Maine 2023-2024 Regular Session

Maine House Bill LD1709 Latest Draft

Bill / Chaptered Version

                            Page 1 - 131LR2160(03)
STATE OF MAINE
_____
IN THE YEAR OF OUR LORD
TWO THOUSAND TWENTY-THREE
_____
H.P. 1098 - L.D. 1709
An Act to Update the Elevator and Tramway Safety Laws Regarding 
Construction Hoists
Be it enacted by the People of the State of Maine as follows:
Sec. 1.  32 MRSA §15202, sub-§3-A is enacted to read:
3-A.  Construction hoist. 
part of a building or structure; is installed inside or outside the building or structure during 
the construction, alteration or demolition of the building or structure; and is used to raise 
and lower workers, other personnel and materials.  "Construction hoist" does not include:
A.  An elevator that is temporarily installed in a hoistway during the construction of a 
building or structure and that incorporates a part of a permanent elevator that will be 
installed later;
B.  A hoist for raising and lowering materials that is not designed to carry workers or 
other personnel;
C.  A manlift that operates through a counterbalance mechanism or through the use of 
a continuous belt;
D.  A mine hoist;
E.  A wire rope hoist, whether guided or unguided; or 
F.  A transport platform.
Sec. 2.  32 MRSA §15202, sub-§3-B is enacted to read:
3-B.  Construction hoist operator. 
operates or is responsible for the operation of a construction hoist.
Sec. 3.  32 MRSA §15230 is enacted to read:
§15230.  Construction hoist operators; rules
The director shall adopt rules regarding the proper operation of construction hoists and 
training requirements for construction hoist operators.  After adoption of the rules, a person 
may not operate a construction hoist except as in accordance with the rules adopted by the 
APPROVED
JUNE 26, 2023
BY GOVERNOR
CHAPTER
326
PUBLIC LAW Page 2 - 131LR2160(03)
director.  Rules adopted under this section are routine technical rules as defined in Title 5, 
chapter 375, subchapter 2-A.