 A BILL TO BE ENTITLED
 AN ACT
 relating to the waiver and release of a mechanic's, contractor's, or
 materialman's lien or payment bond claim.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 53.085(c), Property Code, is amended to
 read as follows:
 (c)  The affidavit may include:
 (1)  a waiver or release of lien rights or payment bond
 claims by the affiant that is conditioned on the receipt of actual
 payment or collection of funds when payment is made by check or
 draft, as provided by Subchapter L;
 (2)  a warranty or representation that certain bills or
 classes of bills will be paid by the affiant from funds paid in
 reliance on the affidavit; and
 (3)  an indemnification by the affiant for any loss or
 expense resulting from false or incorrect information in the
 affidavit.
 SECTION 2.  Chapter 53, Property Code, is amended by adding
 Subchapter L to read as follows:
 SUBCHAPTER L. WAIVER AND RELEASE OF LIEN OR PAYMENT BOND CLAIM
 Sec. 53.281.  WAIVER AND RELEASE OF LIEN OR PAYMENT BOND
 CLAIM.  (a)  Any waiver and release of a lien or payment bond claim
 under this chapter is unenforceable unless a waiver and release is
 executed and delivered in accordance with this subchapter.
 (b)  A waiver and release is effective to release the owner,
 the owner's property, the contractor, and the surety on a payment
 bond from claims and liens only if:
 (1)  the waiver and release substantially complies with
 one of the forms prescribed by this subchapter;
 (2)  the waiver and release is signed by the claimant or
 the claimant's authorized agent and notarized; and
 (3)  in the case of a conditional release, evidence of
 payment to the claimant exists.
 Sec. 53.282.  CONDITIONS FOR WAIVER, RELEASE, OR IMPAIRMENT
 OF LIEN OR PAYMENT BOND CLAIM.  (a)  A statement purporting to
 waive, release, or otherwise adversely affect a lien or payment
 bond claim is not enforceable and does not create an estoppel or
 impairment of a lien or payment bond claim unless:
 (1)  the statement is in writing and complies with this
 subchapter;
 (2)  the claimant has actually received payment in good
 and sufficient funds in full for the lien or payment bond claim; or
 (3)  the statement is:
 (A)  in a written original contract or subcontract
 for the construction, remodel, or repair of a single-family house
 or duplex; and
 (B)  made before labor or materials are provided
 under the original contract or subcontract and a good faith dispute
 exists regarding the quality of the labor or material provided by
 the original contractor or subcontractor that has resulted in the
 nonpayment of the original contractor or subcontractor.
 (b)  This section does not affect the enforceability of an
 accord and satisfaction regarding a bona fide dispute or any
 agreement made in settlement of an action pending in any court if
 the accord and satisfaction or agreement made in settlement makes
 specific reference to the lien or payment bond claim.
 (c)  The filing of a lien rendered unenforceable by a lien
 waiver under Subsection (a)(3) does not violate Section 12.002,
 Civil Practice and Remedies Code.
 Sec. 53.283.  UNCONDITIONAL WAIVER AND RELEASE: PAYMENT
 REQUIRED.  A person may not require a claimant or potential claimant
 to execute an unconditional waiver and release for a progress
 payment or final payment amount unless the claimant or potential
 claimant received payment in that amount in good and sufficient
 funds.
 Sec. 53.284.  FORMS FOR WAIVER AND RELEASE OF LIEN OR PAYMENT
 BOND CLAIM.  (a)  A waiver and release given by a claimant or
 potential claimant is unenforceable unless it substantially
 complies with the applicable form described by Subsections (b)-(e).
 (b)  If a claimant or potential claimant is required to
 execute a waiver and release in exchange for or to induce the
 payment of a progress payment and is not paid in exchange for the
 waiver and release or if a single payee check or joint payee check
 is given in exchange for the waiver and release, the waiver and
 release must read:
 "CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
 "Project ___________________
 "Job No. ___________________
 "On receipt by the signer of this document of a check from
 ________________ (maker of check) in the sum of $__________ payable
 to _____________________ (payee or payees of check) and when the
 check has been properly endorsed and has been paid by the bank on
 which it is drawn, this document becomes effective to release any
 mechanic's lien right, any right arising from a payment bond that
 complies with a state or federal statute, any common law payment
 bond right, any claim for payment, and any rights under any similar
 ordinance, rule, or statute related to claim or payment rights for
 persons in the signer's position that the signer has on the
 property of ________________ (owner) located at
 ______________________ (location) to the following extent:
 ______________________ (job description).
 "This release covers a progress payment for all labor,
 services, equipment, or materials furnished to the property or to
 __________________ (person with whom signer contracted) as
 indicated in the attached statement(s) or progress payment
 request(s), except for unpaid retention, pending modifications and
 changes, or other items furnished.
 "Before any recipient of this document relies on this
 document, the recipient should verify evidence of payment to the
 signer.
 "The signer warrants that the signer has already paid or will
 use the funds received from this progress payment to promptly pay in
 full all of the signer's laborers, subcontractors, materialmen, and
 suppliers for all work, materials, equipment, or services provided
 for or to the above referenced project in regard to the attached
 statement(s) or progress payment request(s).
 "Date ____________________________
 "_________________________________ (Company name)
 "By ______________________________ (Signature)
 "_________________________________ (Title)"
 (c)  If a claimant or potential claimant is required to
 execute an unconditional waiver and release to prove the receipt of
 good and sufficient funds for a progress payment and the claimant or
 potential claimant asserts in the waiver and release that the
 claimant or potential claimant has been paid the progress payment,
 the waiver and release must:
 (1)  contain a notice at the top of the document,
 printed in bold type at least as large as the largest type used in
 the document, but not smaller than 10-point type, that reads:
 "NOTICE:
 "This document waives rights unconditionally and states that
 you have been paid for giving up those rights. This document may be
 enforceable against you if you sign it, even if you have not been
 paid. It is unlawful for a person to require you to sign this
 document if you have not been paid the payment amount set forth
 below.  If you have not been paid, use a conditional release form.";
 and
 (2)  below the notice, read:
 "UNCONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
 "Project ___________________
 "Job No. ___________________
 "The signer of this document has been paid and has received a
 progress payment in the sum of $___________ for all labor,
 services, equipment, or materials furnished to the property or to
 _____________________ (person with whom signer contracted) on the
 property of _______________________ (owner) located at
 ______________________ (location) to the following extent:
 ______________________ (job description).  The signer therefore
 waives and releases any mechanic's lien right, any right arising
 from a payment bond that complies with a state or federal statute,
 any common law payment bond right, any claim for payment, and any
 rights under any similar ordinance, rule, or statute related to
 claim or payment rights for persons in the signer's position that
 the signer has on the above referenced project to the following
 extent:
 "This release covers a progress payment for all labor,
 services, equipment, or materials furnished to the property or to
 __________________ (person with whom signer contracted) as
 indicated in the attached statement(s) or progress payment
 request(s), except for unpaid retention, pending modifications and
 changes, or other items furnished.
 "The signer warrants that the signer has already paid or will
 use the funds received from this progress payment to promptly pay in
 full all of the signer's laborers, subcontractors, materialmen, and
 suppliers for all work, materials, equipment, or services provided
 for or to the above referenced project in regard to the attached
 statement(s) or progress payment request(s).
 "Date ____________________________
 "_________________________________ (Company name)
 "By ______________________________ (Signature)
 "_________________________________ (Title)"
 (d)  If a claimant or potential claimant is required to
 execute a waiver and release in exchange for or to induce the
 payment of a final payment and is not paid in good and sufficient
 funds in exchange for the waiver and release or if a single payee
 check or joint payee check is given in exchange for the waiver and
 release, the waiver and release must read:
 "CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
 "Project ___________________
 "Job No. ___________________
 "On receipt by the signer of this document of a check from
 ________________ (maker of check) in the sum of $____________
 payable to _____________________ (payee or payees of check) and
 when the check has been properly endorsed and has been paid by the
 bank on which it is drawn, this document becomes effective to
 release any mechanic's lien right, any right arising from a payment
 bond that complies with a state or federal statute, any common law
 payment bond right, any claim for payment, and any rights under any
 similar ordinance, rule, or statute related to claim or payment
 rights for persons in the signer's position that the signer has on
 the property of _____________________ (owner) located at
 ______________________ (location) to the following extent:
 ______________________ (job description).
 "This release covers the final payment to the signer for all
 labor, services, equipment, or materials furnished to the property
 or to __________________ (person with whom signer contracted).
 "Before any recipient of this document relies on this
 document, the recipient should verify evidence of payment to the
 signer.
 "The signer warrants that the signer has already paid or will
 use the funds received from this final payment to promptly pay in
 full all of the signer's laborers, subcontractors, materialmen, and
 suppliers for all work, materials, equipment, or services provided
 for or to the above referenced project up to the date of this waiver
 and release.
 "Date ____________________________
 "_________________________________ (Company name)
 "By ______________________________ (Signature)
 "_________________________________ (Title)"
 (e)  If a claimant or potential claimant is required to
 execute an unconditional waiver and release to prove the receipt of
 good and sufficient funds for a final payment and the claimant or
 potential claimant asserts in the waiver and release that the
 claimant or potential claimant has been paid the final payment, the
 waiver and release must:
 (1)  contain a notice at the top of the document,
 printed in bold type at least as large as the largest type used in
 the document, but not smaller than 10-point type, that reads:
 "NOTICE:
 "This document waives rights unconditionally and states that
 you have been paid for giving up those rights. This document may be
 enforceable against you if you sign it, even if you have not been
 paid.  It is unlawful for a person to require you to sign this
 document if you have not been paid the payment amount set forth
 below.  If you have not been paid, use a conditional release form.";
 and
 (2)  below the notice, read:
 "UNCONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
 "Project ___________________
 "Job No. ___________________
 "The signer of this document has been paid in full for all
 labor, services, equipment, or materials furnished to the property
 or to ___________________ (person with whom signer contracted) on
 the property of ______________________ (owner) located at
 ______________________ (location) to the following extent:
 ______________________ (job description).  The signer therefore
 waives and releases any mechanic's lien right, any right arising
 from a payment bond that complies with a state or federal statute,
 any common law payment bond right, any claim for payment, and any
 rights under any similar ordinance, rule, or statute related to
 claim or payment rights for persons in the signer's position.
 "The signer warrants that the signer has already paid or will
 use the funds received from this final payment to promptly pay in
 full all of the signer's laborers, subcontractors, materialmen, and
 suppliers for all work, materials, equipment, or services provided
 for or to the above referenced project up to the date of this waiver
 and release.
 "Date ____________________________
 "_________________________________ (Company name)
 "By ______________________________ (Signature)
 "_________________________________ (Title)"
 Sec. 53.285.  ATTEMPTED COMPLIANCE. (a) A waiver or release
 shall be construed to comply with this subchapter and is
 enforceable in the same manner as a waiver and release under this
 subchapter if the waiver or release:
 (1)  is furnished in attempted compliance with this
 subchapter; or
 (2)  evidences by its terms intent to comply with this
 subchapter.
 (b)  Any provision in any waiver or release furnished in
 attempted compliance with this subchapter that expands or restricts
 the rights or liabilities provided under this subchapter shall be
 disregarded and the provisions of this subchapter shall be read
 into that waiver or release.
 (c)  This section expires August 31, 2012.
 Sec. 53.286.  PUBLIC POLICY. (a) Notwithstanding any other
 law and except as provided by Section 53.282, any contract,
 agreement, or understanding purporting to waive the right to file
 or enforce any lien or claim created under this chapter is void as
 against public policy.
 (b)  This subchapter does not apply to a written agreement to
 subordinate, release, or satisfy all or part of a lien claimed after
 a notice of lien has been filed.
 SECTION 3.  The changes in law made by this Act apply only to
 a contract executed on or after September 1, 2011.  A contract
 executed before September 1, 2011, is covered by the law applicable
 to the contract immediately before the effective date of this Act,
 and the former law is continued in effect for that purpose.