Texas 2023 - 88th Regular

Texas House Bill HB1146 Latest Draft

Bill / Introduced Version Filed 12/29/2022

Download
.pdf .doc .html
                            88R3710 JXC-D
 By: Reynolds H.B. No. 1146


 A BILL TO BE ENTITLED
 AN ACT
 relating to the interconnection of the ERCOT power grid to grids
 outside the ERCOT power region.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Subtitle B, Title 2, Utilities Code, is amended
 by adding Chapter 39A to read as follows:
 CHAPTER 39A. INTERCONNECTION OF FACILITIES IN ERCOT TO GRIDS
 OUTSIDE ERCOT POWER REGION
 Sec. 39A.0101.  UTILITY AND COOPERATIVE AUTHORITY.
 Notwithstanding any other law, a transmission and distribution
 utility, municipally owned utility, or electric cooperative that
 transmits or distributes power purchased at wholesale in the ERCOT
 power region may construct, own, and operate facilities as
 necessary to:
 (1)  access transmission service from outside of the
 ERCOT power region; and
 (2)  purchase power at wholesale from outside of the
 ERCOT power region.
 Sec. 39A.0102.  COMMISSION AUTHORITY. (a) The commission
 may request any federal approval necessary for the interconnection
 of a facility described by Section 39A.0101.
 (b)  Unless otherwise provided by federal law, the
 commission shall require the independent organization certified
 for the ERCOT power region under Section 39.151 to approve the
 interconnection of a facility described by Section 39A.0101 unless
 the commission or the independent organization determines that the
 interconnection poses a significant and imminent risk to public
 health and safety.
 (c)  The commission may provide technical and administrative
 assistance to a transmission and distribution utility, municipally
 owned utility, or electric cooperative seeking to construct, own,
 or operate a facility described by Section 39A.0101.
 Sec. 39A.0103.  SYNCHRONOUS AND NON-SYNCHRONOUS
 INTERCONNECTIONS. (a) This chapter applies to synchronous and
 non-synchronous interconnections.
 (b)  Unless otherwise provided by federal law, the
 commission shall approve an application for a certificate of
 convenience and necessity submitted under Section 39A.0104 by a
 transmission and distribution utility, municipally owned utility,
 or electric cooperative for a facility that would synchronously
 interconnect to a facility outside the ERCOT power region if the
 application complies with all applicable provisions of Chapter 37
 and this chapter.
 (c)  Not later than September 1, 2025, the commission shall
 identify transmission facilities in ERCOT that may be synchronously
 interconnected with transmission facilities outside of ERCOT for
 the purpose of allowing federal regulation of transmission service
 and wholesale power sales in ERCOT. Notwithstanding any other law,
 the commission shall require a transmission and distribution
 utility, municipally owned utility, or electric cooperative that
 owns a transmission facility identified by the commission to make
 requests, obtain approvals, enter into contracts, and construct
 facilities as necessary to synchronously interconnect the facility
 with a transmission facility outside of ERCOT. This subsection
 expires August 31, 2029.
 SECTION 2.  Sections 37.051(c-1), (c-2), and (c-3),
 Utilities Code, are redesignated as Section 39A.0104, Utilities
 Code, and amended to read as follows:
 Sec. 39A.0104.  CERTIFICATES OF CONVENIENCE AND NECESSITY.
 (a) A transmission and distribution utility, [(c-1)
 Notwithstanding any other provision of this title except Section
 11.009, and except as provided by Subsection (c-2), a person,
 including an electric utility or] municipally owned utility, or
 electric cooperative may not interconnect a facility described by
 Section 39A.0101 [to the ERCOT transmission grid that enables
 additional power to be imported into or exported out of the ERCOT
 power grid] unless the utility or cooperative [person] obtains a
 certificate from the commission in the manner provided by Chapter
 37 and this chapter stating that the interconnection does not pose a
 significant and imminent risk to public health and safety [public
 convenience and necessity requires or will require the
 interconnection].
 (b)  In the case of a conflict between Chapter 37 and this
 chapter, this chapter prevails.
 (c)  Sections 37.056(c)(1) and (2) and (d) do not apply to an
 application for a certificate described by Subsection (a).
 (d)  Unless otherwise provided by federal law, the
 commission shall approve an application for a certificate described
 by Subsection (a) unless the commission determines that granting
 the application poses a significant and imminent risk to public
 health and safety.
 (e)  The transmission and distribution utility, municipally
 owned utility, or electric cooperative [person] must apply to the
 commission for a [the] certificate described by Subsection (a) not
 later than the 180th day before the date the utility or cooperative
 [person] seeks any order from the Federal Energy Regulatory
 Commission related to the interconnection.
 (f) [The commission shall apply Section 37.056 in
 considering an application under this subsection. In addition, the
 commission must determine that the application is consistent with
 the public interest before granting the certificate. The commission
 may adopt rules necessary to implement this subsection. This
 subsection does not apply to a facility that is in service on
 December 31, 2014.
 [(c-2)] The commission, not later than the 185th day after
 the date the application is filed, shall approve an application
 [filed under Subsection (c-1)] for a facility that is to be
 constructed under an interconnection agreement appended to an offer
 of settlement approved in a final order of the Federal Energy
 Regulatory Commission that was issued in Docket No. TX11-01-001 on
 or before December 31, 2014, directing physical connection between
 the ERCOT and SERC regions under Sections 210, 211, and 212 of the
 Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In
 approving the application, the commission may prescribe reasonable
 conditions to protect the public interest that are consistent with
 the final order of the Federal Energy Regulatory Commission.
 (g) [(c-3)] Nothing in this section [Subsection (c-1) or
 (c-2)] is intended to restrict the authority of the commission or
 the independent organization certified under Section 39.151 for the
 ERCOT power region to adopt rules or protocols of general
 applicability.
 SECTION 3.  This Act takes effect September 1, 2023.