Texas 2023 - 88th Regular

Texas House Bill HB2848 Latest Draft

Bill / House Committee Report Version Filed 04/24/2023

Download
.pdf .doc .html
                            88R22860 DIO-F
 By: Darby, Guillen, Hernandez, Slawson, H.B. No. 2848
 Burrows
 Substitute the following for H.B. No. 2848:
 By:  Smithee C.S.H.B. No. 2848


 A BILL TO BE ENTITLED
 AN ACT
 relating to the approval of a certificate of public convenience and
 necessity for certain transmission projects.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Section 37.056, Utilities Code, is amended by
 amending Subsections (c-1) and (d) and adding Subsections (d-1) and
 (d-2) to read as follows:
 (c-1)  In considering the need for additional service under
 Subsection (c)(2) for a reliability transmission project that
 serves the ERCOT power region, the commission must consider the
 historical load, forecasted load growth, and additional load
 currently seeking interconnection, including load for which the
 electric utility has yet to sign an interconnection agreement, as
 determined by the electric utility with the responsibility for
 serving the load.
 (d)  The commission by rule shall establish criteria, in
 addition to the criteria described by Subsection (c), for granting
 a certificate for a transmission project that serves the ERCOT
 power region, that is not necessary to meet state or federal
 reliability standards, and that is not included in a plan developed
 under Section 39.904(g).  [The criteria must include a comparison
 of the estimated cost of the transmission project for consumers and
 the estimated congestion cost savings for consumers that may result
 from the transmission project, considering both current and future
 expected congestion levels and the transmission project's ability
 to reduce those congestion levels.] The commission shall include
 with its decision on an application for a certificate to which this
 subsection applies findings on the criteria. The criteria must:
 (1)  include a comparison of the estimated cost of the
 transmission project to consumers and the estimated congestion cost
 savings for consumers that may result from the project, considering
 both current and expected congestion levels and the project's
 ability to reduce those levels;
 (2)  address:
 (A)  other benefits of the transmission project,
 including deferral of reliability upgrade costs, reduction of
 transmission system losses, and reduction of operating reserve
 costs;
 (B)  solutions to relieve generic transmission
 constraints;
 (C)  potential for increasing transmission system
 reliability, resiliency, and operational flexibility;
 (D)  potential for minimizing outage moratoria
 and transmission system congestion by employing planning criteria
 that include contingencies for a planned outage followed by an
 unplanned outage under peak conditions; and
 (E)  the operational benefits and reduced impacts
 on affected landowners of constructing new transmission lines
 operating at or below 345 kilovolts as double circuit capable
 lines;
 (3)  evaluate:
 (A)  the costs of the transmission project on a
 levelized basis over the life of the project; and
 (B)  the benefits of the transmission project on a
 levelized basis over the life of the project or the longest period
 determined to be reasonable by the commission; and
 (4)  in high growth areas and areas experiencing or
 expected to experience rapid growth in power demand, including
 coastal regions, oil and gas producing, processing, or refining
 regions, and semiconductor manufacturing regions, prioritize the
 development of additional and sufficient transmission capacity to
 provide flexibility to serve new load.
 (d-1)  For a transmission project described by Subsection
 (d), the commission shall require all new transmission lines
 operating at or below 345 kilovolts to be constructed as double
 circuit capable lines unless the electric utility requests an
 exception.
 (d-2)  For a transmission project described by Subsection
 (d)(4), the applicant for the transmission project certificate
 shall submit a copy of the application to the independent
 organization certified under Section 39.151 for the ERCOT power
 region.  The independent organization shall review and provide the
 commission with the organization's recommendations regarding the
 application not later than the 90th day after the date the
 application is received.  If the organization fails to provide the
 commission with its recommendations before the 91st day after the
 date the application is received, the commission shall consider the
 transmission project to be a project that meets the need for
 additional service under this section.
 SECTION 2.  Section 37.057, Utilities Code, is amended to
 read as follows:
 Sec. 37.057.  DEADLINE FOR APPLICATION FOR NEW TRANSMISSION
 FACILITY. The commission must approve or deny an application for a
 certificate for a new transmission facility not later than the
 181st day after [the first anniversary of] the date the application
 is filed. If the commission does not approve or deny the
 application on or before that date, a party may seek a writ of
 mandamus in a district court of Travis County to compel the
 commission to decide on the application.
 SECTION 3.  The changes in law made by this Act apply only to
 a proceeding affecting a certificate of public convenience and
 necessity that commences on or after the effective date of this Act.
 A proceeding affecting a certificate of public convenience and
 necessity that commenced before the effective date of this Act is
 governed by the law in effect on the date the proceeding is
 commenced, and that law is continued in effect for that purpose.
 SECTION 4.  This Act takes effect immediately if it receives
 a vote of two-thirds of all the members elected to each house, as
 provided by Section 39, Article III, Texas Constitution.  If this
 Act does not receive the vote necessary for immediate effect, this
 Act takes effect September 1, 2023.