Virginia 2026 Regular Session

Virginia Senate Bill SB497

Introduced
1/13/26  
Refer
1/13/26  
Report Pass
2/12/26  
Engrossed
2/16/26  
Refer
2/19/26  
Report Pass
2/24/26  
Enrolled
3/4/26  
Chaptered
3/31/26  

Caption

Transmission lines, certain; Department of Transportation to identify opportunities for siting.

Impact

If enacted, SB497 will direct the Department of Transportation to convene a work group composed of various stakeholders, including the State Corporation Commission and the Virginia Utility Coordinating Committee. This work group is tasked with identifying opportunities and developing recommendations to streamline regulations and permitting processes that facilitate the expedient and efficient siting of new electrical transmission infrastructure within existing state highway rights-of-way. The bill aims to create a more efficient framework for infrastructure development that balances the needs for power accessibility and environmental protection.

Summary

SB497 aims to improve the siting of new electric transmission facilities, particularly high-voltage transmission lines, by prioritizing the use of existing linear infrastructure corridors, such as utility and highway corridors, over the establishment of new corridors. The bill reflects a policy direction by the Commonwealth of Virginia to ensure that infrastructural developments are consistent with economic and engineering considerations, reliability of the electric grid, and protection of cultural, historical, and environmental resources. By focusing on existing corridors, the bill seeks to streamline the regulatory process for new electric infrastructure developments.

Sentiment

The overall sentiment surrounding SB497 appears to be positive, with a strong emphasis on collaboration between state agencies and stakeholders to optimize the siting of electrical transmission lines. The bill is viewed favorably by proponents who recognize the importance of modernizing the electrical grid and enhancing energy transmission capabilities while minimizing additional disruptions to the environment. However, there may be some concerns among environmental advocates who will be watching closely to ensure that the prioritization of existing corridors does not compromise protections for cultural and environmental resources.

Contention

While SB497 seeks to streamline the process for siting electric transmission facilities, there may be points of contention regarding the balance between development and environmental stewardship. Stakeholders may express concerns regarding how prioritizing existing corridors could impact local ecosystems, particularly if such corridors cross through sensitive areas. Additionally, the effectiveness of the proposed work group in addressing regulatory barriers and the quality of recommendations produced will be crucial in determining the success of this bill in practice.

Companion Bills

No companion bills found.

Previously Filed As

VA HB2386

Public utilities; certificate of convenience and necessity for certain new transmission lines.

VA SB1049

Electric utilities; approval required for construction of certain electrical transmission lines.

VA HB1822

Electric utilities; construction of certain electrical transmission lines, advanced conductors.

VA HB2755

Underground transmission lines; qualifying projects.

VA SB1358

Underground transmission lines; qualifying projects.

VA SB1022

State Corporation Commission; time frame for completion of certain transmission lines proceedings.

VA HB2470

Electric utilities; construction of certain transmission lines, notice required.

VA SB708

Underground transmission lines; qualifying projects, pilot program.

VA HB2648

State Corporation Commission; time frame for completion of certain transmission lines proceedings.

VA SB1190

Solar photovoltaic projects; siting, decisions of localities, etc.

Similar Bills

No similar bills found.