13 | 12 | | redesignated as Section 223.2001, Transportation Code, and amended |
---|
14 | 13 | | to read as follows: |
---|
15 | 14 | | Sec. 223.2001. DEFINITION. [(b)] In this subchapter, |
---|
16 | 15 | | "comprehensive development agreement" means an agreement that, at a |
---|
17 | 16 | | minimum, provides for the design and construction, reconstruction, |
---|
18 | 17 | | rehabilitation, expansion, or improvement of a project described in |
---|
19 | 18 | | Section 223.201(a) [Subsection (a)] and may also provide for the |
---|
20 | 19 | | financing, acquisition, maintenance, or operation of a project |
---|
21 | 20 | | described in that section [Subsection (a)]. |
---|
22 | 21 | | SECTION 2. Subchapter E, Chapter 223, Transportation Code, |
---|
23 | 22 | | is amended by adding Section 223.2002 to read as follows: |
---|
24 | 23 | | Sec. 223.2002. LIMITATION. The department may enter into a |
---|
29 | 30 | | (f) The department may enter into a comprehensive |
---|
30 | 31 | | development agreement [only] for all or part of[: |
---|
31 | 32 | | [(1)] the State Highway 99 (Grand Parkway) project[; |
---|
32 | 33 | | [(2) the Interstate Highway 35E managed lanes project |
---|
33 | 34 | | in Dallas and Denton Counties from Interstate Highway 635 to U.S. |
---|
34 | 35 | | Highway 380; |
---|
35 | 36 | | [(3) the Interstate Highway 35W project in Tarrant |
---|
36 | 37 | | County from Interstate Highway 30 to State Highway 114; |
---|
37 | 38 | | [(4) the State Highway 183 managed lanes project in |
---|
38 | 39 | | Tarrant and Dallas Counties from State Highway 121 to Interstate |
---|
39 | 40 | | Highway 35E; |
---|
40 | 41 | | [(5) the Interstate Highway 35E/U.S. Highway 67 |
---|
41 | 42 | | Southern Gateway project in Dallas County, including: |
---|
42 | 43 | | [(A) Interstate Highway 35E from 8th Street to |
---|
43 | 44 | | Interstate Highway 20; and |
---|
44 | 45 | | [(B) U.S. Highway 67 from Interstate Highway 35E |
---|
45 | 46 | | to Farm-to-Market Road 1382 (Belt Line Road); |
---|
46 | 47 | | [(6) the State Highway 288 project from U.S. Highway |
---|
47 | 48 | | 59 to south of State Highway 6 in Brazoria County and Harris County; |
---|
48 | 49 | | [(7) the U.S. Highway 290 managed lanes project in |
---|
49 | 50 | | Harris County from Interstate Highway 610 to State Highway 99; |
---|
50 | 51 | | [(8) the Interstate Highway 820 project from State |
---|
51 | 52 | | Highway 183 to Randol Mill Road; |
---|
52 | 53 | | [(9) the State Highway 114 project in Dallas County |
---|
53 | 54 | | from State Highway 121 to State Highway 183; |
---|
54 | 55 | | [(10) the Loop 12 project in Dallas County from State |
---|
55 | 56 | | Highway 183 to Interstate Highway 35E; |
---|
56 | 57 | | [(11) the Loop 9 project in Dallas and Ellis Counties |
---|
57 | 58 | | from Interstate Highway 20 to U.S. Highway 67; and |
---|
58 | 59 | | [(12) the U.S. Highway 181 Harbor Bridge project in |
---|
59 | 60 | | Nueces County between U.S. Highway 181 at Beach Avenue and |
---|
60 | 61 | | Interstate Highway 37]. |
---|
61 | 69 | | SECTION 4. Section 223.2012(a), Transportation Code, is |
---|
62 | 70 | | amended to read as follows: |
---|
63 | 71 | | (a) In this section, the North Tarrant Express project is |
---|
64 | 72 | | the project on Interstate Highway 35W in Tarrant County from |
---|
65 | 73 | | Interstate Highway 30 to State Highway 114 that was [described by |
---|
66 | 74 | | Section 223.201(f)(3)] entered into on June 23, 2009. |
---|
67 | 75 | | SECTION 5. Subchapter E, Chapter 223, Transportation Code, |
---|
68 | 76 | | is amended by adding Section 223.2014 to read as follows: |
---|
69 | 77 | | Sec. 223.2014. AUTHORIZED PROJECTS. (a) The department |
---|
70 | 78 | | may enter into a comprehensive development agreement for: |
---|
81 | | - | (5) a project listed under Section 370.3051. |
---|
82 | | - | (b) The department may combine in a comprehensive |
---|
83 | | - | development agreement: |
---|
84 | | - | (1) two or more projects authorized in this section; |
---|
85 | | - | or |
---|
86 | | - | (2) a project authorized in this section and a |
---|
87 | | - | facility under Chapter 91. |
---|
88 | | - | (c) This section expires August 31, 2029. |
---|
89 | | - | SECTION 6. Section 223.202, Transportation Code, is amended |
---|
90 | | - | to read as follows: |
---|
91 | | - | Sec. 223.202. LIMITATION ON [DEPARTMENT] FINANCIAL |
---|
92 | | - | PARTICIPATION. (a) The [amount of money disbursed by the] |
---|
93 | | - | department may not disburse money from the state highway fund or |
---|
94 | | - | [and] the Texas mobility fund [during a federal fiscal year] to pay |
---|
95 | | - | all or part of the actual cost of construction for a project |
---|
96 | | - | developed [the costs] under a comprehensive development agreement |
---|
97 | | - | [agreements may not exceed 40 percent of the obligation authority |
---|
98 | | - | under the federal-aid highway program that is distributed to this |
---|
99 | | - | state for that fiscal year]. |
---|
100 | | - | (b) This section does not preclude the expenditure of funds |
---|
101 | | - | by the department, or the disbursement of funds by the department to |
---|
102 | | - | another governmental entity, for activities related to a project |
---|
103 | | - | ultimately developed under a comprehensive development agreement, |
---|
104 | | - | including: |
---|
105 | | - | (1) environmental review; |
---|
106 | | - | (2) right-of-way acquisition; |
---|
107 | | - | (3) traffic estimates; |
---|
108 | | - | (4) preliminary engineering; |
---|
109 | | - | (5) feasibility studies; and |
---|
110 | | - | (6) necessary or incidental administrative, legal, |
---|
111 | | - | and other expenses. |
---|
112 | | - | SECTION 7. Section 223.208, Transportation Code, is amended |
---|
113 | | - | by adding Subsection (i) to read as follows: |
---|
114 | | - | (i) Notwithstanding Subsection (h), a comprehensive |
---|
115 | | - | development agreement entered into on or before March 22, 2007, for |
---|
116 | | - | State Highway 130 from U.S. Highway 183 to Interstate Highway 10 |
---|
117 | | - | (Segments 5 and 6) may be amended at the discretion of the |
---|
118 | | - | department to extend the duration of the agreement and other |
---|
119 | | - | agreement terms if the amendment outlines the financial and other |
---|
120 | | - | benefits the state will receive from each amendment. The amendment |
---|
121 | | - | must require the private participant to: |
---|
122 | | - | (1) design, finance, and cause to be constructed a |
---|
123 | | - | non-tolled connector between Interstate Highway 35 and State |
---|
124 | | - | Highway 130 that will be owned by the state; and |
---|
125 | | - | (2) competitively procure the construction of the |
---|
126 | | - | connector described in Subdivision (1). |
---|
127 | | - | SECTION 8. Section 370.305(c), Transportation Code, is |
---|
| 94 | + | (7) a project listed under Section 370.3051. |
---|
| 95 | + | (b) This section expires August 31, 2029. |
---|
| 96 | + | SECTION 6. Section 370.305(c), Transportation Code, is |
---|
130 | | - | agreement only for specific projects authorized under this |
---|
131 | | - | subchapter [Except as provided by this chapter, an authority's |
---|
132 | | - | authority to enter into a comprehensive development agreement |
---|
133 | | - | expires on August 31, 2011]. |
---|
134 | | - | SECTION 9. Subchapter G, Chapter 370, Transportation Code, |
---|
| 99 | + | agreement only: |
---|
| 100 | + | (1) for specific projects authorized under this |
---|
| 101 | + | subchapter; or |
---|
| 102 | + | (2) as provided by Subchapter K [Except as provided by |
---|
| 103 | + | this chapter, an authority's authority to enter into a |
---|
| 104 | + | comprehensive development agreement expires on August 31, 2011]. |
---|
| 105 | + | SECTION 7. Subchapter G, Chapter 370, Transportation Code, |
---|
135 | 106 | | is amended by adding Section 370.3051 to read as follows: |
---|
136 | 107 | | Sec. 370.3051. AUTHORIZED PROJECTS FOR COMPREHENSIVE |
---|
137 | 108 | | DEVELOPMENT AGREEMENTS. (a) A regional mobility authority may |
---|
138 | 109 | | enter into a comprehensive development agreement for: |
---|
139 | 110 | | (1) the Interstate Highway 35 Northeast Expansion |
---|
140 | 111 | | project, from Loop 410 South in Bexar County to Farm-to-Market Road |
---|
141 | 112 | | 1103 in Comal County; |
---|
142 | 113 | | (2) the Loop 1604 project in Bexar County; |
---|
143 | 114 | | (3) the Outer Parkway project in Cameron County from |
---|
144 | 115 | | U.S. Highway 77 to Farm-to-Market Road 1847; |
---|
145 | 116 | | (4) the South Padre Island Second Access Causeway |
---|
146 | 117 | | project in Cameron County from State Highway 100 to Park Road 100; |
---|
147 | 118 | | (5) the Farm-to-Market 1925 project from U.S. Highway |
---|
148 | 119 | | 281 in Hidalgo County to U.S. Highway 77 in Cameron County; |
---|
149 | 120 | | (6) the Hidalgo County Loop project; |
---|
150 | 121 | | (7) the International Bridge Trade Corridor project in |
---|
151 | 122 | | Hidalgo County; |
---|