1 | 1 | | FIRSTREGULARSESSION |
---|
2 | 2 | | HOUSEBILLNO.413 |
---|
3 | 3 | | 103RDGENERALASSEMBLY |
---|
4 | 4 | | INTRODUCEDBYREPRESENTATIVECASTEEL. |
---|
5 | 5 | | 0894H.03I DANARADEMANMILLER,ChiefClerk |
---|
6 | 6 | | ANACT |
---|
7 | 7 | | Torepealsections8.690,67.5050,and67.5060,RSMo,andtoenactinlieuthereofthreenew |
---|
8 | 8 | | sectionsrelatingtodesign-buildcontracts. |
---|
9 | 9 | | BeitenactedbytheGeneralAssemblyofthestateofMissouri,asfollows: |
---|
10 | 10 | | SectionA.Sections8.690,67.5050,and67.5060,RSMo,arerepealedandthreenew |
---|
11 | 11 | | 2sectionsenactedinlieuthereof,tobeknownassections8.690,67.5050,and67.5060,toread |
---|
12 | 12 | | 3asfollows: |
---|
13 | 13 | | 8.690.1.Theofficeofadministrationshallhavetheauthoritytoutilize: |
---|
14 | 14 | | 2 (1)Theconstructionmanager-at-riskdeliverymethod,asprovidedforinsection |
---|
15 | 15 | | 367.5050;and |
---|
16 | 16 | | 4 (2)Thedesign-builddeliverymethod,asprovidedforinsection67.5060,onlyas |
---|
17 | 17 | | 5follows: |
---|
18 | 18 | | 6 (a)Fornoncivilworksprojects,asthattermisusedinsection67.5060,inexcessof |
---|
19 | 19 | | 7sevenmilliondollars;and |
---|
20 | 20 | | 8 (b)Nomorethanfivenoncivilworksprojects,asthattermisusedinsection67.5060, |
---|
21 | 21 | | 9maybecontractedforinanyfiscalyearthatarelessthansevenmilliondollars. |
---|
22 | 22 | | 10 2.Theofficeofadministrationshallnotbesubjecttosubsection15ofsection |
---|
23 | 23 | | 1167.5050[andsubsection22ofsection67.5060] inexecutingcontractspursuanttothis |
---|
24 | 24 | | 12section. |
---|
25 | 25 | | 13 3.Theofficeofadministrationshallnotbesubjecttosubsection4ofsection67.5060. |
---|
26 | 26 | | 14Theofficeofadministrationshallpublishitsadvertisementforproposalsinthepublications, |
---|
27 | 27 | | 15andonthewebsiteoftheofficeroragencyorthroughanelectronicprocurementsystemasset |
---|
28 | 28 | | EXPLANATION—Matterenclosedinbold-facedbrackets[thus] intheabovebillisnotenactedandis |
---|
29 | 29 | | intendedtobeomittedfromthelaw.Matterinbold-facetypeintheabovebillisproposedlanguage. 16forthinsubsection3ofsection8.250.Theselectionandawardshallfollowsections67.5050 |
---|
30 | 30 | | 17and67.5060,asapplicable. |
---|
31 | 31 | | 67.5050.1.Asusedinthissection,thefollowingtermsmean: |
---|
32 | 32 | | 2 (1)"Constructionmanager",thelegalentitythatproposestoenterintoaconstruction |
---|
33 | 33 | | 3[management-at-risk] manager-at-riskcontractunderthissection; |
---|
34 | 34 | | 4 (2)"Constructionmanager-at-risk",asoleproprietorship,partnership,corporation,or |
---|
35 | 35 | | 5otherlegalentitythatassumestheriskfortheconstruction,rehabilitation,alteration,orrepair |
---|
36 | 36 | | 6ofaprojectatthecontractedpriceasageneralcontractorandprovidesconsultationtoa |
---|
37 | 37 | | 7politicalsubdivisionregardingconstructionduringandafterthedesignoftheproject. |
---|
38 | 38 | | 8 2.Anypoliticalsubdivisionmayusetheconstructionmanager-at-riskmethodfor: |
---|
39 | 39 | | 9civilworksprojectssuchasroads,streets,bridges,utilities,watersupplyprojects,water |
---|
40 | 40 | | 10plants,wastewaterplants,waterdistributionandwastewaterconveyancefacilities,airport |
---|
41 | 41 | | 11runwaysandtaxiways,stormdrainageandfloodcontrolprojects,ortransitprojects |
---|
42 | 42 | | 12commonlydesignedbyprofessionalengineersinexcessoftwomilliondollars;andnoncivil |
---|
43 | 43 | | 13worksprojectssuchasbuildings,siteimprovements,andotherstructures,habitableornot, |
---|
44 | 44 | | 14commonlydesignedbyarchitectsinexcessofthreemilliondollars.Inusingthatmethodand |
---|
45 | 45 | | 15inenteringintoacontractfortheservicesofaconstructionmanager-at-risk,thepolitical |
---|
46 | 46 | | 16subdivisionshallfollowtheproceduresprescribedbythissection. |
---|
47 | 47 | | 17 3.Thepoliticalsubdivisionshallpubliclydiscloseataregularmeetingitsintentto |
---|
48 | 48 | | 18utilizetheconstruction[managementat-risk] manager-at-riskmethodanditsselection |
---|
49 | 49 | | 19criteriaatleastoneweekpriortopublishingtherequestforqualifications.Beforeor |
---|
50 | 50 | | 20concurrentlywithselectingaconstructionmanager-at-risk,thepoliticalsubdivisionshall |
---|
51 | 51 | | 21selectordesignateanengineerorarchitectwhoshallpreparetheconstructiondocumentsfor |
---|
52 | 52 | | 22theprojectandwhoshallcomplywithallstatelaws,asapplicable.Iftheengineeror |
---|
53 | 53 | | 23architectisnotafull-timeemployeeofthepoliticalsubdivision,thepoliticalsubdivisionshall |
---|
54 | 54 | | 24selecttheengineerorarchitectonthebasisofdemonstratedcompetenceandqualificationsas |
---|
55 | 55 | | 25providedbysections8.285to8.291.Thepoliticalsubdivision'sengineerorarchitectfora |
---|
56 | 56 | | 26projectmaynotserve,aloneorincombinationwithanother,astheconstructionmanager-at- |
---|
57 | 57 | | 27risk.Thissubsectiondoesnotprohibitapoliticalsubdivision'sengineerorarchitectfrom |
---|
58 | 58 | | 28providingcustomaryconstructionphaseservicesundertheengineer'sorarchitect'soriginal |
---|
59 | 59 | | 29professionalserviceagreementinaccordancewithapplicablelicensinglaws. |
---|
60 | 60 | | 30 4.Thepoliticalsubdivisionmayprovideorcontractfor,independentlyofthe |
---|
61 | 61 | | 31constructionmanager-at-risk,inspectionservices,testingofconstructionmaterials, |
---|
62 | 62 | | 32engineering,andverificationoftestingservicesnecessaryforacceptanceoftheprojectby |
---|
63 | 63 | | 33thepoliticalsubdivision. |
---|
64 | 64 | | 34 5.Thepoliticalsubdivisionshallselecttheconstructionmanager-at-riskinatwo-step |
---|
65 | 65 | | 35process.Thepoliticalsubdivisionshallpreparearequestforqualifications,forthecaseofthe |
---|
66 | 66 | | HB413 2 36firststepofthetwo-stepprocess,thatincludesgeneralinformationontheprojectsite,project |
---|
67 | 67 | | 37scope,schedule,selectioncriteria,andthetimeandplaceforreceiptofproposalsor |
---|
68 | 68 | | 38qualifications,asapplicable,andotherinformationthatmayassistthepoliticalsubdivisionin |
---|
69 | 69 | | 39itsselectionofaconstructionmanager-at-risk.Thepoliticalsubdivisionshallstatethe |
---|
70 | 70 | | 40selectioncriteriaintherequestforproposalsorqualifications,asapplicable.Theselection |
---|
71 | 71 | | 41criteriamayincludetheconstructionmanager'sexperience,pastperformance,safetyrecord, |
---|
72 | 72 | | 42proposedpersonnelandmethodology,andotherappropriatefactorsthatdemonstratethe |
---|
73 | 73 | | 43capabilityoftheconstructionmanager-at-risk.Thepoliticalsubdivisionshallnotrequestfees |
---|
74 | 74 | | 44orpricesinstepone.Insteptwo,thepoliticalsubdivisionmayrequestthatfiveorfewer |
---|
75 | 75 | | 45constructionmanagers,selectedsolelyonthebasisofqualifications,provideadditional |
---|
76 | 76 | | 46information,includingtheconstructionmanager-at-risk'sproposedfeeanditspricefor |
---|
77 | 77 | | 47fulfillingthegeneralconditions.Qualificationsshallaccountforaminimumoffortypercent |
---|
78 | 78 | | 48oftheevaluation.Costshallaccountforamaximumofsixtypercentoftheevaluation. |
---|
79 | 79 | | 49 6.Thepoliticalsubdivisionshallpublishtherequestforproposalsorqualificationsby |
---|
80 | 80 | | 50publicationinanewspaperofgeneralcirculationpublishedinthecountywherethepolitical |
---|
81 | 81 | | 51subdivisionislocatedonceaweekfortwoconsecutiveweekspriortoopeningtheproposals |
---|
82 | 82 | | 52orqualificationssubmissionsorbyavirtualnoticeprocedurethatnotifiesinterestedparties |
---|
83 | 83 | | 53foratleasttwentyvariouspurchases,designcontracts,constructioncontracts,orother |
---|
84 | 84 | | 54contractseachyearforthepoliticalsubdivision. |
---|
85 | 85 | | 55 7.Foreachstep,thepoliticalsubdivisionshallreceive,publiclyopen,andreadaloud |
---|
86 | 86 | | 56thenamesoftheconstructionmanagers.Withinforty-fivedaysafterthedateofopeningthe |
---|
87 | 87 | | 57proposalsorqualificationsubmissions,thepoliticalsubdivisionoritsrepresentativeshall |
---|
88 | 88 | | 58evaluateandrankeachproposalorqualificationsubmissionsubmittedinrelationtothe |
---|
89 | 89 | | 59criteriasetforthintherequestforproposalsorrequestforqualifications.Thepolitical |
---|
90 | 90 | | 60subdivisionshallinterviewatleasttwoofthetopqualifiedofferorsaspartofthefinal |
---|
91 | 91 | | 61selection. |
---|
92 | 92 | | 62 8.Thepoliticalsubdivisionoritsrepresentativeshallselecttheconstructionmanager |
---|
93 | 93 | | 63thatsubmitstheproposalthatoffersthebestvalueforthepoliticalsubdivisionbasedonthe |
---|
94 | 94 | | 64publishedselectioncriteriaandonitsrankingevaluation.Thepoliticalsubdivisionorits |
---|
95 | 95 | | 65representativeshallfirstattempttonegotiateacontractwiththeselectedconstruction |
---|
96 | 96 | | 66manager.Ifthepoliticalsubdivisionoritsrepresentativeisunabletonegotiateasatisfactory |
---|
97 | 97 | | 67contractwiththeselectedconstructionmanager,thepoliticalsubdivisionoritsrepresentative |
---|
98 | 98 | | 68shall,formallyandinwriting,endnegotiationswiththatconstructionmanagerandproceedto |
---|
99 | 99 | | 69negotiatewiththenextconstructionmanagerintheorderoftheselectionrankinguntila |
---|
100 | 100 | | 70contractisreachedornegotiationswithallrankedconstructionmanagersend. |
---|
101 | 101 | | 71 9.Aconstructionmanager-at-riskshallpubliclyadvertise,inthemannerprescribed |
---|
102 | 102 | | 72bychapter50,andreceivebidsorproposalsfromtradecontractorsorsubcontractorsforthe |
---|
103 | 103 | | HB413 3 73performanceofallmajorelementsoftheworkotherthantheminorworkthatmaybe |
---|
104 | 104 | | 74includedinthegeneralconditions.Aconstructionmanager-at-riskmayseektoperform |
---|
105 | 105 | | 75portionsoftheworkitselfiftheconstructionmanager-at-risksubmitsitssealedbidorsealed |
---|
106 | 106 | | 76proposalforthoseportionsoftheworkinthesamemannerasallothertradecontractorsor |
---|
107 | 107 | | 77subcontractors.Allsealedbidsorproposalsshallbesubmittedatthetimeandlocationas |
---|
108 | 108 | | 78specifiedintheadvertisementforbidsorproposalsandshallbepubliclyopenedandthe |
---|
109 | 109 | | 79identityofeachbidderandtheirbidamountshallbereadaloud.Thepoliticalsubdivision |
---|
110 | 110 | | 80shallhavetheauthoritytorestricttheconstructionmanager-at-riskfromsubmittingbidsto |
---|
111 | 111 | | 81performportionsofthework. |
---|
112 | 112 | | 82 10.Theconstructionmanager-at-riskandthepoliticalsubdivisionorits |
---|
113 | 113 | | 83representativeshallreviewalltradecontractor,subcontractor,orconstructionmanager-at- |
---|
114 | 114 | | 84riskbidsorproposalsinamannerthatdoesnotdisclosethecontentsofthebidorproposal |
---|
115 | 115 | | 85duringtheselectionprocesstoapersonnotemployedbytheconstructionmanager-at-risk, |
---|
116 | 116 | | 86engineer,architect,orpoliticalsubdivisioninvolvedwiththeproject.Iftheconstruction |
---|
117 | 117 | | 87manager-at-risksubmittedbidsorproposals,thepoliticalsubdivisionshalldetermineifthe |
---|
118 | 118 | | 88constructionmanager-at-risk'sbidorproposaloffersthebestvalueforthepolitical |
---|
119 | 119 | | 89subdivision.Afterallproposalshavebeenevaluatedandclarified,theawardofall |
---|
120 | 120 | | 90subcontractsshallbemadepublic. |
---|
121 | 121 | | 91 11.Iftheconstructionmanager-at-riskreviews,evaluates,andrecommendstothe |
---|
122 | 122 | | 92politicalsubdivisionabidorproposalfromatradecontractororsubcontractorbutthe |
---|
123 | 123 | | 93politicalsubdivisionrequiresanotherbidorproposaltobeaccepted,thepoliticalsubdivision |
---|
124 | 124 | | 94shallcompensatetheconstructionmanager-at-riskbyachangeinprice,time,orguaranteed |
---|
125 | 125 | | 95maximumcostforanyadditionalcostandriskthattheconstructionmanager-at-riskmay |
---|
126 | 126 | | 96incurbecauseofthepoliticalsubdivision'srequirementthatanotherbidorproposalbe |
---|
127 | 127 | | 97accepted. |
---|
128 | 128 | | 98 12.Ifaselectedtradecontractororsubcontractormateriallydefaultsinthe |
---|
129 | 129 | | 99performanceofitsworkorfailstoexecuteasubcontractafterbeingselectedinaccordance |
---|
130 | 130 | | 100withthissection,theconstructionmanager-at-riskmayitself,withoutadvertising,fulfillthe |
---|
131 | 131 | | 101contractrequirementsorselectareplacementtradecontractororsubcontractortofulfillthe |
---|
132 | 132 | | 102contractrequirements.Thepenalsumsoftheperformanceandpaymentbondsdeliveredto |
---|
133 | 133 | | 103thepoliticalsubdivisionshalleachbeinanamountequaltothefixedcontractamountor |
---|
134 | 134 | | 104guaranteedmaximumprice.Theconstructionmanager-at-riskshalldeliverthebondsnot |
---|
135 | 135 | | 105laterthanthetenthdayafterthedatethefixedcontractamountorguaranteedmaximumprice |
---|
136 | 136 | | 106isestablished. |
---|
137 | 137 | | 107 13.Anypoliticalsubdivisionengagedinaprojectunderthissection,whichimpactsa |
---|
138 | 138 | | 108railroadregulatedbytheFederalRailroadAdministration,shallconsultwiththeaffected |
---|
139 | 139 | | HB413 4 109railroadonrequiredspecificationsrelatingtoclearance,safety,insurance,and |
---|
140 | 140 | | 110indemnificationtobeincludedintheconstructiondocumentsforsuchproject. |
---|
141 | 141 | | 111 14.Thissectionshallnotapplyto: |
---|
142 | 142 | | 112 (1)AnymetropolitansewerdistrictestablishedunderArticleVI,Section30(a)ofthe |
---|
143 | 143 | | 113ConstitutionofMissouri; |
---|
144 | 144 | | 114 (2)Anyspecialchartercity,oranycityorcountygovernedbyhomeruleunder |
---|
145 | 145 | | 115ArticleVI,[Section18]Sections18(a)to18(r)orSection19oftheConstitutionofMissouri |
---|
146 | 146 | | 116thathasadoptedaconstructionmanager-at-riskmethodviaordinance,ruleorregulation. |
---|
147 | 147 | | 117 [15.Notwithstandingtheprovisionsofsection23.253tothecontrary,theprovisions |
---|
148 | 148 | | 118ofthissectionshallexpireSeptember1,2026.] |
---|
149 | 149 | | 67.5060.1.Asusedinthissection,thefollowingtermsmean: |
---|
150 | 150 | | 2 (1)"Design-build",aprojectdeliverymethodsubjecttoathree-stagequalifications- |
---|
151 | 151 | | 3basedselectionforwhichthedesignandconstructionservicesarefurnishedunderone |
---|
152 | 152 | | 4contract; |
---|
153 | 153 | | 5 (2)"Design-buildcontract",acontractwhichissubjecttoathree-stagequalifications- |
---|
154 | 154 | | 6basedselectionprocesssimilartothatdescribedinsections8.285to8.291betweenapolitical |
---|
155 | 155 | | 7subdivisionandadesign-buildertofurnishthearchitectural,engineering,andrelateddesign |
---|
156 | 156 | | 8servicesandthelabor,materials,supplies,equipment,andotherconstructionservices |
---|
157 | 157 | | 9requiredforadesign-buildproject; |
---|
158 | 158 | | 10 (3)"Design-buildproject",thedesign,construction,alteration,addition,remodeling, |
---|
159 | 159 | | 11orimprovementofanybuildingsorfacilitiesundercontractwithapoliticalsubdivision. |
---|
160 | 160 | | 12Suchdesign-buildprojectsinclude,butarenotlimitedto: |
---|
161 | 161 | | 13 (a)Civilworksprojects,suchasroads,streets,bridges,utilities,airportrunwaysand |
---|
162 | 162 | | 14taxiways,stormdrainageandfloodcontrolprojects,ortransitprojects;and |
---|
163 | 163 | | 15 (b)Noncivilworksprojects,suchasbuildings,siteimprovements,andother |
---|
164 | 164 | | 16structures,habitableornot,commonlydesignedbyarchitectsinexcessofsevenmillion |
---|
165 | 165 | | 17dollars; |
---|
166 | 166 | | 18 (4)"Design-builder",anyindividual,partnership,jointventure,orcorporationsubject |
---|
167 | 167 | | 19toaqualification-basedselectionthatofferstoprovideorprovidesdesignservicesand |
---|
168 | 168 | | 20generalcontractingservicesthroughadesign-buildcontractinwhichserviceswithinthe |
---|
169 | 169 | | 21scopeofthepracticeofprofessionalarchitectureorengineeringareperformedrespectively |
---|
170 | 170 | | 22byalicensedarchitectorlicensedengineerandinwhichserviceswithinthescopeofgeneral |
---|
171 | 171 | | 23contractingareperformedbyageneralcontractororotherlegalentitythatfurnishes |
---|
172 | 172 | | 24architectureorengineeringservicesandconstructionserviceseitherdirectlyorthrough |
---|
173 | 173 | | 25subcontractsorjointventures; |
---|
174 | 174 | | 26 (5)"Designcriteriaconsultant",aperson,corporation,partnership,orotherlegal |
---|
175 | 175 | | 27entitydulylicensedandauthorizedtopracticearchitectureorprofessionalengineeringinthis |
---|
176 | 176 | | HB413 5 28stateunderchapter327whoisemployedbyorcontractedbythepoliticalsubdivisiontoassist |
---|
177 | 177 | | 29thepoliticalsubdivisioninthedevelopmentofprojectdesigncriteria,requestsforproposals, |
---|
178 | 178 | | 30evaluationofproposals,theevaluationoftheconstructionunderadesign-buildcontractto |
---|
179 | 179 | | 31determineadherencetothedesigncriteria,andanyadditionalservicesrequestedbythe |
---|
180 | 180 | | 32political[subdivisions] subdivisiontorepresentitsinterestsinrelationtoaproject.The |
---|
181 | 181 | | 33designcriteriaconsultantmaynotsubmitaproposalorfurnishdesignorconstructionservices |
---|
182 | 182 | | 34forthedesign-buildcontractforwhichitsservicesweresought; |
---|
183 | 183 | | 35 (6)"Designcriteriapackage",performance-orientedprogram,scope,and |
---|
184 | 184 | | 36specificationsforthedesign-buildprojectsufficienttopermitadesign-buildertopreparea |
---|
185 | 185 | | 37responsetoapoliticalsubdivision'srequestforproposalsforadesign-buildproject,which |
---|
186 | 186 | | 38mayincludecapacity,durability,standards,ingressandegressrequirements,performance |
---|
187 | 187 | | 39requirements,descriptionofthesite,surveys,soilandenvironmentalinformationconcerning |
---|
188 | 188 | | 40thesite,interiorspacerequirements,materialqualitystandards,designandconstruction |
---|
189 | 189 | | 41schedules,sitedevelopmentrequirements,provisionsforutilities,stormwaterretentionand |
---|
190 | 190 | | 42disposal,parkingrequirements,applicablegovernmentalcoderequirements,preliminary |
---|
191 | 191 | | 43designsfortheprojectorportionsthereof,andothercriteriafortheintendeduseofthe |
---|
192 | 192 | | 44project; |
---|
193 | 193 | | 45 (7)"Designprofessionalservices",servicesthatare: |
---|
194 | 194 | | 46 (a)Withinthepracticeofarchitectureasdefinedinsection327.091,orwithinthe |
---|
195 | 195 | | 47practiceofprofessionalengineeringasdefinedinsection327.181;or |
---|
196 | 196 | | 48 (b)Performedbyalicensedorauthorizedarchitectorprofessionalengineerin |
---|
197 | 197 | | 49connectionwiththearchitect'sorprofessionalengineer'semploymentorpractice; |
---|
198 | 198 | | 50 (8)"Proposal",anofferinresponsetoarequestforproposalsbyadesign-builderto |
---|
199 | 199 | | 51enterintoadesign-buildcontractforadesign-buildprojectunderthissection; |
---|
200 | 200 | | 52 (9)"Requestforproposal",thedocumentbywhichthepoliticalsubdivisionsolicits |
---|
201 | 201 | | 53proposalsforadesign-buildcontract; |
---|
202 | 202 | | 54 (10)"Stipend",anamountpaidtotheunsuccessfulbutresponsive,short-listed |
---|
203 | 203 | | 55design-builderstodefraythecostofparticipatinginphaseIIoftheselectionprocess |
---|
204 | 204 | | 56describedinthissection. |
---|
205 | 205 | | 57 2.Inusingadesign-buildcontract,thepoliticalsubdivisionshalldeterminethescope |
---|
206 | 206 | | 58andlevelofdetailrequiredtopermitqualifiedpersonstosubmitproposalsinaccordancewith |
---|
207 | 207 | | 59therequestforproposalsgiventhenatureoftheproject. |
---|
208 | 208 | | 60 3.Adesigncriteriaconsultantshallbeemployedorretainedbythepolitical |
---|
209 | 209 | | 61subdivisiontoassistinpreparationofthedesigncriteriapackageandrequestforproposal, |
---|
210 | 210 | | 62performperiodicsitevisitstoobserveadherencetothedesigncriteria,prepareprogress |
---|
211 | 211 | | 63reports,reviewandapproveprogressandfinalpayapplicationsofthedesign-builder,review |
---|
212 | 212 | | 64shopdrawingsandsubmissions,provideinputindisputes,helpinterprettheconstruction |
---|
213 | 213 | | HB413 6 65documents,performinspectionsuponsubstantialandfinalcompletion,assistinwarranty |
---|
214 | 214 | | 66inspections,andprovideanyotherprofessionalserviceassistingwiththeproject |
---|
215 | 215 | | 67administration.Thedesigncriteriaconsultantmayalsoevaluateconstructionastothe |
---|
216 | 216 | | 68adherenceofthedesigncriteria.Theconsultantshallbeselectedanditscontractnegotiated |
---|
217 | 217 | | 69incompliancewithsections8.285to8.291unlesstheconsultantisadirectemployeeofthe |
---|
218 | 218 | | 70politicalsubdivision. |
---|
219 | 219 | | 71 4.Thepoliticalsubdivisionshallpubliclydiscloseataregularmeetingitsintentto |
---|
220 | 220 | | 72utilizethedesign-buildmethodanditsprojectdesigncriteriaatleastoneweekpriorto |
---|
221 | 221 | | 73publishingtherequestforproposals.Noticeofrequestsforproposalsshallbeadvertisedby |
---|
222 | 222 | | 74publicationinanewspaperofgeneralcirculationpublishedinthecountywherethepolitical |
---|
223 | 223 | | 75subdivisionislocatedonceaweekfortwoconsecutiveweekspriortoopeningtheproposals, |
---|
224 | 224 | | 76orbyavirtualnoticeprocedurethatnotifiesinterestedpartiesforatleasttwentyvarious |
---|
225 | 225 | | 77purchases,designcontracts,constructioncontracts,orothercontractseachyearforthe |
---|
226 | 226 | | 78politicalsubdivision.Thepoliticalsubdivisionshallpublishanoticeofarequestforproposal |
---|
227 | 227 | | 79withadescriptionoftheproject,theproceduresforsubmission,andtheselectioncriteriato |
---|
228 | 228 | | 80beused. |
---|
229 | 229 | | 81 5.Thepoliticalsubdivisionshallestablishintherequestforproposalatime,place, |
---|
230 | 230 | | 82andotherspecificinstructionsforthereceiptofproposals.Proposalsnotsubmittedinstrict |
---|
231 | 231 | | 83accordancewiththeinstructionsshallbesubjecttorejection. |
---|
232 | 232 | | 84 6.Arequestforproposalshallbepreparedforeachdesign-buildcontractcontaining |
---|
233 | 233 | | 85atminimumthefollowingelements: |
---|
234 | 234 | | 86 (1)Theprocedurestobefollowedforsubmittingproposals,thecriteriaforevaluating |
---|
235 | 235 | | 87proposalsandtheirrelativeweight,andtheproceduresformakingawards; |
---|
236 | 236 | | 88 (2)Theproposedtermsandconditionsforthedesign-buildcontract,ifavailable; |
---|
237 | 237 | | 89 (3)Thedesigncriteriapackage; |
---|
238 | 238 | | 90 (4)Adescriptionofthedrawings,specifications,orotherinformationtobesubmitted |
---|
239 | 239 | | 91withtheproposal,withguidanceastotheformandlevelofcompletenessofthedrawings, |
---|
240 | 240 | | 92specifications,orotherinformationthatwillbeacceptable; |
---|
241 | 241 | | 93 (5)Ascheduleforplannedcommencementandcompletionofthedesign-build |
---|
242 | 242 | | 94contract,ifany; |
---|
243 | 243 | | 95 (6)Budgetlimitsforthedesign-buildcontract,ifany; |
---|
244 | 244 | | 96 (7)Requirementsincludinganyavailableratingsforperformancebonds,payment |
---|
245 | 245 | | 97bonds,andinsurance,ifany; |
---|
246 | 246 | | 98 (8)Theamountofthestipendwhichwillbeavailable;and |
---|
247 | 247 | | 99 (9)Anyotherinformationthatthepoliticalsubdivisioninitsdiscretionchoosesto |
---|
248 | 248 | | 100supplyincluding,butnotlimitedto,surveys,soilreports,drawingsofexistingstructures, |
---|
249 | 249 | | HB413 7 101environmentalstudies,photographs,referencestopublicrecords,oraffirmativeactionand |
---|
250 | 250 | | 102minoritybusinessenterpriserequirementsconsistentwithstateandfederallaw. |
---|
251 | 251 | | 103 7.Thepoliticalsubdivisionshallsolicitproposalsinathree-stageprocess.PhaseI |
---|
252 | 252 | | 104shallbethesolicitationofqualificationsofthedesign-buildteam.PhaseIIshallbethe |
---|
253 | 253 | | 105solicitationofatechnicalproposalincludingconceptualdesignfortheproject.PhaseIIIshall |
---|
254 | 254 | | 106betheproposaloftheconstructioncost. |
---|
255 | 255 | | 107 8.Thepoliticalsubdivisionshallreviewthesubmissionsoftheproposalsandassign |
---|
256 | 256 | | 108pointstoeachproposalinaccordancewiththissectionandassetoutintheinstructionsofthe |
---|
257 | 257 | | 109requestforproposal. |
---|
258 | 258 | | 110 9.PhaseIshallrequirealldesign-builderstosubmitastatementofqualificationthat |
---|
259 | 259 | | 111shallinclude,butnotbelimitedto: |
---|
260 | 260 | | 112 (1)Demonstratedabilitytoperformprojectscomparableindesign,scope,and |
---|
261 | 261 | | 113complexity; |
---|
262 | 262 | | 114 (2)Referencesofownersforwhomdesign-buildprojects,constructionprojects,or |
---|
263 | 263 | | 115designprojectshavebeenperformed; |
---|
264 | 264 | | 116 (3)Qualificationsofpersonnelwhowillmanagethedesignandconstructionaspects |
---|
265 | 265 | | 117oftheproject;and |
---|
266 | 266 | | 118 (4)Thenamesandqualificationsoftheprimarydesignconsultantsandtheprimary |
---|
267 | 267 | | 119tradecontractorswithwhomthedesign-builderproposestosubcontractorjointventure.The |
---|
268 | 268 | | 120design-buildermaynotreplaceanidentifiedcontractor,subcontractor,designconsultant,or |
---|
269 | 269 | | 121subconsultantwithoutthewrittenapprovalofthepoliticalsubdivision. |
---|
270 | 270 | | 122 10.Thepoliticalsubdivisionshallevaluatethequalificationsofallthedesign- |
---|
271 | 271 | | 123builderswhosubmittedproposalsinaccordancewiththeinstructionsoftherequestfor |
---|
272 | 272 | | 124proposal.Architecturalandengineeringservicesontheprojectshallbeevaluatedin |
---|
273 | 273 | | 125accordancewiththerequirementsofsections8.285and8.291.Qualifieddesign-builders |
---|
274 | 274 | | 126selectedbytheevaluationteammayproceedtophaseIIoftheselectionprocess.Design- |
---|
275 | 275 | | 127builderslackingthenecessaryqualificationstoperformtheworkshallbedisqualifiedand |
---|
276 | 276 | | 128shallnotproceedtophaseIIoftheprocess.Thisprocessofshortlistingshallnarrowthe |
---|
277 | 277 | | 129numberofqualifieddesign-builderstonotmorethanfivenorfewerthantwo.Underno |
---|
278 | 278 | | 130circumstancesshallpriceorfeesbeapartoftheprequalificationcriteria.Design-builders |
---|
279 | 279 | | 131maybeinterviewedineitherphaseIorphaseIIoftheprocess.PointsassignedinphaseIof |
---|
280 | 280 | | 132theevaluationprocessshallnotcarryforwardtophaseIIoftheprocess.Allqualifieddesign- |
---|
281 | 281 | | 133buildersshallberankedonpointsgiveninphasesIIandIIIonly. |
---|
282 | 282 | | 134 11.Thepoliticalsubdivisionshallhavediscretiontodisqualifyanydesign-builder |
---|
283 | 283 | | 135who,inthepoliticalsubdivision'sopinion,lackstheminimumqualificationsrequiredto |
---|
284 | 284 | | 136performthework. |
---|
285 | 285 | | HB413 8 137 12.Onceasufficientnumberofnomorethanfiveandnofewerthantwoqualified |
---|
286 | 286 | | 138design-buildershavebeenselected,thedesign-buildersshallhaveaspecifiedamountoftime |
---|
287 | 287 | | 139inwhichtoassemblephaseIIandphaseIIIproposals. |
---|
288 | 288 | | 140 13.PhaseIIoftheprocessshallbeconductedasfollows: |
---|
289 | 289 | | 141 (1)Thepoliticalsubdivisionshallinvitethetopqualifieddesign-buildersto |
---|
290 | 290 | | 142participateinphaseIIoftheprocess; |
---|
291 | 291 | | 143 (2)Adesign-buildershallsubmititsdesignfortheprojecttothelevelofdetail |
---|
292 | 292 | | 144requiredintherequestforproposal.Thedesignproposalshalldemonstratecompliancewith |
---|
293 | 293 | | 145therequirementssetoutintherequestforproposal; |
---|
294 | 294 | | 146 (3)Theabilityofthedesign-buildertomeetthescheduleforcompletingaprojectas |
---|
295 | 295 | | 147specifiedbythepoliticalsubdivisionmaybeconsideredasanelementofevaluationinphase |
---|
296 | 296 | | 148II; |
---|
297 | 297 | | 149 (4)Uptotwentypercentofthepointsawardedtoeachdesign-builderinphaseIImay |
---|
298 | 298 | | 150bebasedoneachdesign-builder'squalificationsandabilitytodesign,contract,anddeliverthe |
---|
299 | 299 | | 151projectontimeandwithinthebudgetofthepoliticalsubdivision; |
---|
300 | 300 | | 152 (5)Undernocircumstancesshallthedesignproposalcontainanyreferencetothecost |
---|
301 | 301 | | 153oftheproposal;and |
---|
302 | 302 | | 154 (6)Thesubmitteddesignsshallbeevaluatedandassignedpointsinaccordancewith |
---|
303 | 303 | | 155therequirementsoftherequestforproposal.PhaseIIshallaccountfornotlessthanforty |
---|
304 | 304 | | 156percentofthetotalpointscoreasspecifiedintherequestforproposal. |
---|
305 | 305 | | 157 14.PhaseIIIshallbeconductedasfollows: |
---|
306 | 306 | | 158 (1)ThephaseIIIproposalshallprovideafirm,fixedcostofdesignandconstruction. |
---|
307 | 307 | | 159Theproposalshallbeaccompaniedbybidsecurityandanyotheritems,suchasstatementsof |
---|
308 | 308 | | 160minorityparticipationasrequiredbytherequestforproposal; |
---|
309 | 309 | | 161 (2)Costproposalsshallbesubmittedinaccordancewiththeinstructionsofthe |
---|
310 | 310 | | 162requestforproposal.Thepoliticalsubdivisionshallrejectanyproposalthatisnotsubmitted |
---|
311 | 311 | | 163ontime.PhaseIIIshallaccountfornotlessthanfortypercentofthetotalpointscoreas |
---|
312 | 312 | | 164specifiedintherequestforproposal; |
---|
313 | 313 | | 165 (3)ProposalsforphaseIIandphaseIIIshallbesubmittedconcurrentlyatthetime |
---|
314 | 314 | | 166andplacespecifiedintherequestforproposal,butinseparateenvelopesorothermeansof |
---|
315 | 315 | | 167submission.ThephaseIIIcostproposalsshallbeopenedonlyafterthephaseIIdesign |
---|
316 | 316 | | 168proposalshavebeenevaluatedandassignedpoints,rankedinorder,andposted; |
---|
317 | 317 | | 169 (4)Costproposalsshallbeopenedandreadaloudatthetimeandplacespecifiedin |
---|
318 | 318 | | 170therequestforproposal.Atthesametimeandplace,theevaluationteamshallmakepublic |
---|
319 | 319 | | 171itsscoringofphaseII.Costproposalsshallbeevaluatedinaccordancewiththerequirements |
---|
320 | 320 | | 172oftherequestforproposal.Inevaluatingthecostproposals,thelowestresponsivebidder |
---|
321 | 321 | | 173shallbeawardedthetotalnumberofpointsassignedtobeawardedinphaseIII.Forallother |
---|
322 | 322 | | HB413 9 174bidders,costpointsshallbecalculatedbyreducingthemaximumpointsavailableinphaseIII |
---|
323 | 323 | | 175byatleastonepercentforeachpercentagepointbywhichthebidderexceedsthelowestbid |
---|
324 | 324 | | 176andthepointsassignedshallbeaddedtothepointsassignedforphaseIIforeachdesign- |
---|
325 | 325 | | 177builder; |
---|
326 | 326 | | 178 (5)Ifthepoliticalsubdivisiondeterminesthatitisnotinthebestinterestofthe |
---|
327 | 327 | | 179politicalsubdivisiontoproceedwiththeprojectpursuanttotheproposalofferedbythe |
---|
328 | 328 | | 180design-builderwiththehighesttotalnumberofpoints,thepoliticalsubdivisionshallrejectall |
---|
329 | 329 | | 181proposals.Inthisevent,allqualifiedandresponsivedesign-builderswithlowerpointtotals |
---|
330 | 330 | | 182shallreceiveastipendandtheresponsivedesign-builderwiththehighesttotalnumberof |
---|
331 | 331 | | 183pointsshallreceiveanamountequaltotwotimesthestipend.Ifthepoliticalsubdivision |
---|
332 | 332 | | 184decidestoawardtheproject,theresponsivedesign-builderwiththehighestnumberofpoints |
---|
333 | 333 | | 185shallbeawardedthecontract;and |
---|
334 | 334 | | 186 (6)Ifallproposalsarerejected,thepoliticalsubdivisionmaysolicitnewproposals |
---|
335 | 335 | | 187usingdifferentdesigncriteria,budgetconstraints,orqualifications. |
---|
336 | 336 | | 188 15.Asaninducementtoqualifieddesign-builders,thepoliticalsubdivisionshallpay |
---|
337 | 337 | | 189areasonablestipend,theamountofwhichshallbeestablishedintherequestforproposal,to |
---|
338 | 338 | | 190eachprequalifieddesign-builderwhoseproposalisresponsivebutnotaccepted.Suchstipend |
---|
339 | 339 | | 191shallbenolessthanone-halfofonepercentofthetotalprojectbudget.Uponpaymentofthe |
---|
340 | 340 | | 192stipendtoanyunsuccessfuldesign-builder,thepoliticalsubdivisionshallacquirea |
---|
341 | 341 | | 193nonexclusiverighttousethedesignsubmittedbythedesign-builder,andthedesign- |
---|
342 | 342 | | 194buildershallhavenofurtherliabilityfortheuseofthedesignbythepoliticalsubdivisionin |
---|
343 | 343 | | 195anymanner.Ifthedesign-builderdesirestoretainallrightsandinterestinthedesign |
---|
344 | 344 | | 196proposed,thedesign-buildershallforfeitthestipend. |
---|
345 | 345 | | 197 16.(1)Asusedinthissubsection,"wastewaterorwatercontract"meansanydesign- |
---|
346 | 346 | | 198buildcontractthatinvolvestheprovisionofengineeringandconstructionserviceseither |
---|
347 | 347 | | 199directlybyapartytothecontractorthroughsubcontractorsretainedbyapartytothecontract |
---|
348 | 348 | | 200forawastewaterorwaterstorage,conveyance,ortreatmentfacilityproject. |
---|
349 | 349 | | 201 (2)Anypoliticalsubdivisionmayenterintoawastewaterorwatercontractfor |
---|
350 | 350 | | 202design-buildofawastewaterorwaterproject. |
---|
351 | 351 | | 203 (3)Indisbursingcommunitydevelopmentblockgrantsunder42U.S.C.Sections |
---|
352 | 352 | | 2045301to5321,thedepartmentofeconomicdevelopmentshallnotrejectwastewaterorwater |
---|
353 | 353 | | 205projectssolelyforutilizingwastewaterorwatercontracts. |
---|
354 | 354 | | 206 (4)Thedepartmentofnaturalresourcesshallnotprecludewastewaterorwater |
---|
355 | 355 | | 207contractsfromconsiderationforfundingprovidedbythewaterandwastewaterloanfund |
---|
356 | 356 | | 208undersection644.122. |
---|
357 | 357 | | HB413 10 209 (5)Apoliticalsubdivisionplanningawastewaterorwaterdesign-buildprojectshall |
---|
358 | 358 | | 210retainanengineerdulylicensedinthisstatetoassistinpreparinganynecessarydocuments |
---|
359 | 359 | | 211andspecificationsandevaluationsofdesign-buildproposals. |
---|
360 | 360 | | 212 17.Thepaymentbondrequirementsofsection107.170shallapplytothedesign- |
---|
361 | 361 | | 213buildproject.Allpersonsfurnishingdesignservicesshallbedeemedtobecoveredbythe |
---|
362 | 362 | | 214paymentbondthesameasanypersonfurnishinglaborandmaterials.Theperformancebond |
---|
363 | 363 | | 215forthedesign-buildershallnotcoveranydamagesofthetypespecifiedtobecoveredbythe |
---|
364 | 364 | | 216professionalliabilityinsuranceestablishedbythepoliticalsubdivisionintherequestfor |
---|
365 | 365 | | 217proposals. |
---|
366 | 366 | | 218 18.Anypersonorfirmperformingarchitectural,engineering,landscapearchitecture, |
---|
367 | 367 | | 219orland-surveyingservicesforthedesign-builderonthedesign-buildprojectshallbeduly |
---|
368 | 368 | | 220licensedorauthorizedinthisstatetoprovidesuchservicesasrequiredbychapter327. |
---|
369 | 369 | | 221 19.Anypoliticalsubdivisionengagedinaprojectunderthissectionwhichimpactsa |
---|
370 | 370 | | 222railroadregulatedbytheFederalRailroadAdministrationshallconsultwiththeaffected |
---|
371 | 371 | | 223railroadonrequiredspecificationsrelatingtoclearance,safety,insurance,and |
---|
372 | 372 | | 224indemnificationtobeincludedintheconstructiondocumentsforsuchproject. |
---|
373 | 373 | | 225 20.Undersection327.465,anydesign-builderthatentersintoadesign-buildcontract |
---|
374 | 374 | | 226withapoliticalsubdivisionisexemptfromtherequirementthatsuchpersonorentityholda |
---|
375 | 375 | | 227licenseorthatsuchcorporationholdacertificateofauthorityifthearchitectural,engineering, |
---|
376 | 376 | | 228orland-surveyingservicestobeperformedunderthedesign-buildcontractareperformed |
---|
377 | 377 | | 229throughsubcontractsorjointventureswithproperlylicensedorauthorizedpersonsorentities, |
---|
378 | 378 | | 230andnotperformedbythedesign-builderoritsownemployees. |
---|
379 | 379 | | 231 21.Thissectionshallnotapplyto: |
---|
380 | 380 | | 232 (1)AnymetropolitansewerdistrictestablishedunderArticleVI,Section30(a)ofthe |
---|
381 | 381 | | 233ConstitutionofMissouri;or |
---|
382 | 382 | | 234 (2)Anyspecialchartercity,oranycityorcountygovernedbyhomeruleunder |
---|
383 | 383 | | 235ArticleVI,[Section18]Sections18(a)to18(r)orSection19oftheConstitutionofMissouri |
---|
384 | 384 | | 236thathasadoptedadesign-buildprocessviaordinance,rule,orregulation. |
---|
385 | 385 | | 237 [22.Theauthoritytousedesign-buildanddesign-buildcontractsprovidedunderthis |
---|
386 | 386 | | 238sectionshallexpireSeptember1,2026.] |
---|
387 | 387 | | âś” |
---|
388 | 388 | | HB413 11 |
---|