Texas 2017 - 85th 1st C.S.

Texas Senate Bill SB13 Latest Draft

Bill / Engrossed Version Filed 07/26/2017

                            By: Burton, et al. S.B. No. 13


 A BILL TO BE ENTITLED
 AN ACT
 relating to the issuance of a permit by a political subdivision.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 214.904, Local Government Code, is
 amended to read as follows:
 Sec. 214.904.  PROCEDURES AND PERIOD [TIME] FOR APPROVAL OR
 DENIAL [ISSUANCE] OF MUNICIPAL [BUILDING] PERMIT APPLICATIONS;
 PROHIBITED PERMIT REQUIREMENTS. (a)  In this section, "permit" and
 "project" have the meanings assigned by Section 245.001.
 (a-1)  This section applies [only] to any [a] permit required
 by a municipality that relates to any project [to erect or improve a
 building or other structure in the municipality or its
 extraterritorial jurisdiction].
 (b)  Not later than the 30th [45th] day after the date an
 application for a permit is submitted, the municipality must:
 (1)  grant or make a preliminary determination to deny
 the permit;
 (2)  provide written notice to the applicant stating
 the reasons why the municipality has been unable to act on [grant or
 deny] the permit application; [or]
 (3)  reach a written agreement with the applicant
 providing for a deadline not later than the 120th day after the date
 the application was submitted for granting or denying the permit;
 or
 (4)  grant conditional approval of the permit and
 provide written notice to the applicant stating:
 (A)  the applicant has met the municipality's
 requirements for the permit;
 (B)  the municipality has not received
 documentation of state or federal approval relating to the permit
 that is required under state or federal law;
 (C)  the municipality is granting conditional
 approval of the permit; and
 (D)  the municipality will grant final approval of
 the permit or deny the permit, as applicable, on the date the
 municipality receives documentation of the state or federal
 approval or disapproval.
 (c)  For a permit application for which notice is provided
 under Subsection (b)(2), the municipality must grant or make a
 preliminary determination to deny the permit not later than the
 15th [30th] day after the date the notice is received. A
 municipality may extend the period for the municipality to act on an
 application under this subsection once by an additional 15 days.
 (c-1)  For a permit application for which notice is provided
 under Subsection (b)(4), the municipality must grant the final
 approval of the permit or deny the permit, as applicable, on the
 date the municipality receives documentation of the state or
 federal approval or disapproval relating to the permit.
 (d)  If a municipality fails to act on [grant or deny] a
 permit application within [in] the period [time] required by
 Subsection (c) or (c-1) or by an agreement under Subsection (b)(3),
 the permit application is considered approved and the municipality:
 (1)  may not collect any permit fees associated with
 the application; [and]
 (2)  shall refund to the applicant any permit fees
 associated with the application that have been collected; and
 (3)  shall issue the permit.
 (e)  If a municipality makes a preliminary determination to
 deny a permit application, the municipality must send written
 notice of the determination to the applicant not later than the
 first business day after the date the determination is made
 stating:
 (1)  a plain language description of each deficiency
 that is a reason for the determination, including a citation to the
 specific ordinance, order, regulation, or policy relevant to the
 determination;
 (2)  general guidance regarding how to remedy each
 specified deficiency; and
 (3)  a deadline not earlier than the 30th day after the
 date the notice is sent for the applicant to complete the remedial
 actions specified in the notice before the denial becomes final.
 (f)  If the municipality makes a reasonable determination
 that a new deficiency has arisen from a remedial action taken by the
 applicant, the municipality must send written notice not later than
 the first business day after the date the determination is made
 stating:
 (1)  a plain language description of each new
 deficiency, including a citation to the specific ordinance, order,
 regulation, or policy relevant to the deficiency;
 (2)  general guidance regarding how to remedy each
 specified deficiency; and
 (3)  a new deadline not earlier than the 30th day after
 the date the notice is sent under this subsection for the applicant
 to complete all of the remedial actions.
 (g)  If an applicant substantially completes the remedial
 actions specified in the notice under Subsection (e) and, if
 applicable, Subsection (f) within the period required, the
 applicant may request reconsideration of the determination.  If the
 municipality determines the applicant has substantially completed
 the specified remedial actions, the municipality shall:
 (1)  grant the permit; or
 (2)  conditionally approve the permit, if the
 municipality has not received documentation of state or federal
 approval relating to the permit that is required under state or
 federal law.
 (g-1)  Not later than the 15th day after the date the
 applicant's request for reconsideration is received, the
 municipality shall send the applicant written notice of:
 (1)  a final determination to grant or deny the permit;
 or
 (2)  a determination to conditionally approve the
 permit until state or federal approval or disapproval relating to
 the permit is received.
 (g-2)  If the municipality fails to send notice of a final
 determination to grant or deny a permit within the period required
 by Subsection (g-1), the permit application is considered approved
 and the municipality shall issue the permit. If the municipality
 fails to send notice of a conditional approval of the permit within
 the period required by Subsection (g-1), the permit application is
 considered conditionally approved by the municipality and the
 municipality shall issue or deny the permit, as applicable, on the
 date the municipality receives documentation of the state or
 federal approval or disapproval relating to the permit.
 (h)  Written notice of the municipality's final
 determination that a permit is denied must include the information
 required by Subsections (e)(1) and (2) and, if applicable,
 Subsections (f)(1) and (2) in addition to written findings of the
 reasons the municipality determined that any remedial actions taken
 by the applicant were insufficient to correct the deficiencies
 specified in the notice provided under Subsection (e) or (f).
 (i)  Any final determination that a permit is denied may not
 be based on:
 (1)  a reason or remedial requirement that was not
 previously disclosed to the applicant in the notice required under
 Subsection (e) or (f); or
 (2)  a requirement for the applicant to comply with any
 ordinance, order, regulation, or policy that is not substantially
 related to the project for which the permit is required.
 (j)  A municipality may not adopt or enforce an ordinance,
 order, regulation, or policy relating to granting or denying a
 permit that:
 (1)  restricts or prohibits the right of an applicant
 to reapply for a permit that was the subject of a denied permit
 application;
 (2)  requires a private employer to offer wages higher
 than the wages required under Chapter 62, Labor Code; or
 (3)  authorizes on-site monitoring of a private
 employer by a nongovernmental entity.
 (k)  The right of a permit applicant to the issuance of a
 determination or a permit as required by this section may be
 enforced only through mandamus or declaratory or injunctive relief.
 A municipality's immunity from suit is waived in regard to an action
 under this section.
 SECTION 2.  Section 233.901, Local Government Code, is
 amended to read as follows:
 Sec. 233.901.  PROCEDURES AND PERIOD [TIME] FOR APPROVAL OR
 DENIAL [ISSUANCE] OF COUNTY [BUILDING] PERMIT APPLICATIONS;
 PROHIBITED PERMIT REQUIREMENTS. (a)  In this section, "permit" and
 "project" have the meanings assigned by Section 245.001.
 (a-1)  This section applies [only] to any [a] permit required
 by a county that relates to any project [with a population of 3.3
 million or more to construct or improve a building or other
 structure in the county], but does not apply to a permit for an
 on-site sewage disposal system.
 (b)  Not later than the 30th [45th] day after the date an
 application for a permit is submitted, the county must:
 (1)  grant or make a preliminary determination to deny
 the permit;
 (2)  provide written notice to the applicant stating
 the reasons why the county has been unable to act on the permit
 application; [or]
 (3)  reach a written agreement with the applicant
 providing for a deadline not later than the 120th day after the date
 the application was submitted for granting or denying the permit;
 or
 (4)  grant conditional approval of the permit and
 provide written notice to the applicant stating:
 (A)  the applicant has met the county's
 requirements for the permit;
 (B)  the county has not received documentation of
 state or federal approval relating to the permit that is required
 under state or federal law;
 (C)  the county is granting conditional approval
 of the permit; and
 (D)  the county will grant final approval of the
 permit or deny the permit, as applicable, on the date the county
 receives documentation of the state or federal approval or
 disapproval.
 (c)  For a permit application for which notice is provided
 under Subsection (b)(2), the county must grant or make a
 preliminary determination to deny the permit not later than the
 15th [30th] day after the date the notice is received. A county may
 extend the period for the county to act on an application under this
 subsection once by an additional 15 days.
 (c-1)  For a permit application for which notice is provided
 under Subsection (b)(4), the county must grant the final approval
 of the permit or deny the permit, as applicable, on the date the
 county receives documentation of the state or federal approval or
 disapproval relating to the permit.
 (d)  If a county fails to act on a permit application within
 [in] the period [time] required by Subsection (c) or (c-1) or by an
 agreement under Subsection (b)(3), the permit application is
 considered approved and the county:
 (1)  may not collect any permit fees associated with
 the application; [and]
 (2)  shall refund to the applicant any permit fees
 associated with the application that have been collected; and
 (3)  shall issue the permit.
 (e)  If a county makes a preliminary determination to deny a
 permit application, the county must send written notice of the
 determination to the applicant not later than the first business
 day after the date the determination is made stating:
 (1)  a plain language description of each deficiency
 that is a reason for the determination, including a citation to the
 specific ordinance, order, regulation, or policy relevant to the
 determination;
 (2)  general guidance regarding how to remedy each
 specified deficiency; and
 (3)  a deadline not earlier than the 30th day after the
 date the notice is sent for the applicant to complete the remedial
 actions specified in the notice before the denial becomes final.
 (f)  If the county makes a reasonable determination that a
 new deficiency has arisen from a remedial action taken by the
 applicant, the county must send written notice not later than the
 first business day after the date the determination is made
 stating:
 (1)  a plain language description of each new
 deficiency, including a citation to the specific ordinance, order,
 regulation, or policy relevant to the deficiency;
 (2)  general guidance regarding how to remedy each
 specified deficiency; and
 (3)  a new deadline not earlier than the 30th day after
 the date the notice is sent under this subsection for the applicant
 to complete all of the remedial actions.
 (g)  If an applicant substantially completes the remedial
 actions specified in the notice under Subsection (e) and, if
 applicable, Subsection (f) within the period required, the
 applicant may request reconsideration of the determination.  If the
 county determines the applicant has substantially completed the
 specified remedial actions, the county shall:
 (1)  grant the permit; or
 (2)  conditionally approve the permit, if the county
 has not received documentation of state or federal approval
 relating to the permit that is required under state or federal law.
 (g-1)  Not later than the 15th day after the date the
 applicant's request for reconsideration is received, the county
 shall send the applicant written notice of:
 (1)  a final determination to grant or deny the permit;
 or
 (2)  a determination to conditionally approve the
 permit until state or federal approval or disapproval relating to
 the permit is received.
 (g-2)  If the county fails to send notice of a final
 determination to grant or deny a permit within the period required
 by Subsection (g-1), the permit application is considered approved
 and the county shall issue the permit. If the county fails to send
 notice of a conditional approval of the permit within the period
 required by Subsection (g-1), the permit application is considered
 conditionally approved by the county and the county shall issue or
 deny the permit, as applicable, on the date the county receives
 documentation of the state or federal approval or disapproval
 relating to the permit.
 (h)  Written notice of the county's final determination that
 a permit is denied must include the information required by
 Subsections (e)(1) and (2) and, if applicable, Subsections (f)(1)
 and (2) in addition to written findings of the reasons the county
 determined that any remedial actions taken by the applicant were
 insufficient to correct the deficiencies specified in the notice
 provided under Subsection (e) or (f).
 (i)  Any final determination that a permit is denied may not
 be based on:
 (1)  a reason or remedial requirement that was not
 previously disclosed to the applicant in the notice required under
 Subsection (e) or (f); or
 (2)  a requirement for the applicant to comply with any
 ordinance, order, regulation, or policy that is not substantially
 related to the project for which the permit is required.
 (j)  A county may not adopt or enforce an ordinance, order,
 regulation, or policy relating to granting or denying a permit
 that:
 (1)  restricts or prohibits the right of an applicant
 to reapply for a permit that was the subject of a denied permit
 application;
 (2)  requires a private employer to offer wages higher
 than the wages required under Chapter 62, Labor Code; or
 (3)  authorizes on-site monitoring of a private
 employer by a nongovernmental entity.
 (k)  The right of a permit applicant to the issuance of a
 determination or a permit as required by this section may be
 enforced only through mandamus or declaratory or injunctive relief.
 A county's immunity from suit is waived in regard to an action under
 this section.
 (l)  Nothing in this section shall be construed to authorize
 a county to require a permit to undertake a project in the county.
 SECTION 3.  Chapter 250, Local Government Code, is amended
 by adding Section 250.010 to read as follows:
 Sec. 250.010.  EXPEDITED PERMITTING PROCEDURES. (a)  In
 this section, "permit" and "political subdivision" have the
 meanings assigned by Section 245.001.
 (b)  This title does not prohibit a political subdivision
 from adopting procedures to provide a shorter period than provided
 by law for the approval of a permit.
 (c)  Any ordinance, order, regulation, or policy providing
 procedures for the expedited approval of a permit must comply with
 the requirements of other law, other than the period for the
 approval of a permit.
 (d)  A procedure authorized by this section may not:
 (1)  restrict or prohibit the right of an applicant to
 reapply for a permit that was the subject of a denied expedited
 permit application; or
 (2)  include any additional conditions or requirements
 for the expedited approval of the permit, other than a reasonable
 fee to offset the increased costs of expediting the permit.
 SECTION 4.  The changes in law made by this Act apply only to
 a permit application filed on or after the effective date of this
 Act. An application filed before the effective date of this Act is
 governed by the law in effect immediately before the effective date
 of this Act, and the former law is continued in effect for that
 purpose.
 SECTION 5.  This Act takes effect immediately if it receives
 a vote of two-thirds of all the members elected to each house, as
 provided by Section 39, Article III, Texas Constitution.  If this
 Act does not receive the vote necessary for immediate effect, this
 Act takes effect December 1, 2017.