1 | 1 | | 88R3710 JXC-D |
---|
2 | 2 | | By: Reynolds H.B. No. 1146 |
---|
3 | 3 | | |
---|
4 | 4 | | |
---|
5 | 5 | | A BILL TO BE ENTITLED |
---|
6 | 6 | | AN ACT |
---|
7 | 7 | | relating to the interconnection of the ERCOT power grid to grids |
---|
8 | 8 | | outside the ERCOT power region. |
---|
9 | 9 | | BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
---|
10 | 10 | | SECTION 1. Subtitle B, Title 2, Utilities Code, is amended |
---|
11 | 11 | | by adding Chapter 39A to read as follows: |
---|
12 | 12 | | CHAPTER 39A. INTERCONNECTION OF FACILITIES IN ERCOT TO GRIDS |
---|
13 | 13 | | OUTSIDE ERCOT POWER REGION |
---|
14 | 14 | | Sec. 39A.0101. UTILITY AND COOPERATIVE AUTHORITY. |
---|
15 | 15 | | Notwithstanding any other law, a transmission and distribution |
---|
16 | 16 | | utility, municipally owned utility, or electric cooperative that |
---|
17 | 17 | | transmits or distributes power purchased at wholesale in the ERCOT |
---|
18 | 18 | | power region may construct, own, and operate facilities as |
---|
19 | 19 | | necessary to: |
---|
20 | 20 | | (1) access transmission service from outside of the |
---|
21 | 21 | | ERCOT power region; and |
---|
22 | 22 | | (2) purchase power at wholesale from outside of the |
---|
23 | 23 | | ERCOT power region. |
---|
24 | 24 | | Sec. 39A.0102. COMMISSION AUTHORITY. (a) The commission |
---|
25 | 25 | | may request any federal approval necessary for the interconnection |
---|
26 | 26 | | of a facility described by Section 39A.0101. |
---|
27 | 27 | | (b) Unless otherwise provided by federal law, the |
---|
28 | 28 | | commission shall require the independent organization certified |
---|
29 | 29 | | for the ERCOT power region under Section 39.151 to approve the |
---|
30 | 30 | | interconnection of a facility described by Section 39A.0101 unless |
---|
31 | 31 | | the commission or the independent organization determines that the |
---|
32 | 32 | | interconnection poses a significant and imminent risk to public |
---|
33 | 33 | | health and safety. |
---|
34 | 34 | | (c) The commission may provide technical and administrative |
---|
35 | 35 | | assistance to a transmission and distribution utility, municipally |
---|
36 | 36 | | owned utility, or electric cooperative seeking to construct, own, |
---|
37 | 37 | | or operate a facility described by Section 39A.0101. |
---|
38 | 38 | | Sec. 39A.0103. SYNCHRONOUS AND NON-SYNCHRONOUS |
---|
39 | 39 | | INTERCONNECTIONS. (a) This chapter applies to synchronous and |
---|
40 | 40 | | non-synchronous interconnections. |
---|
41 | 41 | | (b) Unless otherwise provided by federal law, the |
---|
42 | 42 | | commission shall approve an application for a certificate of |
---|
43 | 43 | | convenience and necessity submitted under Section 39A.0104 by a |
---|
44 | 44 | | transmission and distribution utility, municipally owned utility, |
---|
45 | 45 | | or electric cooperative for a facility that would synchronously |
---|
46 | 46 | | interconnect to a facility outside the ERCOT power region if the |
---|
47 | 47 | | application complies with all applicable provisions of Chapter 37 |
---|
48 | 48 | | and this chapter. |
---|
49 | 49 | | (c) Not later than September 1, 2025, the commission shall |
---|
50 | 50 | | identify transmission facilities in ERCOT that may be synchronously |
---|
51 | 51 | | interconnected with transmission facilities outside of ERCOT for |
---|
52 | 52 | | the purpose of allowing federal regulation of transmission service |
---|
53 | 53 | | and wholesale power sales in ERCOT. Notwithstanding any other law, |
---|
54 | 54 | | the commission shall require a transmission and distribution |
---|
55 | 55 | | utility, municipally owned utility, or electric cooperative that |
---|
56 | 56 | | owns a transmission facility identified by the commission to make |
---|
57 | 57 | | requests, obtain approvals, enter into contracts, and construct |
---|
58 | 58 | | facilities as necessary to synchronously interconnect the facility |
---|
59 | 59 | | with a transmission facility outside of ERCOT. This subsection |
---|
60 | 60 | | expires August 31, 2029. |
---|
61 | 61 | | SECTION 2. Sections 37.051(c-1), (c-2), and (c-3), |
---|
62 | 62 | | Utilities Code, are redesignated as Section 39A.0104, Utilities |
---|
63 | 63 | | Code, and amended to read as follows: |
---|
64 | 64 | | Sec. 39A.0104. CERTIFICATES OF CONVENIENCE AND NECESSITY. |
---|
65 | 65 | | (a) A transmission and distribution utility, [(c-1) |
---|
66 | 66 | | Notwithstanding any other provision of this title except Section |
---|
67 | 67 | | 11.009, and except as provided by Subsection (c-2), a person, |
---|
68 | 68 | | including an electric utility or] municipally owned utility, or |
---|
69 | 69 | | electric cooperative may not interconnect a facility described by |
---|
70 | 70 | | Section 39A.0101 [to the ERCOT transmission grid that enables |
---|
71 | 71 | | additional power to be imported into or exported out of the ERCOT |
---|
72 | 72 | | power grid] unless the utility or cooperative [person] obtains a |
---|
73 | 73 | | certificate from the commission in the manner provided by Chapter |
---|
74 | 74 | | 37 and this chapter stating that the interconnection does not pose a |
---|
75 | 75 | | significant and imminent risk to public health and safety [public |
---|
76 | 76 | | convenience and necessity requires or will require the |
---|
77 | 77 | | interconnection]. |
---|
78 | 78 | | (b) In the case of a conflict between Chapter 37 and this |
---|
79 | 79 | | chapter, this chapter prevails. |
---|
80 | 80 | | (c) Sections 37.056(c)(1) and (2) and (d) do not apply to an |
---|
81 | 81 | | application for a certificate described by Subsection (a). |
---|
82 | 82 | | (d) Unless otherwise provided by federal law, the |
---|
83 | 83 | | commission shall approve an application for a certificate described |
---|
84 | 84 | | by Subsection (a) unless the commission determines that granting |
---|
85 | 85 | | the application poses a significant and imminent risk to public |
---|
86 | 86 | | health and safety. |
---|
87 | 87 | | (e) The transmission and distribution utility, municipally |
---|
88 | 88 | | owned utility, or electric cooperative [person] must apply to the |
---|
89 | 89 | | commission for a [the] certificate described by Subsection (a) not |
---|
90 | 90 | | later than the 180th day before the date the utility or cooperative |
---|
91 | 91 | | [person] seeks any order from the Federal Energy Regulatory |
---|
92 | 92 | | Commission related to the interconnection. |
---|
93 | 93 | | (f) [The commission shall apply Section 37.056 in |
---|
94 | 94 | | considering an application under this subsection. In addition, the |
---|
95 | 95 | | commission must determine that the application is consistent with |
---|
96 | 96 | | the public interest before granting the certificate. The commission |
---|
97 | 97 | | may adopt rules necessary to implement this subsection. This |
---|
98 | 98 | | subsection does not apply to a facility that is in service on |
---|
99 | 99 | | December 31, 2014. |
---|
100 | 100 | | [(c-2)] The commission, not later than the 185th day after |
---|
101 | 101 | | the date the application is filed, shall approve an application |
---|
102 | 102 | | [filed under Subsection (c-1)] for a facility that is to be |
---|
103 | 103 | | constructed under an interconnection agreement appended to an offer |
---|
104 | 104 | | of settlement approved in a final order of the Federal Energy |
---|
105 | 105 | | Regulatory Commission that was issued in Docket No. TX11-01-001 on |
---|
106 | 106 | | or before December 31, 2014, directing physical connection between |
---|
107 | 107 | | the ERCOT and SERC regions under Sections 210, 211, and 212 of the |
---|
108 | 108 | | Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In |
---|
109 | 109 | | approving the application, the commission may prescribe reasonable |
---|
110 | 110 | | conditions to protect the public interest that are consistent with |
---|
111 | 111 | | the final order of the Federal Energy Regulatory Commission. |
---|
112 | 112 | | (g) [(c-3)] Nothing in this section [Subsection (c-1) or |
---|
113 | 113 | | (c-2)] is intended to restrict the authority of the commission or |
---|
114 | 114 | | the independent organization certified under Section 39.151 for the |
---|
115 | 115 | | ERCOT power region to adopt rules or protocols of general |
---|
116 | 116 | | applicability. |
---|
117 | 117 | | SECTION 3. This Act takes effect September 1, 2023. |
---|