1 | 1 | | 1.1 A bill for an act |
---|
2 | 2 | | 1.2 relating to energy; modifying the definition of large energy facility; amending |
---|
3 | 3 | | 1.3 Minnesota Statutes 2024, section 216B.2421, subdivision 2. |
---|
4 | 4 | | 1.4BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA: |
---|
5 | 5 | | 1.5 Section 1. Minnesota Statutes 2024, section 216B.2421, subdivision 2, is amended to read: |
---|
6 | 6 | | 1.6 Subd. 2.Large energy facility."Large energy facility" means: |
---|
7 | 7 | | 1.7 (1) any electric power generating plant or combination of plants at a single site with a |
---|
8 | 8 | | 1.8combined capacity of 50,000 kilowatts or more and transmission lines directly associated |
---|
9 | 9 | | 1.9with the plant that are necessary to interconnect the plant to the transmission system; |
---|
10 | 10 | | 1.10 (2) any high-voltage transmission line with a capacity of 300 kilovolts or more and |
---|
11 | 11 | | 1.11greater than one mile in length in Minnesota; |
---|
12 | 12 | | 1.12 (3) any high-voltage transmission line with a capacity of 100 kilovolts or more with |
---|
13 | 13 | | 1.13more than ten miles of its length in Minnesota; |
---|
14 | 14 | | 1.14 (4) any pipeline greater than six inches in diameter and having more than 50 miles of |
---|
15 | 15 | | 1.15its length in Minnesota used for the transportation of coal, crude petroleum or petroleum |
---|
16 | 16 | | 1.16fuels or oil, or their derivatives; |
---|
17 | 17 | | 1.17 (5) any pipeline for transporting natural or synthetic gas at pressures in excess of 200 |
---|
18 | 18 | | 1.18pounds per square inch with more than 50 miles of its length in Minnesota; |
---|
19 | 19 | | 1.19 (6) any facility designed for or capable of storing on a single site more than 100,000 |
---|
20 | 20 | | 1.201,000,000 gallons of liquefied natural gas or synthetic gas; |
---|
21 | 21 | | 1.21 (7) any underground gas storage facility requiring a permit pursuant to section 103I.681; |
---|
22 | 22 | | 1Section 1. |
---|
23 | 23 | | 25-02995 as introduced02/05/25 REVISOR RSI/MI |
---|
24 | 24 | | SENATE |
---|
25 | 25 | | STATE OF MINNESOTA |
---|
26 | 26 | | S.F. No. 1455NINETY-FOURTH SESSION |
---|
27 | 27 | | (SENATE AUTHORS: HOFFMAN and Rarick) |
---|
28 | 28 | | OFFICIAL STATUSD-PGDATE |
---|
29 | 29 | | Introduction and first reading02/17/2025 |
---|
30 | 30 | | Referred to Energy, Utilities, Environment, and Climate 2.1 (8) any nuclear fuel processing or nuclear waste storage or disposal facility; and |
---|
31 | 31 | | 2.2 (9) any facility intended to convert any material into any other combustible fuel and |
---|
32 | 32 | | 2.3having the capacity to process in excess of 75 tons of the material per hour. |
---|
33 | 33 | | 2Section 1. |
---|
34 | 34 | | 25-02995 as introduced02/05/25 REVISOR RSI/MI |
---|