 AN ACT
 relating to the use of geothermal energy as a dispatchable
 generation resource.
 BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
 SECTION 1.  Subchapter A, Chapter 34, Utilities Code, is
 amended by adding Section 34.01015 to read as follows:
 Sec. 34.01015.  APPLICABILITY. For the purposes of this
 chapter:
 (1)  a generating facility is considered to be
 dispatchable if the facility's output can be controlled primarily
 by forces under human control; and
 (2)  a geothermal energy generation facility is
 considered to be dispatchable.
 SECTION 2.  Section 34.0104, Utilities Code, is amended by
 amending Subsection (a) and adding Subsection (a-1) to read as
 follows:
 (a)  The commission may use money in the fund without further
 appropriation to provide loans to finance upgrades to existing
 dispatchable electric generating facilities providing power for
 the ERCOT power region that result in a net increase of at least 100
 megawatts of capacity for each facility or the construction of
 dispatchable electric generating facilities providing power for
 the ERCOT power region that each have a generation capacity of at
 least 100 megawatts.  [For the purposes of this section, a
 generating facility is considered to be dispatchable if the
 facility's output can be controlled primarily by forces under human
 control.] An electric energy storage facility, other than a
 geothermal energy conservation well, is not eligible for a loan
 under this section.
 (a-1)  Notwithstanding Subsections (a) and (b)(1), the
 commission may use money in the fund, without further
 appropriation, to provide loans to finance the construction of
 geothermal energy generation facilities and geothermal energy
 conservation wells in the ERCOT power region that have a generation
 capacity of at least 10 megawatts.
 SECTION 3.  Sections 34.0105(a) and (c), Utilities Code, are
 amended to read as follows:
 (a)  The commission shall provide, using money available in
 the fund for the purpose without further appropriation, a
 completion bonus grant for the construction of dispatchable
 electric generating facilities in the ERCOT power region.  [For the
 purposes of this section, a generating facility is considered to be
 dispatchable if the facility's output can be controlled primarily
 by forces under human control.]  An electric energy storage
 facility, other than a geothermal energy conservation well, is not
 eligible for a grant under this section.
 (c)  The commission may provide a grant under this section
 only for construction of a facility that:
 (1)  will have a generation capacity of at least 100
 megawatts or at least 10 megawatts for a geothermal energy
 generation facility or geothermal energy conservation well; and
 (2)  does not meet the planning model requirements
 necessary to be included in the Capacity Demand and Reserves Report
 of the independent organization certified under Section 39.151 for
 the ERCOT power region before June 1, 2023.
 SECTION 4.  Section 39.159(a), Utilities Code, is amended to
 read as follows:
 (a)  For the purposes of this section:
 (1)[,] a generation facility is considered to be
 dispatchable if the facility's output can be controlled primarily
 by forces under human control; and
 (2)  a geothermal energy generation facility and a
 geothermal energy conservation well are considered to be
 dispatchable [non-dispatchable if the facility's output is
 controlled primarily by forces outside of human control].
 SECTION 5.  This Act takes effect September 1, 2025.