Hawaii 2023 Regular Session

Hawaii House Bill HB1402 Compare Versions

Only one version of the bill is available at this time.
OldNewDifferences
11 HOUSE OF REPRESENTATIVES H.B. NO. 1402 THIRTY-SECOND LEGISLATURE, 2023 STATE OF HAWAII A BILL FOR AN ACT RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR SCHOOLS IN THE THIRTY-EIGHTH REPRESENTATIVE DISTRICT. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
22
33 HOUSE OF REPRESENTATIVES H.B. NO. 1402
44 THIRTY-SECOND LEGISLATURE, 2023
55 STATE OF HAWAII
66
77 HOUSE OF REPRESENTATIVES
88
99 H.B. NO.
1010
1111 1402
1212
1313 THIRTY-SECOND LEGISLATURE, 2023
1414
1515
1616
1717 STATE OF HAWAII
1818
1919
2020
2121
2222
2323
2424
2525
2626
2727
2828
2929
3030
3131 A BILL FOR AN ACT
3232
3333
3434
3535
3636
3737 RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR SCHOOLS IN THE THIRTY-EIGHTH REPRESENTATIVE DISTRICT.
3838
3939
4040
4141
4242
4343 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
4444
4545
4646
4747 SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2023-2024: 1. Kipapa elementary, Oahu A. Construction of covered play court, land preparation, construction of a stage, bathrooms and storage. These are additional funds to approved 2021 appropriations to cover increased costs. Design and construction $2,500,000 Total funding $2,500,000 B. Air conditioning the cafeteria. Design and construction $1,500,000 Total funding $1,500,000 2. Mililani high school, Oahu A. Faculty Housing with Preschool. Plan $1,000,000 Design $2,000,000 Construction $17,000,000 Total funding $20,000,000 B. Construction of covered play court. Design $900,000 Construction $6,100,000 Total funding $7,000,000 3. Mililani Ike elementary school, Oahu. Resurfacing of driveways, drop off lanes, and two parking lots. Design, removal of current materials, installation, re-stripping. Construction $1,000,000 Total funding $1,000,000 4. Mililani Waena elementary school, Oahu. Cafeteria upgrades. Expansion of the existing dining room. Construction of an outdoor covered open-air dining area. Addition of a serving kitchen within the cafeteria building. Renovation of the existing serving kitchen into offices and a conference room for counselors, including air conditioning. Design $700,000 Construction $6,000,000 Equipment $300,000 Additional $7,000,000 Total funding $14,000,000 SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the department of education for the purposes of this Act. SECTION 3. This Act shall take effect on July 1, 2023. INTRODUCED BY: _____________________________
4848
4949 SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2023-2024:
5050
5151 1. Kipapa elementary, Oahu
5252
5353 A. Construction of covered play court, land preparation, construction of a stage, bathrooms and storage. These are additional funds to approved 2021 appropriations to cover increased costs.
5454
5555 Design and construction $2,500,000
5656
5757 Total funding $2,500,000
5858
5959 B. Air conditioning the cafeteria.
6060
6161 Design and construction $1,500,000
6262
6363 Total funding $1,500,000
6464
6565 2. Mililani high school, Oahu
6666
6767 A. Faculty Housing with Preschool.
6868
6969 Plan $1,000,000
7070
7171 Design $2,000,000
7272
7373 Construction $17,000,000
7474
7575 Total funding $20,000,000
7676
7777 B. Construction of covered play court.
7878
7979 Design $900,000
8080
8181 Construction $6,100,000
8282
8383 Total funding $7,000,000
8484
8585 3. Mililani Ike elementary school, Oahu.
8686
8787 Resurfacing of driveways, drop off lanes, and two parking lots. Design, removal of current materials, installation, re-stripping.
8888
8989 Construction $1,000,000
9090
9191 Total funding $1,000,000
9292
9393 4. Mililani Waena elementary school, Oahu.
9494
9595 Cafeteria upgrades. Expansion of the existing dining room. Construction of an outdoor covered open-air dining area. Addition of a serving kitchen within the cafeteria building. Renovation of the existing serving kitchen into offices and a conference room for counselors, including air conditioning.
9696
9797 Design $700,000
9898
9999 Construction $6,000,000
100100
101101 Equipment $300,000
102102
103103 Additional $7,000,000
104104
105105 Total funding $14,000,000
106106
107107 SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the department of education for the purposes of this Act.
108108
109109 SECTION 3. This Act shall take effect on July 1, 2023.
110110
111111
112112
113113 INTRODUCED BY: _____________________________
114114
115115 INTRODUCED BY:
116116
117117 _____________________________
118118
119119
120120
121121
122122
123123 Report Title: CIP; Thirty-eighth Representative District Description: Appropriates funds for capital improvement projects for the benefit of the thirty-eighth Representative District. The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
124124
125125
126126
127127
128128
129129 Report Title:
130130
131131 CIP; Thirty-eighth Representative District
132132
133133
134134
135135 Description:
136136
137137 Appropriates funds for capital improvement projects for the benefit of the thirty-eighth Representative District.