update.

          Design                                    $  200,000

          Equipment                                 $  200,000

          Construction                               $1,800,000

               Total funding                         $2,200,000

     SECTION 2.  The appropriation made for the capital improvement project authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.

     SECTION 3.  The sums appropriated shall be expended by the department of education for the purposes of this Act.

     SECTION 4.  This Act shall take effect on July 1, 2022.

 

INTRODUCED BY: _____________________________

INTRODUCED BY:

_____________________________

 

 

       Report Title: CIP; 21st Representative District; GO Bonds; Appropriation   Description: Authorizes the issuance of general obligation bonds and appropriates moneys for capital improvement projects for the benefit of the 21st Representative District.       The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent. 

 

 

Report Title:

CIP; 21st Representative District; GO Bonds; Appropriation

 

Description:

Authorizes the issuance of general obligation bonds and appropriates moneys for capital improvement projects for the benefit of the 21st Representative District.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.